TADCO Construction Corp. v. Dormitory Authority

700 F. Supp. 2d 253, 2010 U.S. Dist. LEXIS 26117
CourtDistrict Court, E.D. New York
DecidedMarch 19, 2010
Docket1:08-cr-00073
StatusPublished
Cited by45 cases

This text of 700 F. Supp. 2d 253 (TADCO Construction Corp. v. Dormitory Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TADCO Construction Corp. v. Dormitory Authority, 700 F. Supp. 2d 253, 2010 U.S. Dist. LEXIS 26117 (E.D.N.Y. 2010).

Opinion

MEMORANDUM AND ORDER

TRAGER, District Judge:

This case arises out of a troubled construction contract between TADCO Construction Corporation (“TADCO”) and the Dormitory Authority of the State of New York (“DASNY”) to build a new dormitory facility on Staten Island. Plaintiff TADCO alleges multiple breach of contract claims against DASNY, and further alleges a due process violation under 42 U.S.C. § 1983 *257 stemming from purportedly defamatory comments made by DASNY during its termination of the contract with TADCO and from DASNY’s failure to pay TADCO promptly for work performed. Plaintiff Thomas DeMartino (“DeMartino”), TAD-CO’s on-site superintendent and management representative, additionally asserts federal and state claims of false arrest, malicious prosecution and abuse of process, claiming that DASNY employees Tyrone Middleton, Pat Cinelli, Jack Kemp and John Doe improperly had him arrested for trespassing at the job site on two separate occasions. Defendants have moved to dismiss all of plaintiffs’ federal claims as well as DeMartino’s state law claims, and have requested that this court decline to exercise supplemental jurisdiction over TADCO’s state law claims. For the reasons explained below, this motion is granted in part and denied in part.

Background

(1)

Contractual Disputes between TADCO and DASNY

a. Project Delays

The following facts are drawn from plaintiffs pleadings and, for purposes of this motion, are presumed to be true. In May 2005, defendant DASNY began soliciting bids for a new ten-bed residence building for the Staten Island Developmental Disabilities Services Office (the “project”). Compl. ¶ 14. The project was structured as a “multi-prime” project, meaning that four prime contractors would perform discrete segments of the project under the direct supervision of DASNY. Id. at ¶¶ 15-16. Four separate prime contracts were therefore awarded: one for general construction work, one for mechanical work, one for electrical work and one for plumbing work. Id.

Plaintiff TADCO, a general construction contractor, bid on and was awarded the contract for general construction work (the “contract”) around June 15, 2005. Id. at ¶¶ 17, 23. Prior to the instant dispute, TADCO had often been awarded state and municipal public works contracts and had previously worked with DASNY several times. Id. at ¶ 13. The contract specified that the project was to be completed by September 29, 2006. See Compl., Ex. A at 2 (contract between TADCO and DASNY).

However, the project was plagued with delays and problems from the outset. Plaintiffs generally attribute these delays to DASNY’s funding problems and DAS-NY’s poor management of the other prime contractors. Id. at ¶¶ 19-24. More specifically, TADCO points to several delays that were caused by events outside of its control and within DASNY’s control. First, plaintiffs allege that their commencement of the project was delayed by approximately five months when DASNY unexpectedly required TADCO to perform some up-front work not included in the plans and specifications, including building a construction fence around the jobsite, id. at ¶¶ 25-29, and probing and underground radar work to locate existing utility lines, id. at ¶¶ 30-34. As a result of requiring this extra work, DASNY agreed to extend the completion date of the project by six weeks, from September 29, 2006, to November 15, 2006. Id. at ¶ 35. Then, a major design defect in the framing of the building set back TADCO’s progress on the project further throughout June and July 2006. Id. at ¶ 41.

Further delays ensued as a result of the slow progress of the mechanical, electrical and plumbing work contractors (collectively, the “MEP contractors”). Id. at ¶¶ 42-50. TADCO believed the MEP contractors’ deficient performance was the fault of poor supervision and direction on the part *258 of DASNY, and approached DASNY with concerns over the progression of the project several times. Id. at ¶ 51. In a September 13, 2006 meeting, TADCO explains that DASNY “acknowledged its responsibility to provide overall project management and coordination,” promised to provide better supervision and coordination of the four prime contractors in the future and again extended the project completion date, this time until December 7, 2006. Id. at ¶ 52. Nevertheless, problems with the MEP contractors’ performance continued throughout the fall of 2006. These problems led DASNY, in early December 2006, to extend the project completion date to January 11, 2007. Id. at ¶ 61.

At the same time these MEP delays were occurring, a dispute erupted between DASNY and TADCO regarding a contract provision that required TADCO to backfill open trenches at the jobsite with soil taken from on-site. Id. at ¶ 62. At some point, apparently during the summer of 2006 (the complaint specifies only “prior to September 2006”), TADCO discovered that the soil at the site was not suitable for use as backfill because of its high moisture content. Id. at ¶ 63. TADCO attributed its late discovery of this moisture problem to DASNY’s failure to provide TADCO with any soil boring logs or geotechnical data. Id. at ¶ 64. Therefore, it asked DASNY to resolve the problem during fall of 2006. However, according to TADCO, DASNY was simply non-responsive. Id. at ¶¶ 66-73.

b. Thomas DeMartino’s Arrests

In November, this unresolved backfill problem provoked a disagreement between an employee of DASNY and an employee of TADCO. One of DASNY’s field representatives and now a named defendant, Tyrone Middleton, ordered DeMartino, TADCO’s onsite project superintendent, to cover the open trenches at the jobsite with wood planks on November 9, 2006. Id. at ¶¶ 75-76. DeMartino refused, explaining that this work was not specified in the contract and would require extra labor, materials, supplies and equipment. Id. at ¶¶ 77-78. Middleton responded this same day by lodging a criminal complaint against DeMartino with the state police officers assigned to the facility, claiming that DeMartino was trespassing. Id. at ¶¶ 80, 134. The complaint additionally alleges that Pat Cinelli, the Director of DASNY’s Statewide Utilities Unit, and/or Jack Kemp, the Chief of Construction Contracts for DASNY, “approved of and authorized” Middleton’s actions in having DeMartino arrested. Id. at ¶ 139. As a result of Middleton’s complaint, DeMartino was arrested, taken to the local precinct and issued a criminal summons for trespassing. Id. at ¶ 82.

Apparently, however, this arrest did not dissuade DeMartino from returning to the job site. In early January 2007, Middleton or some other DASNY personnel lodged a second criminal complaint against DeMartino, who was once again arrested for trespassing at the job site. Id. at ¶¶ 84-86. DeMartino spent one night in jail and was subsequently charged with criminal trespassing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
700 F. Supp. 2d 253, 2010 U.S. Dist. LEXIS 26117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tadco-construction-corp-v-dormitory-authority-nyed-2010.