Sutton v. Vee Jay Cement Contracting Co.

37 S.W.3d 803, 2000 Mo. App. LEXIS 1901, 2000 WL 1847653
CourtMissouri Court of Appeals
DecidedDecember 19, 2000
DocketED 77515
StatusPublished
Cited by27 cases

This text of 37 S.W.3d 803 (Sutton v. Vee Jay Cement Contracting Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sutton v. Vee Jay Cement Contracting Co., 37 S.W.3d 803, 2000 Mo. App. LEXIS 1901, 2000 WL 1847653 (Mo. Ct. App. 2000).

Opinion

MARY RHODES RUSSELL, Judge.

Larry Sutton (“Claimant”) appeals from a workers’ compensation award issued by the Labor and Industrial Relations Commission (“Commission”), asserting that the Commission erred in: (1) failing to award him interest on a past due payment of temporary total disability benefits; (2) refusing to award him future medical benefits; (3) inaccurately doubling a portion of a previous temporary award; and (4) declining to find him permanently and totally disabled. We affirm in part, and reverse and remand in part.

At the time of the injury that forms the basis for Claimant’s workers’ compensation claim, he was employed as an iron-worker for Vee Jay Cement Contracting Company (“Employer”). While working for a previous employer, Claimant sustained work-related injuries to his lower back in 1983, 1984, and 1985, which result *806 ed in the removal of two discs and a spinal fusion. As a result of these injuries, Claimant missed approximately two and one-half years of work. He returned to work briefly as an ironworker in 1985, but then began working at a gun shop. In 1994, he reactivated his union card and resumed employment as an ironworker.

On July 27, 1994, while working for Employer, Claimant re-injured his back attempting to avoid being struck by a chute used to pour concrete. Following the injury, he saw various doctors at Employer’s request and others on his own volition. Employer paid him temporary total disability benefits in the amount of $476.28 per week from July 28, 1994 through October 24, 1994. Thereafter, Claimant filed a hardship petition seeking to continue the temporary total disability benefits and further medical treatment. Following a hearing on this matter, an Administrative Law Judge (“ALJ”) in the Division of Workers’ Compensation issued a temporary award on August 5, 1995 ordering Employer to provide Claimant with a myelogram and post-myelogram CT Scan. The ALJ, however, reserved ruling on the claim for temporary total disability, as well as any determination of permanent partial disability, pending results of these diagnostic tests and the possible receipt of further evidence.

A follow-up hearing was scheduled for December 4, 1995. At the time of the hearing, Employer had failed to provide Claimant with the myelogram and post CT Scan as ordered by the ALJ. Instead, Employer sent Claimant to get a second opinion because it felt there was no basis for the ALJ’s prior ruling. As a result of Employer’s failure to comply with the pri- or temporary award, the ALJ struck all evidence offered by Employer at the second hearing, declared that Employer forfeited the right to have any input in the medical care of Claimant, and ordered Claimant under the care of his own physician. Following the hearing, the ALJ entered a temporary award on December 19, 1995 ordering Employer to retroactively pay Claimant temporary total disability benefits from October 24, 1994 until December 4, 1995, the date of the hearing, at the rate of $476.28 per week for a total of $27,624.24 in temporary total disability benefits. The ALJ declared that Claimant was entitled to future temporary total disability benefits in the amount of $476.28 per week from December 4, 1995 until his physician determined in writing that he reached maximum medical improvement or upon further order of the Division of Workers’ Compensation. The ALJ also awarded Claimant $1,280.75 in past medical benefits for the medical tests previously ordered, as well as all reasonable costs of recovery in the matter.

Employer filed an application for review with the Commission, which was denied. Employer then filed a motion to reconsider, which the Commission also denied. Thereafter, Employer filed an appeal with this court that was dismissed because Employer was not permitted to appeal from a temporary award under the circumstances. See Sutton v. Vee-Jay Cement Contracting Co., 937 S.W.2d 334 (Mo.App.1996).

Employer did not pay Claimant any of the benefits awarded by the ALJ until February 26, 1997, which was after this court issued its mandate. At that time, Employer paid Claimant a total of $58,106.16, which represented his past due temporary total disability benefits from October 24, 1994 through the date of the payment. No interest was tendered for these benefits. On March 5, 1997, Employer began paying Claimant future temporary total disability benefits in the amount of $476.28 per week.

