Technical Facilities of America, Inc. v. Joseph T. Ryerson & Son, Inc.

511 N.E.2d 364, 24 Mass. App. Ct. 601, 1987 Mass. App. LEXIS 2095
CourtMassachusetts Appeals Court
DecidedAugust 10, 1987
StatusPublished
Cited by3 cases

This text of 511 N.E.2d 364 (Technical Facilities of America, Inc. v. Joseph T. Ryerson & Son, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Technical Facilities of America, Inc. v. Joseph T. Ryerson & Son, Inc., 511 N.E.2d 364, 24 Mass. App. Ct. 601, 1987 Mass. App. LEXIS 2095 (Mass. Ct. App. 1987).

Opinion

Perretta, J.

On May 24, 1977, there was a partial collapse of a portable roof-like structure which was used to provide support for overhead lighting equipment at concerts given by rock music groups. The structure was made of aluminum trusses which were bolted together to form the grid-like rectangle. The collapse was caused when a weld connecting one of the trusses to an end plate failed. The structure was owned by the plaintiff, Technical Facilities of America, Inc. (TFA). TFA had supplied the raw materials for the fabrication and manufacturing of the various components of the structure to the defendant Joseph T. Ryerson & Son, Inc. (Ryerson). Pursuant to its agreement with TFA, Ryerson then “located” the third-party defendant Gilchrist Metal Manufacturing Co., Inc. (Gilchrist), to do the fabrication work.1 At trial, the main issue was whether [602]*602TFA or Gilchrist had made the weld that failed. In response to special questions, the jury found that Gilchrist had built the structure but that it had not made the weld. Judgment entered in favor of Ryerson and Gilchrist. On appeal, TFA raises numerous issues, all of which turn on whether the jury’s answers to the special questions were consistent. We affirm.

I. The Structure.

There was evidence to show the following facts. TFA was in the business of providing lighting equipment for use at rock music concerts. In 1976, it designed and manufactured an aluminum roof structure made of various trusses. The trusses were bolted together to form a grid-like rectangle sixty feet in width (across a stage) and forty-five feet in length (or depth). Because the trusses were bolted together, the structure could be assembled and disassembled at the concert site by TFA employees and transported either to the next concert site or to TFA’s warehouse.

When the demand for its services increased, TFA decided that it needed two more roof structures as well as three extension kits so that each of the three structures could be expanded to a rectangle measuring sixty feet by sixty feet. Additionally, TFA wanted the parts of each of the three roof structures to be interchangeable, that is, that the trusses of any one roof structure could be interchanged with their counterparts in any of the other roof structures. The components of the extension kits were also to be interchangeable but only as to extension kits, that is, the parts of the roof structures could not be interchanged with the parts of the extension kits.

In late May of 1976, TFA and Ryerson agreed that TFA would furnish to Ryerson drawings and raw materials for the fabrication and manufacturing of the two additional roof structures and three extension kits and that Ryerson would locate someone to do the actual work. Ryerson thereafter entered into its subcontract with Gilchrist.

Some time between June 5th and June 7th, TFA asked Ryerson whether one of the two ordered roof structures could be delivered to it in early June. After conferring with Gilchrist, Ryerson informed TFA that such an early delivery was impossible. TFA [603]*603next inquired whether one of the three extension kits could be delivered to it so that it could expand its own roof structure of forty-five feet by sixty feet to the needed sixty by sixty rectangle. Ryerson and Gilchrist agreed to that delivery.

On June 9, 1976, TFA received numerous fabricated parts from Gilchrist. The nature and purpose of the parts delivered on that date were sharply disputed at trial for the following reason. As earlier noted, the parts of each of the roof structures and the parts of each of the extension kits could be interchanged. Consequently, no one could state with any certainty which of the three roof structures or three extension kits was involved in the 1977 collapse. However, it was known: (1) that the weld that failed had been made on an extension kit truss; and (2) that Gilchrist had fabricated the pieces for the three extension kits.

TFA offered evidence to show that each extension kit required two 4B trusses for a total order of six such trusses for the three extension kits. The June 9th bill of lading indicated that the pieces delivered to TFA were pieces for 4A2 trusses. As no 4B truss components were delivered to TFA on that date, TFA could not have made the weld that failed. As further support for its claim, TFA pointed to bills of lading dated June 22nd and 25 th, each indicating a delivery of three 4B trusses.

Ryerson’s contention was as follows. The June 9th delivery consisted of unwelded fabricated pieces which were to be used to form the 4B and 4C trusses necessary for the needed extension kit. To form the fabricated pieces into the necessary trusses, welds had to be made. Therefore, TFA made the welds on the components of one of the three extension kits. Some of the evidence offered in support of this contention is as follows. A salesman for Ryerson during the time here pertinent (but not at that time of his testimony), Henry Athanasiou, testified that the June 9th bill of lading was wrong. That exhibit shows, it will be recalled, that on June 9th, TFA received components for 4A2 trusses. With the assistance of a diagram, Athanasiou explained why, in his opinion, on June 9th TFA did not need any 4A2 trusses to expand its own roof structure. He testified that on June 9th, TFA received unwelded tubes [604]*604and plates (that is, the components) for 4B and 4C trusses for an extension kit and that TFA welded those pieces. He further testified that at least one of the two subsequent bills of lading (June 22nd and June 25th) was also in error. According to his testimony, the bills of lading were simply attempts to account for all the pieces or components, even if not welded, that Gilchrist delivered to TFA on its subcontract with Ryerson.

II. The Special Questions.

Fifteen special questions were put to the jury, who were instructed that if their answer to either question one or question two was “no,” they were to “report that answer to the court and . . . not continue to the other questions. ” The first question reads, as relevant: “Was the roof structure extension which was involved in the failure ... a structure which had been built by Gilchrist?” Answering “yes” to question one, the jury took up the second question: “Was the weld which was involved in the failure ... a weld which was made by Gilchrist?” Because the jury responded “no” to this question, they proceeded no further and reported to the court, as instructed.

It appears from the transcript of the lobby conference held to discuss the special questions that question one, as originally worded, would have asked whether Gilchrist had built the “roof structure which was involved.” Gilchrist and Ryerson objected to the question in that form. Gilchrist argued that the question was impossible to answer (because the pieces of the three roof structures were interchangeable and TFA had built one of the three) and that it was immaterial in view of the posture of the evidence and question two, which “goes to the heart of the identification issue.” TFA responded that it would not object to the deletion of question one but that, if put to the jury, the question should be amended to refer to the “roof extension kit.”

Ryerson then objected: “Our theory ... is that TFA built one of the three extension kits. If the jury finds that TFA built

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AYESHA ALEKSOV v. KRIS ALEKSOV & Another.
Massachusetts Appeals Court, 2025
Palriwala v. Palriwala Corp.
834 N.E.2d 1241 (Massachusetts Appeals Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
511 N.E.2d 364, 24 Mass. App. Ct. 601, 1987 Mass. App. LEXIS 2095, Counsel Stack Legal Research, https://law.counselstack.com/opinion/technical-facilities-of-america-inc-v-joseph-t-ryerson-son-inc-massappct-1987.