Taber Partners I v. Insurance Co. of North America, Inc.

875 F. Supp. 81, 1995 U.S. Dist. LEXIS 1809, 1995 WL 58056
CourtDistrict Court, D. Puerto Rico
DecidedFebruary 3, 1995
DocketCiv. 91-1220 (JP), 91-1211 (JP)
StatusPublished
Cited by1 cases

This text of 875 F. Supp. 81 (Taber Partners I v. Insurance Co. of North America, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Taber Partners I v. Insurance Co. of North America, Inc., 875 F. Supp. 81, 1995 U.S. Dist. LEXIS 1809, 1995 WL 58056 (prd 1995).

Opinion

OPINION & ORDER

PIERAS, District Judge.

The Court has before it defendant’s two motions for partial summary judgment (docket Nos. 121, 122), plaintiff’s oppositions (docket Nos. 131, 136), and the respective supplements to their motions. 1 The case at bar is a diversity action filed by Taber Partners I (“Taber”) against Merit Builders, Inc. (“Merit”) 2 for the alleged breach of three construction contracts and the corresponding damages. The three contracts in dispute deal with the renovation and expansion of the Ambassador Plaza Hotel & Casino (“Ambassador”) located in San Juan, Puerto Rico. Merit argues in both motions that the Puerto Rico Supreme Court decision in Constructora Bauzá v. García López, 91 J.T.S. 99 (1991), mandates judgment in its favor as to all claims in the complaint dealing with apparent construction defects and damages for delays in the project. Taber argues that the principles established in Constructora Bauzá are inapplicable to the ease at bar because the three construction contracts specifically set out the duties and responsibilities of the parties regarding apparent defects and substantial completion. Substantially for the same reasons provided by Taber, and as explained below, Merit’s motions for partial summary judgment are hereby DENIED.

I. UNCONTESTED FACTS

For purposes of deciding the motions for partial summary judgment, and taking into consideration the statements submitted by Merit and Taber as to uncontested facts, a careful review of the record reveals the following pertinent uneontested facts:

1) On January 18, 1989, Taber and Merit entered into a cost plus construction contract for the renovation and expansion of the Ambassador. Taber is the owner of the Ambassador, while Merit is a construction company which served as the general contractor for the hotel’s renovation and expansion project under the contract. On July 6, 1989, Taber and Merit entered into a second contract under a fixed price and for the same project as the prior contract. These two contracts are collectively known by the parties as the “Tower Contract.” The Tower Contract, among other things, called for the construction of a ninety-one (91) all suite tower, a parking garage, and a casino shell.

2) On February 9, 1990, Taber and Merit entered into a “Specialty Contract,” which encompassed the necessary finish work for the casino, casino lounges, hotel lobby, and the Chinese and Italian restaurants.

3) On December 1, 1990, Taber and Merit entered into a third agreement, known as the “Interim Agreement.”- In the Interim Agreement the parties set out in writing the manner in which they would resolve certain differences in order to complete the work under the Tower Contract as soon as possible. Before signing the Interim Agreement, Taber had refused to pay Merit’s Application for Payment No. 15 and No. 16 claiming that Merit had failed to conduct its work in an acceptable workmanlike manner and failed to achieve timely Substantial Completion of the Tower Contract. In light of Taber’s refusal to make the requested payments, Merit had filed a demand for arbitration and declaratory relief with the Caribbean Regional Office of the American Arbitration Association. In its demand for arbitration, Merit sought to obtain a declaration that would allow it to suspend performance under the Tower Con *83 tract until Taber paid the requested amounts for work already performed. By signing the Interim Agreement, Taber agreed to pay Merit the outstanding applications for payment (No. 15 and 16), and Merit agreed to file a joint stipulation to stay the arbitration proceedings until the date of Substantial Completion for the Tower Contract. Among other things, the parties also agreed that:

a. As of December 1, 1990, Merit had not achieved Substantial Completion of the Tower Contract.

b. The Substantial Completion date for the Tower Contract, as extended by the appropriate change orders, was October 17, 1990.

4) Both the Tower Contract and the Specialty Contract were prepared on Document A101 of the American Institute of Architects (“AIA”). This contract incorporated in its entirety AIA’s General Conditions for Construction Contracts (AIA Document A201). The contracts between Taber and Merit also included two sets of specially tailored conditions, and a group of professionally drawn specifications and plans. AIA’s general conditions included in the Tower and Specialty contracts provide in part the following:

4.3 SUPERVISION AND CONSTRUCTION PROCEDURES
4.3.3 The Contractor shall not be relieved from his obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of the Architect in his administration of the Contract, or by inspections, tests or approvals required or performed under Paragraph 7.7 by persons other than the Contractor.
7.6 RIGHTS AND REMEDIES
7.6.2 No action or failure to act by the Owner, Architect or Contractor shall constitute a waiver of any right or duty afforded any of them under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach thereunder, except as may be specifically agreed in writing.
9.4 CERTIFICATES FOR PAYMENT
9.4.2 However, by issuing a Certificate for Payment, the Architect shall not thereby be deemed to represent that he has made exhaustive or continuous on-site inspections to check the quality or quantity of the Work or that he has reviewed the construction means, methods, techniques, sequences or procedures, or that he has made any examination to ascertain how or for what purpose the Contractor has used the moneys previously paid on account of the Contract Sum.
9.5 PROGRESS PAYMENTS
9.5.5 No Certificate for a progress payment, nor any progress payment, nor any partial or entire use or occupancy of the Project by the Owner, shall constitute an acceptance of any Work not in accordance with the Contract Documents.
9.8 SUBSTANTIAL COMPLETION
9.8.1 When the Architect on the basis of an inspection determines that the Work or designated portion thereof is substantially complete, he will then prepare a Certificate of Substantial Completion which shall establish the Date of Substantial Completion, shall state the responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, and insurance, and shall fix the time within which the Contractor shall complete the items listed therein.

5) Change order No. 248, which reduced the sum owed under the Tower and Specialty contracts by fifty eight thousand eight hundred and thirty four dollars ($58,834.00), was dated December 3, 1990, and signed by Merit’s representative on December 5, 1990. The effect of the change order was to transfer the responsibility for certain millwork from Merit to Taber.

II. THE RULE 56 STANDARD

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taber Partners I v. Insurance Co. of North America
926 F. Supp. 36 (D. Puerto Rico, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
875 F. Supp. 81, 1995 U.S. Dist. LEXIS 1809, 1995 WL 58056, Counsel Stack Legal Research, https://law.counselstack.com/opinion/taber-partners-i-v-insurance-co-of-north-america-inc-prd-1995.