Tethyan Copper Company Pty Limited v. Islamic Republic of Pakistan

CourtDistrict Court, District of Columbia
DecidedMarch 10, 2022
DocketCivil Action No. 2019-2424
StatusPublished

This text of Tethyan Copper Company Pty Limited v. Islamic Republic of Pakistan (Tethyan Copper Company Pty Limited v. Islamic Republic of Pakistan) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tethyan Copper Company Pty Limited v. Islamic Republic of Pakistan, (D.D.C. 2022).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

TETHYAN COPPER COMPANY PTY LIMITED,

Plaintiff, Case No. 1:19-cv-02424 (TNM) v.

ISLAMIC REPUBLIC OF PAKISTAN,

Defendant.

MEMORANDUM OPINION

Since 1966, Congress has required federal courts to grant full faith and credit to arbitral

awards from the International Centre for Settlement of Investment Disputes (ICSID). See 22

U.S.C. § 1650a(a). This case involves the intersection of that mandate with the standards for

waiver of sovereign immunity by foreign states.

In 2019, ICSID issued a $6 billion award against the Government of Pakistan. The award

arose out of a long dispute between Pakistan and Tethyan Copper Company, an Australian

mining company. Tethyan had submitted the dispute to ICSID arbitration according to the terms

of a bilateral investment treaty signed in 1998 between Pakistan and Australia. Pakistan argued

that ICSID did not have jurisdiction over the dispute. A tribunal disagreed and issued its award

against Pakistan. Tethyan then petitioned this Court to recognize and enforce the award.

Pakistan essentially appealed the award at ICSID, seeking a wholesale annulment of the

award or a modification of it. Those actions triggered automatic provisional stays of

enforcement, all of which the Court applied to these proceedings. But those stays have all

expired. Now, two years after Tethyan filed its petition—and over a decade after Tethyan

commenced arbitration—Pakistan asks the Court to stay proceedings or, in the alternative, to dismiss the petition entirely. Because Pakistan has not shown its entitlement to a stay and D.C.

Circuit precedent demands deference to arbitrability determinations by ICSID, the Court will

deny both requests.

I.

This well-tenured dispute began in 2006, when Tethyan entered a joint venture with a

Pakistani province, Balochistan. See Petition ¶ 7, ECF No. 1 (Pet.). Under that agreement,

Tethyan could “explore potential copper and gold mining” in the province. Id. In 2011, Tethyan

applied to Balochistan for a lease to mine the Reko Diq deposit, located in the province’s

northwest. See id. Despite the joint venture, Balochistan denied the application. See id. That

decision triggered events that ultimately landed the dispute here.

Nine months after the application denial, Tethyan referred the dispute to ICSID. See id.

¶ 11. That body was formed by the ICSID Convention, a multilateral agreement signed by 164

nations—including Australia, Pakistan, and the United States—that provides a framework for

arbitrating investment disputes between contracting states and nationals of other contracting

states and for recognition of any resulting awards. See ICSID Convention, pmbl., Pet. Ex. 2,

ECF No. 1-2. Tethyan made the referral under a bilateral investment treaty between Australia

and Pakistan (Treaty). 1 The Treaty provides that when a signatory nation and an investor of the

other nation cannot resolve a dispute among themselves, “either party to the dispute

may . . . refer the dispute to [ICSID].” Treaty, art. 13(2)(b). ICSID convened a Tribunal in 2012

to arbitrate. See Pet. ¶ 12.

The Tribunal took its time. Over four years, it conducted 32 days of hearings. See id.

¶ 13. Finally, in November 2017, the Tribunal issued a Decision on Jurisdiction and Liability.

1 The full text of this treaty is attached to the Petition. See Pet. Ex. 3, ECF No. 1-3.

2 See Rozen Decl., Ex. B at 635–1020, ECF No. 1-1 (J&L). 2 The Tribunal first decided, over

Pakistan’s objections, that it had jurisdiction to hear Tethyan’s claims. See id. ¶ 688. Next, it

held that Tethyan had a legitimate expectation that Balochistan would approve the mining

application and that Tethyan had relied on that expectation. See id. ¶ 958. Balochistan rejected

the application on pretextual grounds so that Balochistan could start its own mining project using

Tethyan’s hard work. See id. ¶ 1264. Pakistan thus, through one of its provincial governments,

had expropriated the value of Tethyan’s investment, thereby violating multiple provisions of the

Treaty. See id. ¶ 1449. Tethyan was entitled to “all damages and losses resulting from”

Pakistan’s breaches. Id.

