Systemaire, Inc. v. St. Charles County

432 S.W.3d 783, 2014 WL 2108953, 2014 Mo. App. LEXIS 562
CourtMissouri Court of Appeals
DecidedMay 20, 2014
DocketNo. ED 100475
StatusPublished
Cited by5 cases

This text of 432 S.W.3d 783 (Systemaire, Inc. v. St. Charles County) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Systemaire, Inc. v. St. Charles County, 432 S.W.3d 783, 2014 WL 2108953, 2014 Mo. App. LEXIS 562 (Mo. Ct. App. 2014).

Opinion

ROBERT G. DOWD, JR., Judge.

St. Charles County appeals from the trial court’s grant of partial summary judgment in favor of Systemaire, Inc. (“Systemaire”). St. Charles County argues the trial court erred in entering partial summary judgment awarding penalty interest and attorney’s fees against St. Charles County for failure to make final payment of retainage to Systemaire pursuant to Section 34.057. We reverse and remand.

Systemaire contracted with St. Charles County to install two 500 ton fiberglass cooling towers at the St. Charles County Family Arena for $265,000.00. The contract included options to have Sys-temaire also install a basin heater for $10,000.00 and an electric water level control for $23,000.00. During the installation, St. Charles County exercised these options and had Systemaire install the basin heater and electric water level control.

In addition, Systemaire entered into contracts to paint structural steel for $2,500.00 and to furnish and install a heat trace for $24,735.00. Systemaire installed the cooling towers, basin heater, electric water level control, and heat trace and painted the structural steel for St. Charles County.

Subsequently, on March 29, 2012, Syste-maire demanded payment from St. Charles County for the total cost of the options and other projects, which was $60,225.00. St. Charles County failed to pay.

St. Charles County also withheld $26,500.00 in retainage. St. Charles County contended Systemaire failed to comply with contractual conditions precedent for final payment of retainage and is not entitled to pursue interest and attorney’s fees.

In response to St. Charles County’s failure to pay, Systemaire filed a petition for breach of contract, alleging damages of $86,725.00, plus interest and attorney’s fees. Systemaire alleged St. Charles County improperly withheld the retainage of ten percent of the value of the contract totaling $26,500.00, excluding the options and extra work. Thus, the $86,725.00 represented the $26,500.00 in retainage plus the $60,225.00 in options and other additions. Systemaire maintained St. Charles County failed and refused to pay the re-tainage after the completion of the work and the submission of the application for payment. Systemaire also included a count for breach of warranty ex contractu, alleging damages in the amount of $60,225.00, plus interest and attorney’s fees. Systemaire also included a claim for breach of the covenant of good faith and fair dealing. St. Charles County filed an answer.1

[785]*785Systemaire subsequently filed a motion for partial summary judgment, requesting that the trial court enter summary judgment on its claim for breach of contract and breach of warranty ex contractu in the amount of $86,285.00,2 plus interest, costs, and attorney’s fees. St. Charles County filed a response.

The trial court subsequently entered its judgment granting Systemaire’s motion for summary judgment on its breach of contract claim, but denying its motion for summary judgment on its breach of warranty ex contractu claim. The trial court entered judgment in the amount of $60,225.00 for the principal,3 $8,583.80 for the interest, and $32,376.70 for the attorney’s fees, for a total of $101,185.00.

Thereafter, Systemaire voluntarily dismissed its claims for breach of warranty ex contractu and for breach of the covenant of good faith and fair dealing without prejudice.4 This appeal follows.

Appellate review of a trial court’s grant of summary judgment is essentially de novo. ITT Commercial Fin. Corp. v. Mid-America Marine Supply Corp., 854 S.W.2d 371, 376 (Mo. banc 1993). We will review the record in the light most favorable to the party against whom judgment was entered. Id. We accord the non-mov-ant the benefit of all reasonable inferences from the record. Id. The criteria on appeal for testing the propriety of summary judgment are no different from those which should be employed by the trial court to determine the propriety of sustaining the motion initially. Id. We will uphold summary judgment on appeal only where there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. Id.

In its sole point, St. Charles County argues:

the trial court erred in entering partial summary judgment awarding penalty interest and attorney’s fees against St. Charles County for failure to make final payment of retainage to Systemaire pursuant to Section 34.057 ... because Sections 34.057.1(4) and (8)(a) ... authorized St. Charles County to require contractually that final retainage payment to Systemaire be made only upon provision of as-built piping schematics and labor and material warranties to St. Charles County, in that Systemaire never provided the schematics and warranties to St. Charles County.

We initially note that the Prompt Pay Act, Section 34.057, promotes timely payment of contractors, subcontractors, and suppliers on contracts with public owners for public works construction projects. Jerry Bennett Masonry, Inc. v. Crossland Const. Co., Inc., 171 S.W.3d 81, [786]*78689 (Mo.App.S.D.2005). This law requires public owners and contractors to make prompt payments and limits amounts withheld as retainage. Id. The Prompt Pay Act is considered a remedial statute and therefore requires liberal interpretation. Id.

Section 34.057.1 provides:

... all public works contracts ... shall provide for prompt payment by the public owner to the contractor ... in accordance with the following:
(4) The public owner shall pay the re-tainage, less any offsets or deductions authorized in the contract or otherwise authorized by law, to the contractor after substantial completion of the contract work and acceptance by the public owner’s authorized contract representative .... Such payment shall be made within thirty days after acceptance, and the invoice and all other appropriate documentation and certifications in complete and acceptable form are provided, as may be required by the contract documents. If at that time there are any remaining minor items to be completed, an amount equal to two hundred percent of the value of each item as determined by the public owner’s representative shall be withheld until such items are completed;
(8) The public owner shall make final payment of all moneys owed to the contractor, less any offsets or deductions authorized in the contract or otherwise authorized by law, within thirty days of the due date. Final payment shall be considered due upon the earliest of the following events:
(a) Completion of the project and filing with the owner of all required documentation and certifications, in complete and acceptable form, in accordance with the terms and conditions of the contract.

Thus, the public owner must make final payment of all moneys owed to the contractor within thirty days of the due date. Leo Journagan Const. Co., Inc. v. City Utilities of Springfield, Mo.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
432 S.W.3d 783, 2014 WL 2108953, 2014 Mo. App. LEXIS 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/systemaire-inc-v-st-charles-county-moctapp-2014.