Theobald-Jansen Electric Co. v. P. H. Meyer Co.

77 F.2d 27, 1935 U.S. App. LEXIS 4481
CourtCourt of Appeals for the Tenth Circuit
DecidedApril 10, 1935
DocketNo. 1163
StatusPublished
Cited by9 cases

This text of 77 F.2d 27 (Theobald-Jansen Electric Co. v. P. H. Meyer Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Theobald-Jansen Electric Co. v. P. H. Meyer Co., 77 F.2d 27, 1935 U.S. App. LEXIS 4481 (10th Cir. 1935).

Opinion

McDERMOTT, Circuit Judge.

P. II. Meyer Company contracted with the United States to install the plumbing, [28]*28heating and electrical system in the Veterans’ Hospital at Albuquerque, the contractor to furnish all materials and labor therefor. To guarantee the performance of such contract, the Meyer Company as principal atad the United States Guarantee Company as surety, executed a bond conditioned on the faithful performance of the contract and the prompt payment “to all persons supplying the principal with labor and materials in the prosecution of the work.” The bond was that required by section 270, tit. 40 USCA; and in due season suit was brought by the United States against Meyer Company and its surety, as authorized by that section, for the use and benefit of those claiming to have furnished “labor and materials” to the contractor.

Appellant filed its petition in intervention, as authorized by the same section. The trial court sustained a demurrer to the petition; appellant electing to stand thereon, the petition was dismissed. There being no challenge of the faithful performance of the contract by the United States, we are confronted with but one question: Does the petition allege that appellant furnished “labor and materials” in the prosecution of the work for which it has not been paid ? If so, it may recover; if not, it may not, for this is a statutory action on a public bond, and unless the petition states a cause of action for labor and materials furnished in this construction, it is not within the terms of either the statute or the bond; moreover the trial court is without jurisdiction of the controversy, for appellant and the Meyer Company are both citizens of Kentucky.

Appellant would confine our examination of its petition to a statement; in one sentencé, in the nature of a conclusion, that the intervenor “furnished the materials and labor necessary for the installation, construction and completion of the electrical work,” etc. Appellant puts to one side all the rest of its petition as unnecessary and embarrassing background. But we are not content to rest the case on this fragment of a sentence, since an examination of the entire petition discloses affirmatively that the labor and material bills have been paid and that the object of this suit is to recover from the Meyer Company and its surety the fixed profit appellant was entitled to receive from the Meyer Company, and it in turn from another surety company, over and above the cost of labor and materials covered by the bond.

The petition in intervention alleges that the Meyer Company contracted with the United States “to furnish all the labor and materials and to perform all the work required for and in the installation of the plumbing, heating and electrical systems required by the United States of America in connection with the construction of certain portions of the United States Veterans’ Hospital at Albuquerque, New Mexico”; that the bond sued on was given to guarantee the performance of that contract. “That the said contract between the defendant P. H. Meyer Company and United States of America has been fully performed and the work thereunder has been fully completed, approved and accepted by the 'said United States of America, and that final settlement upon said contract with the said defendant was authorized on August 19, 1932.”

The petition then alleges:

“That subsequently to the execution of the said contract and bond hereinabove described, and [the] said defendant, P. H. Meyer Company, negotiated with this intervenor, Theobald-Jansen Electric Company, for the furnishing of the necessary labor to construct and install the electrical system and works in the said contract provided for; that in the said negotiations the said defendant P. H. Meyer Company, represented to plaintiff that it had entered into an agreement with the United States Fidelity & Guaranty Company whereunder the said guaranty company was bound to furnish all materials and labor necessary to the construction and completion of the electrical work provided for in the said contract between P. H. Meyer Company and the United States of America; but that the said United States Fidelity & Guaranty Company not being in a position to personally do the said work or furnish the necessary labor or materials therefor, in turn entered into an agreement with the defendant, P. H. Meyer Company, where-under the latter company should and would furnish the said materials and labor and should fully complete the installation and construction of said electrical system and electrical work in consideration of the payment by the said guaranty company of the cost of all materials and labor, plus 10% calculated as overhead and 10% to be calculated and known as net profit; that iritervenor, Theobald-Jansen Electric Company, relying upon the representations so made to it by the said defendant, P. H. [29]*29Meyer Company,- and the security thereby, afforded, and acting in good faith, entered into an agreement with the said defendant, P. H. Meyer Company, whereunder it undertook to install and complete the construction of the said electrical work required by and in conformity with the provisions of the contract with the United .States of America, in consideration of the payment to it of one-half of the said calculated overhead of 10% and of one-half of the said 10% net profit, and further to furnish a foreman for said construction work at a cost of $60.00 per week, the salary of said foreman and all labor and materials going into and necessary for the completion of said electrical work to be paid for by the said defendant, P. II. Meyer Company; that in order to confirm the said agreement, the said intervenor and the said defendant, P. H. Meyer Company, executed a written memorandum, in words and figures as follows, to-wit:
“January 28, 1932.
“P. H. Meyer Co., 635 S. Preston St., Louisville, Ky.
“Gentlemen: With reference to our conversation in regard to the completion of the electrical work for the U. S. Veterans Hospital, located at Albuquerque, N. Mexico, and in accordance with the contract you have with the Bonding Company to complete the work on the basis of 10% overhead plus 10% profit, we offer the following proposition.
“We agree to complete the installation of the electrical work as per plans and specifications, also furnish a foreman for $60.00 per week, his salary and all other labor and material to be paid for by your company.
“For the services rendered as above stated we are to receive a compensation consisting of one-half (1/2) of the net profits upon completion of the above job.
“Thanking you for the opportunity of submitting a proposition for this work, and trusting to be favored with your order, “Yours very truly,
“Theobald-Jansen Electric Co.,
“John Jansen, Treasurer.
“Accepted P. H. Meyer & Company by P. H. Meyer, Jr.”

It is then alleged that the cost of the work done was $64,800.22 exclusive of the ten per cent overhead and profit. The suit is not for the $64,800.22 or any part thereof, but is for $6,804.02, one-half the overhead and profit. Nothing could make it dearer that the labor and materials covered by the bond have been paid for and that this suit is for the fixed profit on the job. The petition contains an allegation that the $6,-804.02 represents services, labor,' and expenses which went into construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
77 F.2d 27, 1935 U.S. App. LEXIS 4481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/theobald-jansen-electric-co-v-p-h-meyer-co-ca10-1935.