Taylor Construction Inc. v. ABT Service Corp. Inc.

163 F.3d 1119, 42 Cont. Cas. Fed. 77,405, 98 Daily Journal DAR 12901, 98 Cal. Daily Op. Serv. 9222, 1998 U.S. App. LEXIS 31644
CourtCourt of Appeals for the Ninth Circuit
DecidedDecember 21, 1998
DocketNo. 95-35883
StatusPublished
Cited by1 cases

This text of 163 F.3d 1119 (Taylor Construction Inc. v. ABT Service Corp. Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taylor Construction Inc. v. ABT Service Corp. Inc., 163 F.3d 1119, 42 Cont. Cas. Fed. 77,405, 98 Daily Journal DAR 12901, 98 Cal. Daily Op. Serv. 9222, 1998 U.S. App. LEXIS 31644 (9th Cir. 1998).

Opinion

FERGUSON, Circuit Judge:

In this case, a Miller Act surety failed to pay a subcontractor the entire amount due under the bonded subcontract claiming that the Miller Act imposes no duty to pay the subcontractor the amount in the subcontract’s savings clause. The district court disagreed, granting summary judgment against the surety and ordering it to pay the entire amount due under the contract, including under the savings clause. We now affirm because the Miller Act clearly requires a surety to pay the entire amount due under the contract when the prime contractor defaults.

I. BACKGROUND

ABT Service Corporation was the prime contractor on a project at the Idaho National Engineering Laboratory. Pursuant to the Miller Act, 40 U.S.C. §§ 270a-f, defendant International Fidelity Insurance Company issued a payment bond to the prime contractor. The dispute here arises from the surety company’s failure to pay under the Miller Act payment bond.

On April 2, 1992, ABT Service Corporation entered into a subcontract with plaintiff Taylor Construction (Taylor) for Taylor to perform the excavating, utility digging, and foundation work for the project. The subcontract provided that Taylor would be reimbursed for its material, labor, and equipment. What has made this subcontract the center of this appeal is the “savings” provision. The parties agreed in the subcontract as follows:

[1121]*1121FOR THE SUM OF: TOTAL CONTRACT AMOUNT SHALL NOT EXCEED $150,000.00 ANY SAVINGS REALIZED IN THIS .WORK SHALL BE DIVIDED EVENLY BETWEEN THE CONTRACTOR [ABT] AND THE SUBCONTRACTOR [Taylor Construction],

Taylor Construction described the savings clause as an “incentive clause” that would spur fast performance.

Taylor Construction performed the work required in the subcontract and, on a daily basis, submitted to the prime contractor’s superintendent “charge sheets” itemizing the materials, labor, and equipment used on that day. In total, Taylor billed the prime $45,-594 but reduced that to $42,819 after an agreed-upon adjustment, and the prime paid Taylor accordingly. The prime contractor did not, however, pay Taylor the amount required under the subcontract’s savings clause — $41,405.68.1

During the performance of the subcontract, the prime contractor requested Taylor perform some additional unspecified work under a change order. Although Taylor completed the work under that order, the prime did not pay Taylor the $498.00 required under the order. The prime claimed that it did not pay Taylor because Taylor left four hours of sidewalk work uncompleted in the performance of the entire subcontract (not the change order).

On June 16, 1993, Taylor Construction filed this action against both the prime contractor and the surety. Taylor alleged that the prime contractor breached the subcontract and that the surety company thus owed it the amount due under the payment bond. After Taylor moved for summary judgment, the district court granted Taylor’s motion on all issues except attorneys fees from the surety. The court found that both the surety and the prime owed Taylor the $498 on the change order because the prime was not entitled unilaterally to offset that order based on Taylor’s not completing the main project. Furthermore, the court found that the prime owed Taylor $41,405.68 under the savings clause of the contract2 and that the surety owed Taylor that amount because it had bonded the prime contractor under the Miller Act for the subcontract with Taylor.The court found also that both parties owed Taylor prejudgment interest but that only the prime contractor owed Taylor attorneys fees because attorneys fees are not recoverable against a Miller Act surety.

The surety appealed, but the prime did not.

II. STANDARD OF REVIEW

This court reviews a grant of summary judgment de novo. Covey v. Hollydale Mobilehome Estates, 116 F.3d 830, 834 (9th Cir.1997). There are no genuine issues of material fact here, so this court must determine whether the district court correctly applied the relevant substantive law. Id.

III. DISCUSSION

A. Savings Clause

The surety’s main contention on appeal is that it is not required to pay Taylor under the subcontract’s savings clause because the amount owed under that clause is not “labor” or “material” and the Miller Act (the Act) requires payment by the surety only when the prime contractor fails to pay for labor or material. The surety’s reading of the Miller Act is wrong based on both the plain language of the Act and well-established precedent, and we accordingly affirm [1122]*1122the district court’s summary judgment in favor of Taylor.

The Miller Act provides that before a contract exceeding $25,000 for the construction of any federal public work is awarded, the contractor must secure a payment bond “for the protection of all persons supplying labor and material in the prosecution of the work provided for in said contract....” 40 U.S.C. § 270a(a)(2). The Act also provides that any person “who has furnished labor or material in the prosecution of the work provided for in such contract ... and who has not been paid in full therefor ... shall have the right to sue on such payment bond ... for the sum or sums justly due him----” 40 U.S.C. § 270b(a) (emphasis added).

The policy behind the Act is “to provide a surety who, by force of the Act, must make good the obligations of a defaulting contractor to his suppliers of labor and material.” United States ex rel. Sherman v. Carter, 353 U.S. 210, 217, 77 S.Ct. 793, 1 L.Ed.2d 776 (1957). Because the Act is remedial in that the common law did not allow a lien on federal contracts, the Act “is entitled to a liberal construction and application in order ... to protect those whose labor and materials go into public projects.” Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 88 L.Ed. 1163 (1944).

The plain language of the Act provides the quickest answer to the question posed here because it is clear from the face of the Act that Taylor can recover from the surety. Taylor is indisputably entitled to bring suit to recover under the payment bond because Taylor “furnished labor or material in the prosecution of the work.” 40 U.S.C. § 270b(a). What is disputed here is not who can recover but rather what Taylor Construction can recover. Clearly, the “who” is limited to those supplying “labor or material.” The “what” is not so limited and is described simply as “sums justly due.” “Sums justly due” refers back to the term “paid in full” contained in the earlier part of that same sentence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
163 F.3d 1119, 42 Cont. Cas. Fed. 77,405, 98 Daily Journal DAR 12901, 98 Cal. Daily Op. Serv. 9222, 1998 U.S. App. LEXIS 31644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taylor-construction-inc-v-abt-service-corp-inc-ca9-1998.