SYMBIONT SCIENCE, ENGINEERING AND CONSTRUCTION, INC. v. GROUND IMPROVEMENT SERVICES, INC.

CourtDistrict Court, D. New Jersey
DecidedFebruary 1, 2024
Docket3:22-cv-04905
StatusUnknown

This text of SYMBIONT SCIENCE, ENGINEERING AND CONSTRUCTION, INC. v. GROUND IMPROVEMENT SERVICES, INC. (SYMBIONT SCIENCE, ENGINEERING AND CONSTRUCTION, INC. v. GROUND IMPROVEMENT SERVICES, INC.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SYMBIONT SCIENCE, ENGINEERING AND CONSTRUCTION, INC. v. GROUND IMPROVEMENT SERVICES, INC., (D.N.J. 2024).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

SYMBIONT SCIENCE Civ. No. 22-4905 (RK)(JBD) ENGINEERING AND CONSTRUCTION, INC., et al., OPINION Plaintiffs,

v.

GROUND IMPROVEMENT SERVICES, INC., et al.,

Defendants,

GEOPIER FOUNDATION COMPANY, INC., et al.

Third-Party Defendants.

This complex civil action arises from damages sustained in connection with the design and construction of an anaerobic digestion and biogas production facility in Trenton, New Jersey. Plaintiff Symbiont Science, Engineering and Construction, Inc. (“Symbiont”) contracted with non-party Trenton Biogas, LLC to provide engineering, procurement, and construction management services for the facility. Symbiont, in turn, contracted with other entities for, among other things, geotechnical engineering and soil improvement design services. Following construction, Trenton Biogas raised concerns with excessive settlement of the facility’s component tanks and mediation ensued. In February 2022, Symbiont settled with Trenton Biogas for more than $11.7 million to address the defects. Thereafter, Symbiont and its insurers filed this suit in subrogation against two parties that had been contracted to help design a soil improvement system to prevent the tanks from settling beyond an acceptable level. Symbiont alleges that

those defendants are responsible for the defects and ultimately, for the payments that Symbiont’s insurers paid to Trenton Biogas, as well as for millions of dollars in additional damages that Symbiont claims it has incurred or will incur. Defendants, in turn, impleaded additional parties seeking contribution for any assessed liability. The core objective of this case, then, is to allocate fault and financial responsibility amongst the parties for the construction issues at the facility. Pretrial discovery to

that end is complex, voluminous, and ongoing. Presently before the Court is a motion to intervene filed by non-party Denali Water Solutions LLC (“Denali”). Denali played no role in the design or construction of the Trenton Biogas facility and has no financial interest in the outcome of this litigation. Since 2020, however, Denali itself has been embroiled in separate litigation in New Jersey state court with Trenton Renewable Power, LLC (“TRP”), a Trenton Biogas affiliate, in connection with a contract that called for Denali to

supply source-separated organic waste as input material for the facility. Denali seeks to intervene not for the purpose of asserting a claim or defense of its own in this case. Denali also acknowledges that the ultimate disposition of this suit will not affect its interests. Interested instead in the information that will be exchanged during discovery, Denali seeks to intervene for what it says is the more “limited

2 purpose” of protecting its asserted informational interests that could affect its own defenses in the separate state court litigation. Denali specifically requests to play “an observatory role” in these proceedings; to be “notified of all electronic filings and

correspondence”; to be “permitted to observe all proceedings[,] including but not limited to depositions, hearings, and on and off record conferences”; and to be “permitted to review discovery exchanged in this matter.” [Dkt. 92-3] (“Denali Mov. Br.”) at 4. The Court has received extensive briefing on the motion and held oral argument on November 29, 2023. For the following reasons, the Court will deny

Denali’s motion to intervene.1 I. BACKGROUND Denali seeks to intervene in this federal action to obtain information that may help support its defenses in the state court litigation just described. The Court therefore summarizes the two actions in more detail. A. This Action The following facts are derived from Symbiont’s second amended complaint

and, for present purposes only, are assumed as true. As noted above, Symbiont and

1 This opinion and the accompanying order resolve a non-dispositive motion pursuant to 28 U.S.C. § 636(b). See, e.g., Dewey v. Volkswagen Aktiengesellschaft, 558 F. App’x 191, 198 n.6 (3d Cir. 2014) (not precedential) (“[T]he Magistrate Judge considered the motion [to intervene] as a non-dispositive motion under 28 U.S.C. § 636(b), which empowers her to do so even absent consent of the parties.”); In re Gabapentin Patent Litig., 321 F. Supp. 2d 653, 661 (D.N.J. 2004) (“A ruling on a motion to intervene is typically treated as non-dispositive.”).