Following the dismissal of Employer’s appeal, the Division of Workers’ Compensation conducted a third hearing on the matter. The ALJ issued a temporary award on December 19,1997 ordering Employer to pay specified unpaid medical bills that were reasonable and necessary for Claimant’s treatment. The ALJ also ordered Employer to pay for additional med *807 ical care reasonably required to relieve Claimant from the effects of his injury. The ALJ declined to make a finding as to Claimant’s entitlement to interest on the payments required by the December 19, 1995 award because Claimant did not identify that as an issue at the hearing. The ALJ, however, noted “for the benefit of the parties” that, under section 287.160.3 RSMo 1994, 1 when an employer contests an employee’s claim, interest accrues 30 days after the award is entered.

Employer continued to pay Claimant temporary total disability benefits at the rate of $476.28 per week through July 28, 1998. Thereafter, on the basis of its belief that Claimant reached maximum medical improvement on that date, Employer began paying Claimant at the permanent partial disability rate of $249.48 per week. The permanent partial disability payments continued until November 3,1998.

The Division of Workers’ Compensation conducted final hearings on November 5, 1998 and December 4, 1998. Following the hearings, the ALJ issued a final award for permanent partial disability and also doubled a portion of the second temporary award due to Employer’s failure to comply. The ALJ found that Claimant reached maximum medical improvement on or about July 28, 1998, and was not entitled to any future temporary total disability or medical benefits. The ALJ denied Claimant’s claim against the Second Injury Fund. The ALJ’s final award was silent as to interest. Both parties filed applications for review with the Commission. The Commission affirmed the ALJ’s final award, adding only that “[a]ny past due compensation shall bear interest as provided by law.” Claimant now appeals.

There are two standards of review for awards from the Commission. There is a de novo standard for questions of law, which allows this court to examine issues and make holdings as though it were the court of origin. Stawizynski v. J.S. Alberici Const Co., 936 S.W.2d 159, 162 (Mo.App.1996). The standard for questions of fact, however, requires the reviewing court to examine the record and all reasonable inferences therefrom in the light most favorable to the findings and award of the Commission to determine whether they are supported by competent and substantial evidence. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Capital Region Med. Ctr.
564 S.W.3d 800 (Missouri Court of Appeals, 2018)
Poole v. City of St. Louis
328 S.W.3d 277 (Missouri Court of Appeals, 2010)
Mell v. Biebel Bros., Inc.
247 S.W.3d 26 (Missouri Court of Appeals, 2008)
ABB POWER T & D CO. v. Kempker
236 S.W.3d 43 (Missouri Court of Appeals, 2007)
Martin v. Town and Country Supermarkets
220 S.W.3d 836 (Missouri Court of Appeals, 2007)
Townser v. First Data Corp.
215 S.W.3d 237 (Missouri Court of Appeals, 2007)
Kuykendall v. Gates Rubber Co.
207 S.W.3d 694 (Missouri Court of Appeals, 2006)
Russell v. Invensys Cooking & Refrigeration
174 S.W.3d 15 (Missouri Court of Appeals, 2005)
Hawthorne v. Lester E. Cox Medical Centers
165 S.W.3d 587 (Missouri Court of Appeals, 2005)
Forshee v. Landmark Excavating & Equipment
165 S.W.3d 533 (Missouri Court of Appeals, 2005)
Monroe v. Wal-Mart Associates, Inc.
163 S.W.3d 501 (Missouri Court of Appeals, 2005)
Garrone v. Treasurer of State of Missouri
157 S.W.3d 237 (Missouri Court of Appeals, 2004)
Birdsong v. Waste Management
147 S.W.3d 132 (Missouri Court of Appeals, 2004)
Reidelberger v. Hussman Refrigerator Co.
135 S.W.3d 431 (Missouri Court of Appeals, 2004)
Hampton v. Big Boy Steel Erection
121 S.W.3d 220 (Supreme Court of Missouri, 2003)
Cunningham v. Research Medical Center
108 S.W.3d 177 (Missouri Court of Appeals, 2003)
Minies v. Meadowbrook Manor
105 S.W.3d 529 (Missouri Court of Appeals, 2003)
Henderson v. Schnucks Markets
100 S.W.3d 141 (Missouri Court of Appeals, 2003)
Feller v. Lear Corp.
101 S.W.3d 286 (Missouri Court of Appeals, 2002)
McDermott v. City of Northwoods Police Department
103 S.W.3d 134 (Missouri Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
37 S.W.3d 803, 2000 Mo. App. LEXIS 1901, 2000 WL 1847653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sutton-v-vee-jay-cement-contracting-co-moctapp-2000.