Technical Constr. Specialties, Inc. v. New Era Builders, Inc.

2012 Ohio 1328
CourtOhio Court of Appeals
DecidedMarch 28, 2012
Docket25776
StatusPublished
Cited by14 cases

This text of 2012 Ohio 1328 (Technical Constr. Specialties, Inc. v. New Era Builders, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Technical Constr. Specialties, Inc. v. New Era Builders, Inc., 2012 Ohio 1328 (Ohio Ct. App. 2012).

Opinion

[Cite as Technical Constr. Specialties, Inc. v. New Era Builders, Inc., 2012-Ohio-1328.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF SUMMIT )

TECHNICAL CONSTRUCTION C.A. No. 25776 SPECIALTIES, INC. dba NUFLOOR SYSTEMS

Appellee/Cross-Appellant APPEAL FROM JUDGMENT ENTERED IN THE v. STOW MUNICIPAL COURT COUNTY OF SUMMIT, OHIO NEW ERA BUILDINS, INC. et al. CASE No. 2009 CVF 01308

Appellants/Cross-Appellees

DECISION AND JOURNAL ENTRY

Dated: March 28, 2012

MOORE, Judge.

{¶1} Appellant/Cross-Appellee New Era Builders, Inc. appeals from the judgment of

the Stow Municipal Court. Additionally, Appellee/Cross-Appellant Technical Construction

Specialties, Inc. cross-appeals from the trial court’s judgment. This Court affirms in part,

reverses in part, and remands the matter for further proceedings.

I.

{¶2} On October 4, 2007, Technical Construction Specialties, Inc. (“TCS”) entered

into a written contract with New Era Builders, Inc. (“New Era”) to install “overlayment” flooring

at the Baker Building in Cleveland, Ohio. TCS began installation on October 12, 2007, and

completed the job seven days later on October 19, 2007. TCS invoiced New Era for the work on

October 31, 2007. Payment was due within thirty days. No payment was made. 2

{¶3} On January 5, 2008, New Era contacted TCS with a complaint regarding

“delamination” of a section of the installation. TCS contends that the underlayment it installed

was properly bonded, and the cracking was caused by an “unstable subgrade.” TCS offered to

remove the strip and patch or repair the area at the cost of New Era. New Era declined this offer.

{¶4} On April 6, 2009, TCS filed a claim against New Era for breach of contract and

sought to recover $11,900 plus interest. The matter was referred to mediation on January 22,

2010. The parties executed a settlement agreement as well as a separate contract for additional

work to patch and repair the areas where the underlayment was removed. The trial court

subsequently filed an order dismissing the matter, subject to the parties filing an agreed upon

order to the contrary within thirty days. On March 11, 2010, TCS sent a notice of settlement,

settlement agreement, and contract for the additional repair work to New Era for approval. New

Era did not respond. On March 30, 2010, TCS filed a motion to vacate the order dismissing the

claims, a motion to enforce settlement, and a motion for sanctions. New Era filed a reply

claiming that the documents were not signed because an installation date had not been agreed to.

On May 5, 2010, the trial court ordered the parties to agree to a new date.

{¶5} On June 4, 2010, TCS filed a notice of settlement, with the approval of New Era.

However, payment was not tendered by New Era within thirty days as required by the settlement

agreement. On July 15, 2010, TCS filed a motion to enforce the settlement agreement. It also

requested an award of attorney fees. A hearing was held before a magistrate on August 24, 2010.

The magistrate’s decision was issued on September 16, 2010 recommending that the trial court

grant the motion to enforce the settlement agreement. Objections were filed by TCS on

September 27, 2010, and by New Era on October 7, 2010. On December 17, 2010, the trial court 3

overruled New Era’s objections, sustained TCS’ objection to the interest rate amount, and

overruled TCS’ objection to the failure to award attorney fees.

{¶6} New Era timely filed a notice of appeal and raises two assignments of error for

our review. Additionally, TCS timely filed a notice of cross-appeal and raises two cross-

assignments of error.

II.

ASSIGNMENT OF ERROR I

THE TRIAL COURT ERRED WHEN IT EQUATED “ATTEMPTS TO REPAIR” TO “REPAIR”, WHICH WAS A REQUIREMENT PRIOR TO ANY FUNDS BEING DUE.

{¶7} In its first assignment of error, New Era argues that the trial court’s interpretation

of the word “repair” was “contrary to the evidence presented.” This Court disagrees.

