Lenk, J.
The defendant, Martha’s Vineyard Land Bank Commission, owns and manages a nature preserve on the western edge of Martha’s Vineyard. The preserve is comprised of various parcels of land that the defendant purchased in the 1990s. In 2010, the defendant created a hiking trail through the preserve, which it planned to open to the public. The trail began on a main road, crossed over the grounds of an inn owned by the plaintiffs via a
forty-foot wide easement, proceeded from there across three parcels of the defendant’s land for whose benefit the easement was created, and then entered a fourth parcel, also owned by the defendant, that was not intended to benefit from the easement. The plaintiffs filed an action in the Land Court to prevent the defendant from using the easement as part of the hiking trail. They argued, among other things, that it was improper, pursuant to
Murphy
v.
Mart Realty of Brockton, Inc.,
348 Mass. 675 (1965), for the trail to cross over the easement and then continue onto the fourth parcel, given that the easement was not intended to serve that parcel. On this basis, a judge of the Land Court granted partial summary judgment for the plaintiffs. Following a bench trial, at which certain remaining issues were resolved in the defendant’s favor, the defendant appealed from the grant of partial summary judgment, and we allowed its application for direct appellate review.
The defendant contends that the bright-line rule in
Murphy,
disallowing any use of an easement to benefit land to which the easement is not appurtenant,
is overly rigid. The defendant suggests that, instead, this court should adopt a fact-intensive inquiry requiring consideration whether the use of a particular easement to benefit other parcels would increase unfairly the burden on the easement. We conclude that the benefits of preserving the longstanding, bright-line rule set forth in
Murphy
outweigh any costs associated with its rigidity, and we therefore decline to adopt the defendant’s suggestion. Accordingly, we affirm the judgment of the Land Court.
1.
Background.
Martha’s Vineyard Land Bank Commission “was established in 1985 by a special act of the Legislature . . . for the purpose of acquiring land for environmental protection, conservation, and managed public use.” It owns and manages, among other properties, the Aquinnah Headlands Preserve, a nature preserve on the western edge of Martha’s Vineyard located atop the Gay Head Cliffs. The preserve contains a series of hiking trails, which are open to the public annually during the tourism off-season, from September 15 through June 15.
In the early 1990s, the defendant assembled what is now the preserve by purchasing a series of parcels on the Gay Head Cliffs. Four of these parcels are relevant here. From south to north, these adjacent parcels are referenced by the parties as Ginnochio Lot l,
Vanderhoop Parcel, Ginnochio Lot 2, and Diem Lot 5.
None of the four parcels abuts the nearest public way, Lighthouse Road, which runs to the south of the properties. A separate parcel, however, located to the southeast of the defendant’s properties, connects Ginnochio Lot 1 to Lighthouse Road. That parcel, owned by the plaintiffs, is registered land known as the Inn Property. It contains a small hotel with seven guest rooms that is open only during the tourism season, approximately from mid-May through Columbus Day weekend.
The defendant’s parcels benefit from two easements that burden the Inn Property. Those easements, which were created before the defendant purchased the parcels that now comprise the preserve, provide access to and from Lighthouse Road. Neither of the easements is appurtenant to all four of the parcels. The first easement, a forty-foot wide road referred to in the Land Court proceedings and by the parties here as the Disputed Way, is appurtenant to and serves the three southern parcels (Ginnochio Lot 1, Vanderhoop Parcel, and Ginnochio Lot 2). The other easement, called Twenty-Foot Way, is appurtenant to and serves Diem Lot 5, the northernmost property.
In May, 2010, the defendant received approval from various government agencies to implement a “Management Plan”
that
called for creating a hiking trail on the preserve. The proposed trail would incorporate Disputed Way and Twenty-Foot Way in a single loop. The trail would extend along the full length of Disputed Way, “begin[ning] at Lighthouse Road, proceeding] northwesterly over [the Inn] Property, then over Ginnochio Lot 1, . . . and the Vanderhoop Parcel,” and “terminating on Ginnochio Lot 2.” From there, the trail would run north into Diem Lot 5, and ultimately intersect with Twenty-Foot Way. Then, via Twenty-Foot Way, the trail would return to its point of origin near Lighthouse Road.
