Wade & Sons, Inc. v. American Standard, Inc.

127 S.W.3d 814, 2003 Tex. App. LEXIS 10545, 2003 WL 22955938
CourtCourt of Appeals of Texas
DecidedDecember 17, 2003
Docket04-02-00857-CV
StatusPublished
Cited by33 cases

This text of 127 S.W.3d 814 (Wade & Sons, Inc. v. American Standard, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wade & Sons, Inc. v. American Standard, Inc., 127 S.W.3d 814, 2003 Tex. App. LEXIS 10545, 2003 WL 22955938 (Tex. Ct. App. 2003).

Opinion

OPINION

Opinion by

KAREN ANGELINI, Justice.

This appeal arises out of a dispute over a commercial construction project. In fourteen issues, Wade and Sons, Inc. d/b/a Consolidated Service Company (“Consolidated”), Browning Construction Company (“Browning”), and Federal Insurance Company (“Federal”) appeal the trial court’s judgment awarding damages to American Standard, Inc. d/b/a American Standard Products, Inc. d/b/a The Trane Company (“Trane”). In our opinion and judgment of November 5, 2003, we overruled all issues and affirmed the judgment of the trial court. On November 20, 2003, Consolidated 1 filed a motion for rehearing. We deny Consolidated’s motion for rehearing. However, to correct a factual misstatement, we withdraw our opinion issued on November 5, 2003 and substitute this opinion in its place. Our judgment issued on November 5, 2003, however, remains unchanged.

Background

Needing to remodel a building in its corporate headquarters compound, HEB Grocery Stores, Inc. (“HEB”) sought bids from construction companies. In prepar *818 ing its bid to HEB, Browning, a general contractor, sought a bid from Consolidated, a mechanical contractor, for installation of air-conditioning units. Consolidated, in turn, requested a bid from Trane, seeking to know at what price Trane would supply the units. In response, on March 10,1998, Trane sent Consolidated a “Proposal.” According to Trane, attached to this proposal was a document entitled “Standard Terms and Conditions.” Consolidated, on the other hand, claims that the terms and conditions were not attached to the proposal.

Browning, the general contractor, was awarded the contract on the building. Consolidated was awarded the subcontract. After being awarded the subcontract, on April 29, 1998, Henry Wade, the president of Consolidated, prepared “Purchase Order 302-017Q.” In that purchase order, Consolidated sought to purchase the units “as specifically detailed in the proposal dated 3/10/98 and in accordance with the plans, specifications and all other related documents” for $250,000. At this point, Consolidated claims that the contract was formed and that it expected delivery of the units in June of 1998. Trane disagrees, stating that no contract was formed until Consolidated’s credit application was approved on July 30, 1998. On that date,. Trane stamped and signed its approval on Consolidated’s purchase order: “ACCEPTED: Acknowledged, however and in accordance with, the terms and conditions of sale described - on the attached sheet.” These are the same terms and conditions that Trane says/its sent out with its proposal.

The units -were not delivered until August of 1998 and did not have the “piping packages” 2 installed. Trane’s proposal provided for the piping packages to be factory installed. Because the project was now behind schedule, instead of sending the units back to Trane, Consolidated installed the units in the building without the piping packages. Trane hired EZ Mechanical to fabricate the piping packages for Consolidated to install in the field. However, EZ Mechanical’s piping packages did not fit correctly. Consolidated would take the piping packages apart and redo them. So, after EZ Mechanical had fabricated a little more than half of the packages, Consolidated took over the job and began fabricating the rest. Consolidated then had to install the piping packages on the units in a finished space. According to Consolidated, fabrication and installation of the piping packages cost $74,074. Although Consolidated’s phase of the project was due to be finished in September of 1998, Consolidated still had not finished in March of 1999 when Browning terminated Consolidated’s subcontract. According to Timothy Wayne Bentley, the project manager for Browning, Consolidated was not properly supervising the work, was not providing a sufficient number of workers, nor was it providing qualified workers.

Browning filed a declaratory action against Consolidated. Consolidated counterclaimed against Browning and brought a third-party action against HEB and Trane. Consolidated claimed that Trane was untimely in its delivery of the units, causing Consolidated substantial damages. Trane filed a cross-claim against Consolidated and Browning for monies due under the contract. Trane also filed a suit on a sworn account against Consolidated and Browning. And, Trane asserted a claim against Browning’s surety, Federal, on the *819 “Bond to Indemnify Against Lien” procured by Browning. Trane alleged $58,686.80 pursuant to its mechanic’s lien, and an additional $10,036.70 in damages on the contract not subject to the lien.

Further, in its answer to Consolidated’s claim, Trane asserted that the parties, pursuant to the “Standard Terms and Conditions,” had “agreed to the exclusion of all express and implied warranties, including all warranties of merchantability and fitness for a particular’ purpose, with the sole exception of the written warranty set forth in the contract.” And, Trane alleged that the same terms and conditions provided that Trane would have no liability whatsoever “until said products ha[d] been paid for and then said liability shall be limited to the purchase price of the equipment shown to be defective.” Thus, according to Trane, because Consolidated had not paid the full price of $250,000, Trane had no liability. And, even if it did, Consolidated’s damages were limited to the purchase price. Further, Trane contended that all of Consolidated’s damages are incidental and consequential, damages that the terms and conditions specifically excludes.

Consolidated nonsuited HEB. Browning’s and Consolidated’s claims against one another were settled before trial. 3 Consolidated’s and Trane’s claims thus proceeded to trial. Before trial, Trane filed a motion in limine asserting the defenses outlined above. At trial, the trial court heard Trane’s motion in limine and ruled in its favor: Consolidated would not be permitted to present any evidence of incidental or consequential damages. The case was tried before the bench. Although the trial court granted the motion in limine, Consolidated made several bills of exceptions, proving what its incidental and consequential damages would be. The trial court entered judgment for Trane against Consolidated and Browning in the amount of $68,728.00. The trial court awarded Trane judgment for part of this amount, $58,686.30, against Federal on its surety bond. The trial court also awarded Trane $30,000 in attorney’s fees for trial, $2,500 in attorney’s fee if the case was appealed to the court of appeals, and $2,500 if the case was appealed to the supreme court.

Implied Findings of Fact

After the non-jury trial, the trial court did not enter findings of fact and conclusions of law. 4 Thus, we presume that the trial court resolved all questions of fact in support of the judgment. Worford v. Stamper, 801 S.W.2d 108, 109 (Tex.1990) (per curiam); Brown v. Comm’n for Lawyer Discipline, 980 S.W.2d 675, 678-79 (Tex.App.-San Antonio 1998, no pet.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pine Telephone Co. v. Alcatel-Lucent USA Inc.
617 F. App'x 846 (Tenth Circuit, 2015)
DaimlerChrysler Motors Co., LLC v. Manuel
362 S.W.3d 160 (Court of Appeals of Texas, 2012)
Powell Electrical Systems, Inc. v. Hewlett Packard Co.
356 S.W.3d 113 (Court of Appeals of Texas, 2011)
Wolf Hollow I, L.P. v. El Paso Marketing, L.P.
329 S.W.3d 628 (Court of Appeals of Texas, 2010)
in Re Estate of Nora G. Montemayor
Court of Appeals of Texas, 2010
Truss World, Inc. v. ERJS, INC.
284 S.W.3d 393 (Court of Appeals of Texas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
127 S.W.3d 814, 2003 Tex. App. LEXIS 10545, 2003 WL 22955938, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wade-sons-inc-v-american-standard-inc-texapp-2003.