{¶8} In determining whether the trial court’s decision is or is not supported by the

manifest weight of the evidence, this Court applies the civil manifest weight of the evidence

standard set forth in C.E. Morris Co. v. Foley Const. Co., 54 Ohio St.2d 279 (1978), syllabus,

which holds: “Judgments supported by some competent, credible evidence going to all the

essential elements of the case will not be reversed by a reviewing court as being against the

manifest weight of the evidence.” The Ohio Supreme Court has clarified that:

when reviewing a judgment under a manifest-weight-of-the-evidence standard, a court has an obligation to presume that the findings of the trier of fact are correct. Seasons Coal Co., Inc. v. Cleveland, 10 Ohio St.3d 77, 80-81 (1984). This presumption arises because the trial judge had the opportunity “to view the witnesses and observe their demeanor, gestures and voice inflections, and use these observations in weighing the credibility of the proffered testimony.” Id. at 80. “A reviewing court should not reverse a decision simply because it holds a different opinion concerning the credibility of the witnesses and evidence submitted before the trial court. A finding of an error in law is a legitimate ground for reversal, but a difference of opinion on credibility of witnesses and evidence is not.” Id. at 81. 4

State v. Wilson, 113 Ohio St.3d 382, 2007-Ohio-2202, ¶ 24.

{¶9} Pursuant to App.R. 9(B), an appellant who wishes to assert that a finding or

conclusion is unsupported by the evidence or against the manifest weight of the evidence shall

include in the record “a transcript of proceedings that includes all evidence relevant to the

findings or conclusion.” App.R. 9(B) further provides:

Unless the entire transcript of proceedings is to be included in the record, the appellant shall file with the notice of appeal a statement, as follows:

If the proceedings were recorded by a stenographic/shorthand reporter, the statement shall list the assignments of error the appellant intends to present on the appeal and shall either describe the parts of the transcript that the appellant intends to include in the record or shall indicate that the appellant believes that no transcript is necessary.

If the proceedings were not recorded by any means, or if the proceedings were recorded by non-stenographic means but the recording is no longer available for transcription, or if the stenographic record has become unavailable, then the statement shall list the assignments of error the appellant intends to present on appeal and shall indicate that a statement under App. R. 9(C) or 9(D) will be submitted.

{¶10} In this case, the record does not contain a transcript from the hearing before the

magistrate on August 24, 2010. In addition, New Era failed to include a statement demonstrating

that no transcript is necessary pursuant to App.R. 9(C) or 9(D).

{¶11} “When portions of the transcript necessary for resolution of assigned errors are

omitted from the record, the reviewing court has nothing to pass upon and thus, as to those

assigned errors, the court has no choice but to presume the validity of the lower court’s

proceedings, and affirm.” Knapp v. Edwards Laboratories, 61 Ohio St.2d 197, 199 (1980).

Thus, in the absence of a complete record, this Court must presume regularity in the trial court’s

proceedings and accept its judgment. Wozniak v. Wozniak, 90 Ohio App.3d 400, 409 (9th

Dist.1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Suite Living, L.L.C. v. Elyria
2026 Ohio 706 (Ohio Court of Appeals, 2026)
Zeedyk v. 5C's Drying
2026 Ohio 618 (Ohio Court of Appeals, 2026)
Kern v. Mishler
2025 Ohio 1698 (Ohio Court of Appeals, 2025)
Universal Steel Bldgs. Corp. v. Dues
2024 Ohio 698 (Ohio Court of Appeals, 2024)
Vitantonio v. Am. Constr. Group, L.L.C.
2024 Ohio 325 (Ohio Court of Appeals, 2024)
M.C. v. Choudhry
2022 Ohio 915 (Ohio Court of Appeals, 2022)
United Gulf Marine, L.L.C. v. Continental Refining Co., L.L.C.
2019 Ohio 666 (Ohio Court of Appeals, 2019)
Clark v. Corwin
2018 Ohio 1169 (Ohio Court of Appeals, 2018)
Teague v. Schmeltzer
2018 Ohio 76 (Ohio Court of Appeals, 2018)
KNL Custom Homes, Inc. v. Dotsikas
2016 Ohio 5117 (Ohio Court of Appeals, 2016)
Savoy Hospitality, L.L.C. v. 5839 Monore St. Assocs., L.L.C.
2015 Ohio 4879 (Ohio Court of Appeals, 2015)
Ikerd Scuba Ents., L.L.C. v. Lakes
2014 Ohio 533 (Ohio Court of Appeals, 2014)
111 N. Main St., Inc. v. Von Allmen Ents., L.L.C.
2013 Ohio 5554 (Ohio Court of Appeals, 2013)
Ohio Metal Servs., L.L.C. v. All-In Metals
2013 Ohio 2174 (Ohio Court of Appeals, 2013)
Brown v. Spitzer Chevrolet Co.
2012 Ohio 5623 (Ohio Court of Appeals, 2012)
Schiavoni v. Roy
2012 Ohio 4435 (Ohio Court of Appeals, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 1328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/technical-constr-specialties-inc-v-new-era-builders-inc-ohioctapp-2012.