In June, 2010, the plaintiffs filed a complaint in the Land Court seeking a declaratory judgment that the defendant could not use Disputed Way as part of the proposed hiking loop. Among other things, the plaintiffs argued that, because the Disputed Way easement was appurtenant only to Ginnochio Lot 1, Vanderhoop Parcel, and Ginnochio Lot 2, the three southern parcels, the defendant was not entitled to use it as part of a trail that reached Diem Lot 5.
The plaintiffs also argued that opening Disputed Way to the public, even without a continuation onto Diem Lot 5, would overburden
the easement.
In March, 2011, the plaintiffs filed a motion for summary judgment. A Land Court judge granted the motion in part, concluding, among other things, that incorporating Disputed Way into a hiking trail that reached Diem Lot 5 would overload the Disputed Way easement and, accordingly, that any trail passing over Disputed Way must terminate before crossing onto Diem Lot 5. This effectively divided the proposed hiking loop into two separate trails, the first from Lighthouse Road to Ginnochio Lot 2 via Disputed Way, and the other from Lighthouse Road to Diem Lot 5 via Twenty-Foot Way. While hikers could make use of both trails, they would not be able to do so in a single loop.
The judge also concluded, however, that there was a genuine issue of material fact whether, among other things, opening the easement to the public would unreasonably increase pedestrian
traffic on the Inn Property and thereby overburden the easement. The judge conducted a trial on that issue, and concluded that opening Disputed Way to members of the public would not overburden the easement. He noted that “such use comports to the [original] scope of the easement” and that the defendant proposed only “limited use of the Disputed Way by the public.”
The defendant filed a notice of appeal.
Free access — add to your briefcase to read the full text and ask questions with AI
Lenk, J.
The defendant, Martha’s Vineyard Land Bank Commission, owns and manages a nature preserve on the western edge of Martha’s Vineyard. The preserve is comprised of various parcels of land that the defendant purchased in the 1990s. In 2010, the defendant created a hiking trail through the preserve, which it planned to open to the public. The trail began on a main road, crossed over the grounds of an inn owned by the plaintiffs via a
forty-foot wide easement, proceeded from there across three parcels of the defendant’s land for whose benefit the easement was created, and then entered a fourth parcel, also owned by the defendant, that was not intended to benefit from the easement. The plaintiffs filed an action in the Land Court to prevent the defendant from using the easement as part of the hiking trail. They argued, among other things, that it was improper, pursuant to
Murphy
v.
Mart Realty of Brockton, Inc.,
348 Mass. 675 (1965), for the trail to cross over the easement and then continue onto the fourth parcel, given that the easement was not intended to serve that parcel. On this basis, a judge of the Land Court granted partial summary judgment for the plaintiffs. Following a bench trial, at which certain remaining issues were resolved in the defendant’s favor, the defendant appealed from the grant of partial summary judgment, and we allowed its application for direct appellate review.
The defendant contends that the bright-line rule in
Murphy,
disallowing any use of an easement to benefit land to which the easement is not appurtenant,
is overly rigid. The defendant suggests that, instead, this court should adopt a fact-intensive inquiry requiring consideration whether the use of a particular easement to benefit other parcels would increase unfairly the burden on the easement. We conclude that the benefits of preserving the longstanding, bright-line rule set forth in
Murphy
outweigh any costs associated with its rigidity, and we therefore decline to adopt the defendant’s suggestion. Accordingly, we affirm the judgment of the Land Court.
1.
Background.
Martha’s Vineyard Land Bank Commission “was established in 1985 by a special act of the Legislature . . . for the purpose of acquiring land for environmental protection, conservation, and managed public use.” It owns and manages, among other properties, the Aquinnah Headlands Preserve, a nature preserve on the western edge of Martha’s Vineyard located atop the Gay Head Cliffs. The preserve contains a series of hiking trails, which are open to the public annually during the tourism off-season, from September 15 through June 15.
In the early 1990s, the defendant assembled what is now the preserve by purchasing a series of parcels on the Gay Head Cliffs. Four of these parcels are relevant here. From south to north, these adjacent parcels are referenced by the parties as Ginnochio Lot l,
Vanderhoop Parcel, Ginnochio Lot 2, and Diem Lot 5.
