Glendale v. Viste

CourtCourt of Appeals of Arizona
DecidedJanuary 28, 2020
Docket1 CA-CV 18-0572
StatusUnpublished

This text of Glendale v. Viste (Glendale v. Viste) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glendale v. Viste, (Ark. Ct. App. 2020).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

CITY OF GLENDALE, Plaintiff/Appellee/Cross-Appellant,

v.

VIESTE SPE LLC, et al., Defendants/Appellants/Cross-Appellees.

No. 1 CA-CV 18-0572 FILED 1-28-2020

Appeal from the Superior Court in Maricopa County No. CV2015-005387 The Honorable Dawn M. Bergin, Judge

AFFIRMED

COUNSEL

Hagens Berman Sobol Shapiro LLP, Phoenix By Robert B. Carey, Michella A. Kras, John M. DeStefano Co-counsel for Defendants/Appellants/Cross-Appellees

Hagens Berman Sobol Shapiro LLP, Chicago IL By Daniel J. Kurowski, Pro Hac Vice Co-counsel for Defendants/Appellants/Cross-Appellees

Riley, Williams & Piatt LLC, Indianapolis, IN By William N. Riley, Pro Hac Vice Co-counsel for Defendants/Appellants/Cross-Appellees Sacks, Ricketts & Case LLP, Phoenix By Cynthia A. Ricketts, Margaret L. Parker, Nathan J. Kunz Counsel for Plaintiff/Appellee/Cross-Appellant

MEMORANDUM DECISION

Judge Michael J. Brown delivered the decision of the Court, in which Presiding Judge Jennifer B. Campbell and Judge Lawrence F. Winthrop joined.

B R O W N, Judge:

¶1 Vieste SPE, LLC, Vieste Energy, LLC, Michael Comparato, and Mark Branaman (collectively “Vieste”) appeal the superior court’s summary judgment ruling in favor of the City of Glendale (“City”).1 Vieste argues the court should have found that the City’s lawsuit was barred by res judicata and the court improperly interpreted key provisions of a waste- processing contract. For the following reasons, we affirm.

BACKGROUND

¶2 In 2010, Vieste and the City began discussing a renewable- energy project that involved the City supplying Municipal Solid Waste (“MSW”) to Vieste. The project was a “waste-energy initiative,” where Vieste would construct a facility at the City’s landfill to sort MSW into waste and recyclables. The recyclables that still held value would be sold, and the remaining waste would be processed into energy at the facility. In May 2012, City staff and representatives from Vieste presented the project to the Glendale City Council.

¶3 To execute the project, Vieste needed a power purchase agreement for the energy the facility would produce. Because obtaining that agreement was taking longer than the parties anticipated, they decided to do the project in two phases. As Vieste informed the City Council, the

1 Vieste Energy, LLC, is the parent company of Vieste SPE, LLC. Michael Comparato and Mark Branaman are Vieste executives who the City sued individually. Though all are listed in the notice of appeal, neither the parent company nor the executives raise any separate challenges to the court’s grant of summary judgment.

2 GLENDALE v. VIESTE, et al. Decision of the Court

goal of phasing was “in no way, or shape or form[] [to] bifurcate[] the project in half.” Rather, the phases were designed to “accelerate” the project so the parties would not have to wait an “extended period of time” for the power purchase agreement to be finalized.

¶4 Phase 1 contemplated Vieste constructing “a mixed waste materials recovery facility that [would] recover and recycle approximately 50% of solid waste stream currently being landfilled,” and Phase 2 would “consist of power generation from remaining waste destined for landfilling and a co-located economic development project.” In October 2012, the City Council approved the project, voting to execute (1) a master ground lease with Vieste for property located at the landfill, and (2) the Waste Supply Agreement (“Agreement”), governing the supply of MSW the City would need to deliver throughout the project. Significant to this litigation, the Agreement stated that certain yard waste could be delivered to Vieste only during Phase 2 of the project.

¶5 By spring of 2015, Vieste had finished the facilities necessary for Phase 1 and was close to commencing commercial operations, which meant in part that the waste facilities were “operating and able to receive and sort Recovered Recyclables from the Waste received.” However, the parties soon ran into difficulties surrounding the meaning of yard waste, and specifically, what waste was allowed under the Agreement during Phase 1.