In July 2019, the Tribunal issued its damages determination. See Rozen Decl., Ex. A at

5–633, ECF No. 1-1 (Award). The Tribunal directed Pakistan to pay $4.087 billion in

compensation, pre-award interest dating from the start of arbitration proceedings, $2.53 million

in arbitration costs, $59.4 million in Tethyan’s legal costs, and post-award interest compounded

annually. See id. ¶ 1858. All told, the Award totals about $6 billion. See Mot. to Stay at 10,

ECF No. 34 (Mot.).

One month later, Tethyan petitioned this Court to enter an order confirming the Award

and to enter judgment in the specified amounts. See Pet. From there, this case devolved into

several contemporaneous stays. In November 2019, Pakistan applied to ICSID to annul the

award. See Conlon Decl., Ex. A, ECF No. 34-3. As required by ICSID rules, that application

triggered a provisional stay of enforcement. See Conlon Decl., Ex. E at 3, ECF No. 34-7. The

Court likewise stayed its own proceedings. See Hr’g Tr. at 6, ECF No. 30.

2 All page citations refer to the pagination generated by the Court’s CM/ECF system. For the ICSID’s decisional documents, the Court gives the page numbers now for the entire document but throughout this Opinion will cite to paragraph numbers used in those documents.

3 Seven months later, the Annulment Committee concluded that it would maintain a stay

under certain conditions. The Committee required Pakistan to (1) provide a letter of credit for

25% of the Award and (2) submit a letter from the nation’s Minister of Finance promising that, if

the Committee did not annul the Award, Pakistan would recognize it, pay it within 120 days, and

not interfere in Pakistani courts with any amount recovered by Tethyan. See Joint Status Report

at 2, ECF No. 31. If Pakistan did not comply with these requirements, the Committee would lift

the provisional stay of enforcement against half of the Award. See id. at 2–3. For Tethyan to

execute on that half, however, the Committee required Tethyan to promise that it would place

any collected amounts into an escrow account controlled by an international escrow agent. See

id. at 3.

Pakistan did not comply with the Committee’s conditions, so in October 2020 the

Committee lifted the stay for half of the Award. See Joint Status Report at 2, ECF No. 33. The

Court likewise lifted its own stay. See Min. Order, Nov. 9, 2020.

Pakistan then moved to stay proceedings here until the Annulment Committee finishes its

work. In the alternative, Pakistan moved to dismiss Tethyan’s Petition. See Mot. That motion

became ripe in early 2021. Before the Court could rule, however, Pakistan filed another

application with ICSID, this time to revise the Award. 3 See Joint Status Report at 1, ECF No.

3 One might think that ICSID annulment and revision proceedings are the same. Indeed, Pakistan’s revision and annulment applications seek the same outcome—a declaration that Tethyan is not entitled to damages. See Amdt. to Renewed Motion to Stay at 7, ECF No. 46-1 (Renewed Mot.). But the proceedings differ in bases and bodies. A party may request revision based only on previously unknown facts that are “of such a nature as decisively to affect the award.” ICSID Convention art. 51(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Durfee v. Duke
375 U.S. 106 (Supreme Court, 1963)
Argentine Republic v. Amerada Hess Shipping Corp.
488 U.S. 428 (Supreme Court, 1989)
State Farm Mutual Automobile Insurance v. Campbell
538 U.S. 408 (Supreme Court, 2003)
Europcar Italia, S.P.A. v. Maiellano Tours, Inc.
156 F.3d 310 (Second Circuit, 1998)
Ned Chartering & Trading, Inc. v. Republic of Pakistan
130 F. Supp. 2d 64 (District of Columbia, 2001)
Chevron Corporation v. Republic of Ecuador
949 F. Supp. 2d 57 (District of Columbia, 2013)
Nasrin Mohammadi v. Islamic Republic of Iran
782 F.3d 9 (D.C. Circuit, 2015)
Chevron Corporation v. The Republic of Ecuador
795 F.3d 200 (D.C. Circuit, 2015)
Foster v. Chatman
578 U.S. 488 (Supreme Court, 2016)
Hulley Enterprises Ltd. v. Russian Federation
211 F. Supp. 3d 269 (District of Columbia, 2016)
Henry Schein, Inc. v. Archer & White Sales, Inc.
586 U.S. 63 (Supreme Court, 2019)
LLC SPC Stileks v. Republic of Moldova
985 F.3d 871 (D.C. Circuit, 2021)
In re Sealed
932 F.3d 915 (D.C. Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Tethyan Copper Company Pty Limited v. Islamic Republic of Pakistan, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tethyan-copper-company-pty-limited-v-islamic-republic-of-pakistan-dcd-2022.