None of the four parcels abuts the nearest public way, Lighthouse Road, which runs to the south of the properties. A separate parcel, however, located to the southeast of the defendant’s properties, connects Ginnochio Lot 1 to Lighthouse Road. That parcel, owned by the plaintiffs, is registered land known as the Inn Property. It contains a small hotel with seven guest rooms that is open only during the tourism season, approximately from mid-May through Columbus Day weekend.
The defendant’s parcels benefit from two easements that burden the Inn Property. Those easements, which were created before the defendant purchased the parcels that now comprise the preserve, provide access to and from Lighthouse Road. Neither of the easements is appurtenant to all four of the parcels. The first easement, a forty-foot wide road referred to in the Land Court proceedings and by the parties here as the Disputed Way, is appurtenant to and serves the three southern parcels (Ginnochio Lot 1, Vanderhoop Parcel, and Ginnochio Lot 2). The other easement, called Twenty-Foot Way, is appurtenant to and serves Diem Lot 5, the northernmost property.
In May, 2010, the defendant received approval from various government agencies to implement a “Management Plan”
that
called for creating a hiking trail on the preserve. The proposed trail would incorporate Disputed Way and Twenty-Foot Way in a single loop. The trail would extend along the full length of Disputed Way, “begin[ning] at Lighthouse Road, proceeding] northwesterly over [the Inn] Property, then over Ginnochio Lot 1, . . . and the Vanderhoop Parcel,” and “terminating on Ginnochio Lot 2.” From there, the trail would run north into Diem Lot 5, and ultimately intersect with Twenty-Foot Way. Then, via Twenty-Foot Way, the trail would return to its point of origin near Lighthouse Road.
In June, 2010, the plaintiffs filed a complaint in the Land Court seeking a declaratory judgment that the defendant could not use Disputed Way as part of the proposed hiking loop. Among other things, the plaintiffs argued that, because the Disputed Way easement was appurtenant only to Ginnochio Lot 1, Vanderhoop Parcel, and Ginnochio Lot 2, the three southern parcels, the defendant was not entitled to use it as part of a trail that reached Diem Lot 5.
The plaintiffs also argued that opening Disputed Way to the public, even without a continuation onto Diem Lot 5, would overburden
the easement.
In March, 2011, the plaintiffs filed a motion for summary judgment. A Land Court judge granted the motion in part, concluding, among other things, that incorporating Disputed Way into a hiking trail that reached Diem Lot 5 would overload the Disputed Way easement and, accordingly, that any trail passing over Disputed Way must terminate before crossing onto Diem Lot 5. This effectively divided the proposed hiking loop into two separate trails, the first from Lighthouse Road to Ginnochio Lot 2 via Disputed Way, and the other from Lighthouse Road to Diem Lot 5 via Twenty-Foot Way. While hikers could make use of both trails, they would not be able to do so in a single loop.
The judge also concluded, however, that there was a genuine issue of material fact whether, among other things, opening the easement to the public would unreasonably increase pedestrian
traffic on the Inn Property and thereby overburden the easement. The judge conducted a trial on that issue, and concluded that opening Disputed Way to members of the public would not overburden the easement. He noted that “such use comports to the [original] scope of the easement” and that the defendant proposed only “limited use of the Disputed Way by the public.”
The defendant filed a notice of appeal. The notice specified that the defendant was challenging only the Land Court’s decision on summary judgment, i.e., the ruling that Disputed Way could not be used to benefit Diem Lot 5. The defendant then filed an application in this court seeking direct appellate review; that application was allowed.
2.
Discussion.
We have long held that a “right of way appurtenant to [a particular piece of] land . . . cannot be used by the owner of the dominant tenement to pass to or from other land adjacent to or beyond that to which the easement is appurtenant.”
See
Murphy,
348 Mass. at 678-679. See, e.g.,
McLaughlin
v.
Selectmen of Amherst,
422 Mass. 359, 364 (1996) (easement may not be used to serve estate to which not appurtenant);
Davenport
v.
