Tennessee Gas Pipeline Company v. Technip USA Corporation and Technip

CourtCourt of Appeals of Texas
DecidedAugust 21, 2008
Docket01-06-00535-CV
StatusPublished

This text of Tennessee Gas Pipeline Company v. Technip USA Corporation and Technip (Tennessee Gas Pipeline Company v. Technip USA Corporation and Technip) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Company v. Technip USA Corporation and Technip, (Tex. Ct. App. 2008).

Opinion

Opinion issued August 21, 2008






In The

Court of Appeals

For The

First District of Texas





NO. 01-06-00535-CV





TENNESSEE GAS PIPELINE COMPANY, Appellant


V.


TECHNIP USA CORPORATION AND TECHNIP, S.A., Appellees


* * *


TECHNIP USA CORPORATION AND TECHNIP, S.A., Appellants



TENNESSEE GAS PIPELINE COMPANY, Appellee





On Appeal from the 165th District Court

Harris County, Texas

Trial Court Cause No. 2002-60134





MEMORANDUM OPINION ON REHEARING


          This is a breach of contract dispute brought by Tennessee Gas Pipeline Company (“TGP”) against Technip USA Corporation (“Technip USA”) and its parent, Technip S.A. (collectively, “Technip”). TGP engaged Technip USA to construct improvements along an interstate gas pipeline owned by TGP pursuant to a “Lump Sum Turnkey, Engineering, Procurement and Construction Contract” (“Contract”). After project delays occurred, TGP sued Technip to recoup its additional expenses and for allegedly defective work. Technip counterclaimed to recover sums owed under the Contract. A jury found that Technip had breached the Contract and awarded delay damages and defective work damages to TGP. Subsequently, on the motion of Technip, the trial court limited the jury award to certain defective-work damages. Both TGP and Technip have appealed. TGP seeks the total jury award; Technip seeks a holding that TGP take nothing on its claims.

          In its appeal, TGP contends that the trial court erred by denying its Motion for Judgment and by granting Technip USA’s Motions for Summary Judgment Regarding TGP’s damages, Technip’s Motion to Disregard the Jury Findings, and Technip’s Motion for Entry of Judgment Notwithstanding the Verdict because (1) the total damages awarded by the jury constitute “direct damages” to which TGP is entitled as a matter of law; (2) the evidence is legally sufficient to support the jury’s finding of damages; and (3) Technip S.A. was required, pursuant to the guaranty it executed, to pay all damages arising from Technip USA’s breach of the Contract without limitation.

          In its appeal, Technip contends that the trial court erroneously denied its Motion for Judgment Notwithstanding the Verdict on TGP’s defective workmanship claims because (1) such claims are barred by the exclusive remedy provisions of the agreement; (2) the evidence is insufficient to support the damages awarded on certain defective work claims; and (3) the trial court improperly applied the stipulated retainage offset and improperly calculated interest and attorney’s fees.

          On December 21, 2007, we reversed and rendered, in part, and affirmed as modified, in part, the judgment of the trial court in this case. TGP moved for rehearing. We grant the motion, withdraw the opinion dated December 21, 2007, and issue this opinion in its stead. Our disposition and judgment remain unchanged.

          We reverse and render, in part, and affirm as modified, in part.

FACTS AND PROCEDURAL HISTORY

          TGP owns and operates 14,200 miles of pipeline through which it transports 6.4 billion cubic feet of gas each day from Texas to the northeastern United States. Technip USA is an engineering and construction contractor in the oil and gas industry. TGP and Technip USA have conducted business with one another since the 1960s.

          On August 6, 1999, TGP contracted with Technip USA for the replacement and upgrade of six compressors on one of TGP’s main transmission lines, known as the “TGP 100 Line Horsepower Replacement Project” (“Project”), for a “lump sum, fixed amount” of $86,740,000 (“Contract Price”). Work on the Project commenced immediately. TGP expected the Project to be completed within 17 months. Technip contends that the schedule for completion was never formally finalized. Completion of the Project took three years.