3 Trenton Biogas entered into an Engineering, Procurement and Construction (“EPC”) contract, pursuant to which Symbiont provided engineering, procurement, and construction management services in connection with the anaerobic digestion and

biogas production facility in Trenton. Second Amended Complaint, [Dkt. 23] (“SAC”) ¶ 15. The contract contemplated the construction of four large, above-ground tanks—three digester tanks and one buffer tank. Id. ¶ 18. In January 2018, third- party defendant GZA GeoEnvironmental, Inc. (“GZA”) issued a geotechnical engineering evaluation report concerning the facility, which reported that the ground where the tanks would be installed needed to be stabilized and reinforced

because the existing near-surface fill layer was unsuitable to support the tanks’ foundations. Id. ¶¶ 20-21. Accordingly, in February 2018, Symbiont and defendant Ground Improvement Services, Inc. (“GIS”) entered into a contract under which GIS provided soil improvement design services to ensure that the tanks would not settle beyond an acceptable level. Id. ¶¶ 22-24. GIS, in turn, contracted with defendant GeoStructures of Virginia, Inc. (“GeoStructures”) to assist with that endeavor. Id. ¶ 25.

Thereafter, in August 2018, GIS and its subcontractors completed the soil improvement system. SAC ¶¶ 32-33. As part of its work, GIS completed a load test and informed Symbiont that the test complied with the settlement requirements. Id. ¶¶ 33-34. Thereafter, another contractor (not a party to this action) constructed concrete floor slabs for the tanks under a contract with Symbiont, and another

4 contractor (also not a party to this action) erected the four tanks under a direct contract with Trenton Biogas. Id. ¶ 35. The following spring, from March 2019 to May 2019, the tanks were tested by

filling them with water to their operating capacity. Id. ¶ 36. The specifics of the ensuing design and construction issues are immaterial to Denali’s motion to intervene; it suffices for these purposes to say that beginning with the initial tests and continuing for many months, the tanks settled in the soil to an unacceptable level, causing the need for expensive and time-consuming remediation. See generally id. ¶¶ 36-53.

As a result of these issues, Trenton Biogas placed Symbiont on notice of a dispute under the EPC contract, and the parties engaged in mediation. SAC ¶¶ 54- 55. In February 2022, the parties settled and Symbiont agreed to pay Trenton Biogas $11.715 million in exchange for a release of all of Trenton Biogas’s claims relating to the settlement of the digester tanks and buffer tank. Id. ¶ 56. Symbiont’s insurers assumed responsibility for this payment, and Symbiont alleges that it sustained additional losses, costs, and expenses of more than $3.285 million

beyond what its insurers paid to Trenton Biogas, and that it faces additional non- released claims by Trenton Biogas, totaling more than $4 million, for additional alleged damages that defendants caused. Id. ¶¶ 57-61. Symbiont and its insurers thereafter sued GIS and GeoStructures in this Court, asserting claims for, inter alia, breach of contract, negligence, professional

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liberty Mutual Insurance Company v. Treesdale, Inc.
419 F.3d 216 (Third Circuit, 2005)
United States v. Wecht
484 F.3d 194 (Third Circuit, 2007)
Bond v. Utreras
585 F.3d 1061 (Seventh Circuit, 2009)
United States v. Stewart
321 F. Supp. 2d 652 (D. Maryland, 2004)
Dewey v. Volkswagen Aktiengesellschaft
558 F. App'x 191 (Third Circuit, 2014)
King v. Governor of the State of New Jersey
767 F.3d 216 (Third Circuit, 2014)
North Jersey Media Group Inc. v. United States
836 F.3d 421 (Third Circuit, 2016)
Seneca Resources Corp. v. Township of Highland
863 F.3d 245 (Third Circuit, 2017)
AT & T Corp. v. Sprint Corp.
407 F.3d 560 (Second Circuit, 2005)
United States v. W.R. Grace & Co.-Conn.
185 F.R.D. 184 (D. New Jersey, 1999)
In re "Agent Orange" Product Liability Litigation
96 F.R.D. 582 (E.D. New York, 1983)
Harris v. Pernsley
820 F.2d 592 (Third Circuit, 1987)
Brody v. Spang
957 F.2d 1108 (Third Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
SYMBIONT SCIENCE, ENGINEERING AND CONSTRUCTION, INC. v. GROUND IMPROVEMENT SERVICES, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/symbiont-science-engineering-and-construction-inc-v-ground-improvement-njd-2024.