Lamson,
21 Pick. 72, 74 (1838) (it is “well settled by the authorities, that if a [person] have a right of way over another’s land, to a particular close, he [or she] cannot enlarge it and extend it to other closes”). “[A]bsent . . . consent [from the owner of the servient estate], use of an easement to benefit property located beyond the dominant estate constitutes an over[load]ing of the easement” (citation omitted).
McLaughlin, supra
at 364.
This limitation on the permissible use of easements is a bright-line “rule [meant to] avoid[ ] otherwise difficult litigation over the question whether increased use unreasonably increases the burden on the servient estate” and, consequently, applies “even if no additional use of the easement or burden on the servient estate would ensue.” Restatement (Third) of Property: Servitudes § 4.11 comment b (2000) (Restatement of Property). Here, the parties do not dispute that, under this long-standing rule, the defendant would be prohibited from using Disputed Way to access a parcel the easement was not intended to benefit, i.e., Diem Lot 5.
The defendant suggests, however, that this court adopt a new rule that would replace the bright-line test described in
Murphy
with a fact-based inquiry.
The inquiry would consider “whether use of an easement by an adjacent parcel would place additional burden on the servient estate” and, if so, whether such additional use “unfairly burden[s] the servient estate ... in a manner beyond the scope of that intended” in the original grant. This proposed test is the functional equivalent of that used by courts in determining whether the owner of a dominant estate has overburdened an easement by changing the “manner, frequency, [or] intensity of the use.” See Restatement of Property,
supra
at § 4.10. See, e.g.,
Marden
v.
Mallard Decoy Club, Inc.,
361 Mass. 105, 107 (1972) (“easement granted in general terms is . . .. available for all reasonable uses to which the dominant estate may thereafter be devoted”);
Labounty
v.
Vickers,
352 Mass. 337, 345 (1967) (“The question as to the extent and limits of a reasonable right of way . . . [is] largely one of fact. . . ”); Restatement of Property,
supra
at § 4.10 comment c (“Resolution of the conflict [over changed use] often demands a detailed inquiry into the particular facts and circumstances of the case, and the issues as to intent, reasonable expectations, purpose, reasonableness of use, and extent of damage and interference are usually intertwined”). Under this test, the defendant contends, use of the Disputed Way easement to reach Diem Lot 5 would not constitute an overloading, as “it is unlikely that pedestrian traffic over the [plaintiffs’] lot will increase [merely because] the Disputed Way ... is used for access to Diem Lot 5.”
The defendant’s proposed test has the advantage of being more flexible than the current bright-line rule. That flexibility, however, would come with significant costs. First, it requires altering a
long-standing rule of “contract and property law . . . , in which reliance upon existing judicial precedent often influences individual action,” see
Papadopoulos
v.
Target Corp.,
457 Mass. 368, 385 (2010), and in which “considerations favoring stare decisis are ‘at their acme.’ ”
Kimble
v.
Marvel Entertainment, LLC,
135 S. Ct. 2401, 2410 (2015), quoting
Payne
v.
Tennessee,
501 U.S. 808, 828 (1991). While “this court is not barred from departing from previous pronouncements,” we do so only where “the benefits of [the proposed rule] outweigh the values underlying stare decisis.”
Stonehill College
v.
Massachusetts Comm'n Against Discrimination,
441 Mass. 549, 562, cert. denied, 543 U.S. 979 (2004).
Here, we are not persuaded that the defendant’s proposed rule would provide such benefits. The type of detailed inquiry the defendant proposes “frequently presents] difficult factual issues as to how broadly or narrowly the purpose [of the easement] should be defined, whether the proposed [expanded use] is ... of the sort that should have been contemplated by the parties, how much damage or interference is likely to ensue, and whether it is reasonable.” Restatement of Property,
supra
at § 4.10 comment c. Our bright-line rule in
Murphy
was formulated to avoid precisely this type of “difficult” litigation. See
id.
It goes without saying, as the defendant notes, that “we do not reject desirable developments in the law [of easements] solely because such developments may result in disputes spurring litigation.”
M.P.M. Bldrs., LLC
v.
Dwyer,
442 Mass. 87, 93 (2004). We are not so much concerned, however, with the mere fact of litigation, as with the uncertainty that the prospect of such litigation would introduce in land ownership.