¶6 Pursuant to Section 17.4 of the Agreement, the parties proceeded to arbitration. The goal of the arbitration was to answer the following: “Is Yard Waste an Acceptable Waste Type under the Waste Supply Agreement before the date on which the Phase 2 Energy Facilities are commissioned?”2 In a single-page ruling, the arbitrator determined that

2 The parties agreed on the scope of the arbitration; however, in a letter written at the request of the arbitrator, the City stated:

[I]f Vieste’s sole question is whether “Yard Waste” is deemed an “Acceptable Waste” in the Specifications contained in Exhibit B to the [Agreement], there is no need to submit this matter to arbitration. An arbitration that limited in scope would be unnecessary, given the definitions of “Municipal Solid Waste,” “Yard Waste,” and “Unacceptable Waste” in Exhibit B. . . . [T]he City is willing to stipulate that “Yard Waste” is an “Unacceptable Waste.”

3 GLENDALE v. VIESTE, et al. Decision of the Court

“Yard Waste” was not an “Acceptable Waste Type” during Phase 1 of the Agreement. In awarding attorneys’ fees to Vieste, the arbitrator noted the limited scope of his ruling: “In reality, the dispute before me was more about the scope of the arbitration agreement, rather than the respective merits of the parties’ position with respect to which party has the obligation to sort Yard Waste . . . . That dispute was not resolved in the arbitration.”

¶7 Shortly after the arbitrator’s ruling on the merits, the City filed a complaint in the superior court, seeking relief through a number of declaratory judgments and contract-related claims. After filing its answer, Vieste moved to confirm the arbitration award, which the court granted. In the meantime, Vieste moved for judgment on the pleadings, asserting the arbitration award barred the City’s complaint based on the law of the case. The court denied the motion.

¶8 After the parties engaged in significant motion practice and discovery, the City filed a second amended complaint seeking relief against Vieste on 16 counts, including claims for declaratory judgment, breach of contract, and negligent misrepresentation. Vieste filed four counterclaims (tort and contract) based on both the formation and execution of the Agreement. Of these claims, most relevant is Count One of the City’s complaint, which sought a declaratory judgment that the City’s “Municipal Solid Waste is an ‘Acceptable Waste’” under the Agreement.

¶9 Eventually the parties filed cross-motions for summary judgment. Both motions addressed numerous issues related to the parties’ dealings, but the most pertinent issue for this appeal is Count One— whether yard waste was acceptable during Phase 1 of the project. The superior court granted the City’s motion on Count One, concluding that yard waste typically found in the City’s MSW stream could be appropriately delivered to Vieste under the Agreement. The court ruled in favor of the City on most of its other claims, Vieste on some, and neither party on others. After the ruling, the parties stipulated to dismiss without prejudice the remaining few counts that had not been resolved in the ruling. After addressing various other matters over the next year, including damages and attorneys’ fees, the court issued its judgment, certified as final under Arizona Rule of Civil Procedure 54(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dressler v. Morrison
130 P.3d 978 (Arizona Supreme Court, 2006)
Maxwell v. Fidelity Financial Services, Inc.
907 P.2d 51 (Arizona Supreme Court, 1995)
Scholten v. Blackhawk Partners
909 P.2d 393 (Court of Appeals of Arizona, 1995)
Taylor v. State Farm Mutual Automobile Insurance
854 P.2d 1134 (Arizona Supreme Court, 1993)
Phoenix Newspapers, Inc. v. Department of Corrections
934 P.2d 801 (Court of Appeals of Arizona, 1997)
Long v. City of Glendale
93 P.3d 519 (Court of Appeals of Arizona, 2004)
County of La Paz v. Yakima Compost Co.
233 P.3d 1169 (Court of Appeals of Arizona, 2010)
Englert v. Carondelet Health Network
13 P.3d 763 (Court of Appeals of Arizona, 2000)
Grosvenor Holdings, L.C. v. Figueroa
218 P.3d 1045 (Court of Appeals of Arizona, 2009)
Matter of Levine
847 P.2d 1093 (Arizona Supreme Court, 1993)
Liberty Insurance Underwriters, Inc. v. Weitz Co.
158 P.3d 209 (Court of Appeals of Arizona, 2007)
Gfeller v. Scottsdale Vista North Townhomes Ass'n
969 P.2d 658 (Court of Appeals of Arizona, 1998)
Aztar Corp. v. U.S. Fire Insurance
224 P.3d 960 (Court of Appeals of Arizona, 2010)
Technology Construction, Inc. v. City of Kingman
278 P.3d 906 (Court of Appeals of Arizona, 2012)
City of Tempe v. State
351 P.3d 367 (Court of Appeals of Arizona, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Glendale v. Viste, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glendale-v-viste-arizctapp-2020.