          The Agreement

          The progress and completion of the Project was formally governed by Article 5.2 of the Contract, which provides as follows, in pertinent part:

Project Schedule; Critical Path Schedule. [Technip USA] shall perform the Work [its duties and obligations] in accordance with the schedule and management plan set forth in Exhibit E (the “Project Schedule”). Within twenty (20) days after the Effective Date, [Technip USA] shall submit, for [TPG’s] review and approval, a critical path method (“CPM”) schedule which conforms to the Project Schedule and which sets forth the timing of all elements of the Work and the interrelationship of such elements.

It is undisputed that there was never a Project Schedule “set forth in Exhibit E” of the Contract, as contemplated by Article 5.2.

          According to TGP, contemporaneous with the formation of the Contract, a Project Schedule was formulated and was circulated at a meeting involving both parties. The Project Schedule specified that Technip USA would complete the project within 17 months of execution of the Contract. In addition, according to TGP, a CPM schedule was created, also specifying that Technip USA would complete the Project within 17 months. TGP contends that it remained in constant communication with Technip USA and that all parties understood that the Project Schedule governed the project. In addition, contends TGP, the Project Schedule was incorporated into the Contract through Article 19.13, which provides that “[a]ll Exhibits, Schedules or other attachments referenced in this Agreement shall be incorporated into this Agreement by such reference and shall be deemed to be an integral part of this Agreement.”

          Article 5.2A of the Contract also provides that “[m]odifications to the critical path of the Project Schedule shall only be made with the approval of [TGP]” and that “[t]he Project Schedule shall be revised as required under Section 6.5.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Pringle v. Moon
158 S.W.3d 607 (Court of Appeals of Texas, 2005)
Continental Holdings, Ltd. v. Leahy
132 S.W.3d 471 (Court of Appeals of Texas, 2003)
Williams v. Briscoe
137 S.W.3d 120 (Court of Appeals of Texas, 2004)
Brown v. Bank of Galveston, National Ass'n
963 S.W.2d 511 (Texas Supreme Court, 1998)
Western Bank-Downtown v. Carline
757 S.W.2d 111 (Court of Appeals of Texas, 1988)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Phillips v. Phillips
820 S.W.2d 785 (Texas Supreme Court, 1992)
Allied Vista, Inc. v. Holt
987 S.W.2d 138 (Court of Appeals of Texas, 1999)
Transcontinental Gas Pipeline Corp. v. Texaco, Inc.
35 S.W.3d 658 (Court of Appeals of Texas, 2001)
Frost Nat. Bank v. Heafner
12 S.W.3d 104 (Court of Appeals of Texas, 2000)
Tiller v. McLure
121 S.W.3d 709 (Texas Supreme Court, 2003)
Clark v. Walker-Kurth Lumber Co.
689 S.W.2d 275 (Court of Appeals of Texas, 1985)
Tacon Mech. Contractors v. Grant Sheet Metal, Inc.
889 S.W.2d 666 (Court of Appeals of Texas, 1994)
Houston Lighting & Power Co. v. City of Wharton
101 S.W.3d 633 (Court of Appeals of Texas, 2003)
Wade & Sons, Inc. v. American Standard, Inc.
127 S.W.3d 814 (Court of Appeals of Texas, 2003)
Centex Corp. v. Dalton
840 S.W.2d 952 (Texas Supreme Court, 1992)
Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.
930 S.W.2d 877 (Court of Appeals of Texas, 1996)
Hedley Feedlot, Inc. v. Weatherly Trust
855 S.W.2d 826 (Court of Appeals of Texas, 1993)
GT & MC, INC. v. Texas City Refining, Inc.
822 S.W.2d 252 (Court of Appeals of Texas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Tennessee Gas Pipeline Company v. Technip USA Corporation and Technip, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-company-v-technip-usa-corpo-texapp-2008.