Technology Construction, Inc. v. City of Kingman

278 P.3d 906, 229 Ariz. 564, 636 Ariz. Adv. Rep. 20, 2013 WL 2603364, 2012 Ariz. App. LEXIS 98
CourtCourt of Appeals of Arizona
DecidedJune 12, 2012
DocketNo. 1 CA-CV 11-0193
StatusPublished
Cited by6 cases

This text of 278 P.3d 906 (Technology Construction, Inc. v. City of Kingman) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Technology Construction, Inc. v. City of Kingman, 278 P.3d 906, 229 Ariz. 564, 636 Ariz. Adv. Rep. 20, 2013 WL 2603364, 2012 Ariz. App. LEXIS 98 (Ark. Ct. App. 2012).

Opinion

OPINION

THOMPSON, Presiding Judge.

¶ 1 Defendant City of Kingman (City) appeals the trial court’s judgment in favor of plaintiff Technology Construction, Inc. (TCI) in the amount of $324,933 plus interest, attorneys’ fees and costs, and the denial of its motion for new trial pursuant to Arizona Rule of Civil Procedure 59. For the reasons that follow, we affirm.

FACTUAL AND PROCEDURAL HISTORY

¶ 2 In July 2005, TCI entered into a construction contract with City for the construction of the Kingman Airway Avenue Railroad Crossing Improvement District, Project No. 05-ID-0015 (the project). The project consisted of an underpass railroad crossing, preparation of an embankment for a “shoofly” 1 for the Burlington Northern Santa Fe Railroad, excavation, relocation of utilities, construction of storm drains, paving, and various improvements. TCI was the lowest responsible bidder for the project at $5,226,722.

¶ 3 Work on the project was scheduled to be done in two phases. Phase one was scheduled to begin June 1, 2005, and was to be finished by June 30, 2005.2 Phase two was scheduled to begin July 18, 2005, and was to be completed by March 15, 2006.3 TCI’s work did not commence until October 2005, however, as City did not present a contract for TCI to sign until July 7, 2005, and City did not give TCI notices to proceed with the construction until October 14, 2005 (phase two) and November 3, 2005 (phase one).4 TCI did nothing to cause this delay.

¶ 4 In May 2006, TCI submitted a notice of claim to City regarding the work it had contracted to perform. TCI claimed that adjustments to the contract were necessary due to “the increased cost of asphalt materials arising out of the delay in City’s Notice to Proceed, changes in the work, delays beyond the control of (TCI) and cost impact on oil-based products by Hurricane Katrina.”5 The notice of claim letter stated that TCI would submit a change order request for the increased cost of its materials from October 2005 onward, once the final quantity and price of materials had been determined. Subsequently, TCI requested additional payment, but City did not pay.

¶ 5 TCI filed an action in Maricopa County Superior Court against City for breach of contract and violation of the prompt payment act; venue was transferred to Mohave County Superior Court. City filed a motion to dismiss the complaint for failure to state a claim upon which relief can be granted, which the trial court denied.

¶ 6 The trial court held a two-day bench trial. After the trial, the court dismissed TCI’s complaint on the ground that TCI’s notice of claim failed to meet the requirements of the notice of claim statute. TCI timely appealed. In an unpublished decision in 1 CA-CV 09-0011, another panel of this court reversed the dismissal of the complaint and remanded for further proceedings in the trial court, finding that City had waived its right to assert the affirmative defense that the notice of claim was deficient. We asked [566]*566the trial court to render a decision on the merits of TCI’s complaint as presented to the court during the bench trial.

¶ 7 After considering TCI’s brief on the proper measure of damages,6 the trial court entered judgment in favor of TCI in the amount of $324,933 plus pre-judgment interest in the amount of $117,785, post-judgment interest at the rate of ten percent per annum, and attorneys’ fees and costs. The trial court made extensive findings of fact and conclusions of law. The court’s order provides, in part:

The record before the Court contains undisputed testimony as to delay after delay. None of the delays can be attributed to TCI. TCI did not delay the execution of the Contract. TCI did not initiate the requirement that the Phase 2 work commence before Phase 1 work. There were unexpected utilities that had to be relocated to complete the construction on the Project. Reengineering had to occur with respect to the sanitary sewer.
The former City Engineer for the CITY also testified. He testified that the delay in executing the Contract occurred because the CITY had to go back to the District property owners in order to pay for additional costs. The City Engineer, Mr. Johnson, agreed that TCI was not responsible for that delay. Mr. Johnson further testified that TCI was not responsible for the Phase 1 work not beginning on June 1, 2005, but being commenced many months later. Mr. Johnson further testified that it was not TCI’s responsibility for the delay with respect to the work completed by BNSF. He testified the delays by the CITY in getting the Contract executed and financing in place made it impossible for BNSF to complete its work prior to the fourth quarter of the year.
The City Engineer further testified that there were a number of unforeseen conditions that had to be addressed throughout the Project. Mr. Johnson not only testified that these were not the fault of TCI, but that TCI handled the unforeseen problems in a responsible manner.
As a result of Hurricane Katrina, the price of oil materials increased dramatically. At the time of the bid in May, 2005, the price of the oil materials was $190.00 per ton FOB. The FOB price of oil increased to $240.00 per ton in October, 2005, after Hurricane Katrina. In the first quarter of 2006, the price was now $275.00 per ton. At the time of delivery of the materials to the Project for paving the price of oil had increased to $340.00 per ton FOB. This led to an increase in cost of asphalt.
At the conclusion of the Project, 10, 359 tons of asphalt were installed. The initial bid price was $559,988.00 or $54.10 per ton. The actual price to install the asphalt was $884,921.00 or $85.40 per ton. The price for asphalt in October/November, 2005, when the CITY gave notice to proceed, was $61.00 per ton. The amount of damages claimed by TCI is $324,933.00, or the total increase in cost from bid/eontraet execution to actual cost of installation.
CITY contractually obligated itself to pay for damages based upon delay under Section 109.8.2 (of the MAG Specs). The CITY further obligated itself to pay for damages when there are unforeseen circumstances that neither party anticipated at the time of contracting under Section 110.1 (of the MAG Specs). Again, the record is replete with unforeseen circumstances that delayed this project. The mere fact that Hurricane Katrina occurred simply drove up the damages that neither party anticipated. Hurricane Katrina did not hold up performance of the Contract terms or otherwise contribute to the delay. However, it was an unforeseen circumstance that increased the cost of materials. The unforeseen circumstances were those that created the various delays referenced previously. The cost increase due to Hurricane Katrina is a changed condition under § 110.1. It further added to TCI’s damages as additional expenses occurred due to delay under Section 109.8.
[567]*567AR.S. § 34-2217 bolsters TCI’s position. Expenses occurred due to delay. The CITY was responsible for the delay. Neither party contemplated the increase in prices due to Hurricane Katrina. There was timely notification of the issues and damages to the CITY. TCI reasonably and judiciously handled the issues. TCI has met the statutory elements for a damage award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vereit Real Estate v. Fitness Int'l
Court of Appeals of Arizona, 2023
Glendale v. Viste
Court of Appeals of Arizona, 2020
Fieber v. Weisner
Court of Appeals of Arizona, 2019
Bond v. San Tan
Court of Appeals of Arizona, 2014

Cite This Page — Counsel Stack

Bluebook (online)
278 P.3d 906, 229 Ariz. 564, 636 Ariz. Adv. Rep. 20, 2013 WL 2603364, 2012 Ariz. App. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/technology-construction-inc-v-city-of-kingman-arizctapp-2012.