See
id.
at 92 (we disfavor “placing] property interests in an uncertain status”);
Nelson
v.
Blinn,
197 Mass. 279, 281 (1908), aff'd, 222 U.S. 1 (1911) (policy against subjecting “regular and lawful use and ownership of property” to “restrictions and uncertainty”).
For example, a company might acquire a single, small parcel of land served by an easement, and then use that easement to pro
vide access to a large commercial establishment located on multiple adjoining parcels, none of which was intended to beneht from that easement. See
Murphy,
348 Mass. at 677-679 (defendant used easement to serve discount store; “neither the store itself nor [its] parking area” were within lot benehted by easement). In this scenario, a court operating under the current rule could permanently enjoin the company’s expanded use of the easement without any need for further fact hnding. Under the defendant’s fact-intensive rule, however, a court could not issue an injunction without inquiry into whether the expanded use is “of the sort that should have been contemplated by the parties, how much damage or interference is likely to ensue, and whether it is reasonable.” See Restatement of Property,
supra
at § 4.10 comment c. This inquiry would require a longer process of litigation than would the bright-line rule, would lead to a less predictable outcome, and might not be affordable to owners of small servient parcels who are lihgating against defendants with the hnancial means to acquire and develop multiple parcels of land.
See
Perdido Place Condominium Owners Ass’n
v.
Bella Luna Condominium Owners Ass’n,
43 So. 3d 1201, 1210 (Ala. 2009) (Murdock, J., dissenting) (Perdido) (under fact-based inquiry, developer might acquire small parcel of land and use it to serve many adjoining ones; servient landowner at “some point,” depending on circumstances, “way be able to argue that its property is being overburdened” [emphasis supplied]).
The defendant points, however, to cases from two other jurisdictions that had adopted a bright-line rule but subsequently moved away from that rule in favor of a more fact-based analysis. See
Perdido, supra
at 1206-1207 (easement properly used to beneht both lots on which condominium sits);
Abington Ltd. Partnership
v.
Heublein,
246 Conn. 815, 829-832 (1998) (in certain circumstances, easement may serve after-acquired lot). These
cases do not stand for the proposition attributed to them.
In
Perdido, supra
at 1204, while a deed creating the easement at issue stated on its face that the easement was to apply only to one of two lots, the judge concluded that the easement properly could be used to benefit both lots because the “parties at th[e] time [the easement was created] contemplated that the easement would benefit” both. Similarly, in
Abington Ltd. Partnership, supra
at 829, the Connecticut Supreme Court held that an easement could be used for the benefit of after-acquired parcels, but only if the “intent of the parties when the easement was created” was that it would benefit such parcels.
This comports with our rule that the “terms and conditions under which an easement may be created and the manner of its exercise are within the control of the creating parties” (citation omitted).
See
Patterson
v.
Paul,
448 Mass. 658, 665 (2007). See, e.g.,
Pion
v.
Dwight,
11 Mass. App. Ct. 406, 410 (1981) (easement intended to benefit multiple parcels). Here, by contrast, the judge found specifically that, at the time of its creation, the Disputed Way easement was not intended to benefit Diem Lot 5.
Further, we are not persuaded, as the defendant maintains, that “[c]urrent Massachusetts law creates a substantial impracticality” in circumstances such as these, and that it is inconsistent with our “public policy favoring socially productive use of land.” See
Martin
v.
Simmons Props., LLC,
467 Mass. 1, 13 (2014). As applied here, the traditional rule allows hikers to make use of both Disputed Way and Twenty-Foot Way; it prevents them only from walking the two paths in a single loop. While this may be an inconvenience, it does not amount to a “substantial impracticality.” In addition, the current rule will not necessarily prevent
parties in the defendant’s position from expanding their use of the easement insofar as they may attempt to “negotiate a result” with servient landowners. See
M.P.M. Bldrs., LLC,
442 Mass. at 94.
In sum, the bright-line rule articulated in
Murphy
provides owners of servient property with certainty regarding their posses-sory rights. The benefits of this certainty outweigh the perceived advantages of a more flexible rule.
Judgment affirmed.