JAMES MAGUIRE & Others v. PLANNING BOARD OF HAMILTON & Others.

CourtMassachusetts Appeals Court
DecidedMarch 15, 2023
Docket22-P-0229
StatusUnpublished

This text of JAMES MAGUIRE & Others v. PLANNING BOARD OF HAMILTON & Others. (JAMES MAGUIRE & Others v. PLANNING BOARD OF HAMILTON & Others.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JAMES MAGUIRE & Others v. PLANNING BOARD OF HAMILTON & Others., (Mass. Ct. App. 2023).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

22-P-229

JAMES MAGUIRE & others1

vs.

PLANNING BOARD OF HAMILTON & others.2

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

Defendants Patricia and Nazir Shamsuddin appeal from a Land

Court judgment invalidating defendant planning board of

Hamilton's (board) approval of the Shamsuddins' proposed

subdivision plan. Acting on cross motions for summary judgment,

a Land Court judge concluded that the board exceeded its

authority in approving the plan because the plan employed a

private way in a manner that would overload the Shamsuddins'

easement over the way. Agreeing with the judge's conclusion

that, in the circumstances of this case, the proposed use of the

easement as a subdivision road would violate the bright-line

1 Jennifer Maguire, Brett McKechnie, and Laurie McKechnie.

2 Patricia Shamsuddin and Nazir Shamsuddin. rule reaffirmed in Taylor v. Martha's Vineyard Land Bank Comm'n,

475 Mass. 682, 686 (2016), we affirm.

Background. We set forth the undisputed facts drawn from

the summary judgment record. See LeFort Enters., Inc. v.

Lantern 18, LLC, 491 Mass. 144, 145 (2023). The Shamsuddins own

two parcels of land originally shown on separate subdivision

plans. They own "lot C" as shown on a subdivision plan dated

March 24, 1956, and a portion of "lot 28" as shown on a

subdivision plan dated October 12, 1960.3 Lot 28 abuts the

western side of lot C, and a fifty-foot-wide, paved private way

runs along the eastern side of lot C. The plaintiffs, the

Maguires and the McKechnies, own properties that also abut the

private way. The plaintiffs have easements over the private

way, and they use it to gain access to Meyer Road, the nearest

public way.

The Shamsuddins proposed to create three new lots, each

incorporating property derived from lot C (toward the front of

each new lot) and lot 28 (at the rear of new each lot). Two of

the lots would have frontage on, and would be accessed by, the

3 More precisely, the portion of lot 28 owned by the Shamsuddins is shown as lot 5 on a 2013 "approval not required" plan. Following the terminology adopted by the judge and the parties, we refer to the Shamsuddins' portion of lot 28 shown on the subdivision plan simply as "lot 28."

2 private way abutting lot C.4 Lot C has the benefit of an

easement over the private way; however, lot 28 does not.5

Anticipating the overloading issue, the Shamsuddins proposed

that residential homes would be constructed entirely on the

portions of the new lots derived from lot C. The board approved

the subdivision plan with certain conditions, one of those

conditions being that the placement of any structures on the new

lots be limited to lot C.

The plaintiffs appealed the board's decision to the Land

Court pursuant to G. L. c. 41, § 81BB. The judge concluded that

the board exceeded its authority in approving the subdivision

plan because the proposed use of the private way, which would

benefit land derived from lot 28, would overload the easement,

which is appurtenant to the plaintiffs' lots and to lot C, but

not to lot 28. Accordingly, the judge annulled the decision

approving the subdivision plan.6

4 The third lot would have frontage on both the private way and on Meyer Road, with direct access to Meyer Road.

5 The judgment in this case included a declaration that lot C benefited from an express easement over the private way and ordered that a deed be modified to properly reflect that easement. The plaintiffs do not challenge that aspect of the judgment. The judge also found that lot 28 does not have the benefit of an easement over the private way, and the Shamsuddins concede this point.

6 The judge also concluded that the board exceeded its authority by failing to modify the conditions of two earlier subdivision approvals that restricted the number of houses on the lots in

3 Discussion. "Summary judgment is appropriate where there

is no material issue of fact in dispute and the moving party is

entitled to judgment as a matter of law." HSBC Bank USA, N.A.

v. Morris, 490 Mass. 322, 326 (2022). We review the decision de

novo. See id.

"We have long held that a 'right of way appurtenant to [a

particular piece of] land . . . cannot be used by the owner of

the dominant tenement to pass to or from other land adjacent to

or beyond that to which the easement is appurtenant" (footnote

omitted). Taylor, 475 Mass. at 686, quoting Murphy v. Mart

Realty of Brockton, Inc., 348 Mass. 675, 678-679 (1965). See

Greene v. Canny, 137 Mass. 64, 68 (1884). Indeed, "'[a]bsent

. . . consent [from the owner of the servient estate], use of an

easement to benefit property located beyond the dominant estate

constitutes an over[load]ing of the easement' (citation

omitted)." Taylor, supra, quoting McLaughlin v. Selectmen of

Amherst, 422 Mass. 359, 364 (1996). "This limitation on the

question and by failing to obtain consent for modification from the owner of an affected lot. In addition, the judge declared that although the private way would be overloaded, it would not be overburdened. The Shamsuddins and the plaintiffs in their cross appeal contest various aspects of these additional rulings. Because we affirm the annulment of the plan on the grounds of overloading, we need not reach any of these issues; if they recur at all, it will be under entirely different circumstances. In addition, the plaintiffs stated in their brief that we need not address their cross appeal if we affirm on the issue of overloading.

4 permissible use of easements is a bright-line 'rule [meant to]

avoid[] otherwise difficult litigation over the question whether

increased use unreasonably increases the burden on the servient

estate.'" Taylor, supra at 386, quoting Restatement (Third) of

Property: Servitudes § 4.11 comment b (2000).

While recognizing this bright-line rule, the Shamsuddins

contend that it does not control this case because they are not

proposing to construct a structure on, or to make any active use

whatsoever of, the portions of the new lots that derive from lot

28. They contend that the new lots make only passive, not

actual, use of lot 28 -- to satisfy the town's minimum lot size

requirement for the zoning district in which the lots are

situated. At oral argument, the Shamsuddins even suggested they

would be willing to erect fences across the new lots at the

boundary between lot C and lot 28 to prevent the lot 28 portion

of the new lots from deriving any benefit from the use of the

private way.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murphy v. Mart Realty of Brockton, Inc.
205 N.E.2d 222 (Massachusetts Supreme Judicial Court, 1965)
Taylor v. Martha's Vineyard Land Bank Commission
60 N.E.3d 319 (Massachusetts Supreme Judicial Court, 2016)
Greene v. Canny
137 Mass. 64 (Massachusetts Supreme Judicial Court, 1884)
McLaughlin v. Board of Selectmen
664 N.E.2d 786 (Massachusetts Supreme Judicial Court, 1996)
Blue View Construction, Inc. v. Town of Franklin
874 N.E.2d 425 (Massachusetts Appeals Court, 2007)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
JAMES MAGUIRE & Others v. PLANNING BOARD OF HAMILTON & Others., Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-maguire-others-v-planning-board-of-hamilton-others-massappct-2023.