Surplec, Inc. v. Maine Public Service Co.

501 F. Supp. 2d 195, 2007 U.S. Dist. LEXIS 57845, 2007 WL 2269832
Procedural entryThis page is a short order in Surplec, Inc. v. Maine Public Service Co.. Read the opinion of the Court — 495 F. Supp. 2d 147
District Court, D. Maine·Decided August 7, 2007·No. CV-07-55-B-W·Published

Opinion

ORDER ON MOTION TO DISMISS

JOHN A. WOODCOCK, JR., District Judge.

Surplec, Inc. (Surplec) filed a law suit against Maine Public Service Company (MPSC), UPC Wind Management, LLC (UPC), and Evergreen Wind Power, LLC (Evergreen), alleging that, acting as joint venturers, the three Defendants failed to pay Surplec in full for a transformer that has been installed and is operating at their Mars Hill Project, producing electricity. Before the Court is a motion by UPC and Evergreen, claiming that Surplec’s Complaint fails to state a claim against them for conversion (Count IV) and unjust enrichment (Count V). Because Surplec alleged that the taking of the transformer was wrongful, and because there is a justifiable inference that a demand to return the transformer would have been futile, the Court denies the motion as regards the conversion count. Because Surplec alleged that, in ordering and using the transformer, UPC and Evergreen were acting as joint venturers with MPSC, the Court concludes that UPC and Evergreen are potentially jointly and severally liable, and denies the motion as regards the unjust enrichment count. 1

I. LEGAL STANDARD

Rule 12(b)(6) provides, in part:

*197 Every defense, in law or fact, to a claim for relief in any pleading ... shall be asserted in the responsive pleading thereto if one is required, except that the following defenses may at the option of the pleader be made by motion: ... (6) failure to state a claim upon which relief can be granted....

Fed.R.CivP. 12(b)(6). “In ruling on a motion to dismiss [under Rule 12(b)(6)], a court must accept as true all the factual allegations in the complaint and construe all reasonable inferences in favor of the plaintiffs.” Alternative Energy, Inc. v. St. Paul Fire & Marine Ins. Co., 267 F.3d 30, 33 (1st Cir.2001) (citing Beddall v. State St. Bank & Trust Co., 137 F.3d 12, 16 (1st Cir.1998)). However, despite the liberal pleading standard of Federal Rule of Civil Procedure 8, to survive a motion to dismiss, “a complaint must allege ‘a plausible entitlement to relief.’ ” Rodriguez-Ortiz v. Margo Caribe, Inc., 490 F.3d 92, 95 (1st Cir.2007) (quoting Bell Atlantic Corp. v. Twombly, — U.S. -, -, 127 S.Ct. 1955, 1967, 167 L.Ed.2d 929 (2007)). 2 Moreover, the Court “need not credit a complaint’s bald assertions or legal conclusions.” Glassman v. Computervision Corp., 90 F.3d 617, 628 (1st Cir.1996) (citation and internal quotation marks omitted).

II. BACKGROUND 3

On April 30, 2007, Surplec filed suit against MPSC, UPC, and Evergreen, alleging several state law causes of action, including breach of contract, fraudulent misrepresentation, negligent misrepresentation, conversion, and unjust enrichment. 4 See Compl. (Docket # l). 5 For the purposes of this motion, the Court accepts the following facts, alleged in the complaint, as true:

Surplec, a company that manufactures and sells electrical equipment, sold a transformer to MPSC 6 pursuant to a purchase order from MPSC dated March 8, 2006. The parties agreed that, before Surplec would deliver the transformer, MPSC would pay the purchase price of $398,000 (plus a $22,000 delivery charge) in three installments. MPSC paid the first two installments on March 15, 2006 and June 29, 2006. On November 30, 2006, Surplec informed MPSC that the transformer was ready for delivery; that same day, MPSC faxed a copy of a check for the last installment and the express assurance that the check would be sent out immediately. After the check failed to arrive, MPSC made two other representations that payment was forthcoming. Banking on these representations, Surplec shipped the transformer and accessories to MPSC at its Mars *198 Hill, Maine site. However, MPSC never tendered the promised payment. Instead, MPSC informed Surplee that the transformer was neither merchantable nor fit for its intended purpose, and that it would hold the transformer until Surplee delivered a replacement. Nevertheless, MPSC, UPC, and/or Evergreen proceeded to modify or adjust the transformer without advising Surplee in advance, and then installed the transformer. The transformer is currently operational and MPSC, UPC, and/or Evergreen are using it to generate electricity, and Surplee has not yet received the final payment for the transformer.

On June 4, 2007, UPC and Evergreen moved to dismiss Counts TV and V of the Complaint under Federal Rule of Civil Procedure 12(b)(6). See Defs.’ Mot. to Dismiss (Docket # 28) (Defs. ’ Mot.).

III. DISCUSSION

A. Conversion

Under Maine law, to make a prima facie case of conversion, a plaintiff must establish three elements:

(1) a showing that the person claiming that his property was converted has a property interest in the property; (2) that he had the right to possession at the time of the alleged conversion; and (3) that the party with the right to possession made a demand for its return that was denied by the holder.

Withers v. Hackett, 1998 ME 164, ¶ 7, 714 A.2d 798, 800. This motion centers on the third element—a denied demand for return. Defendants assert that “Surplee does not allege that it made any demand to UPC Wind or Evergreen that the Transformer be returned.” Defs.’ Mot. at 3. Surplee counters that it should be excused from the demand requirement for two reasons: first, a demand would have been futile; and, second, the taking was wrongful. Pl.’s Opp’n to Defs.’ Mot. to Dismiss at 6-7 (Docket # 38).

Regarding Surplec’s first point, there is a sensible exception to the demand requirement: “where the circumstances show that a demand would be useless, a demand is not necessary.” Withers, 714 at 800 (citing General Motors Acceptance Corp. v. Anacone, 160 Me. 53, 83, 197 A.2d 506, 524 (1964)). Surplec’s main obstacle is that its Complaint failed to allege explicit facts to support the futility claim. Rather, it relies on an inference that a demand would have been futile:

Free access — add to your briefcase to read the full text and ask questions with AI

Surplec, Inc. v. Maine Public Service Co., 501 F. Supp. 2d 195, 2007 U.S. Dist. LEXIS 57845, 2007 WL 2269832 (D. Me. 2007).

501 F. Supp. 2d 195 (Surplec, Inc. v. Maine Public Service Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Glassman v. Computervision Corp.
90 F.3d 617 (First Circuit, 1996)
Beddall v. State Street Bank & Trust Co.
137 F.3d 12 (First Circuit, 1998)
Rodriguez-Ortiz v. Margo Caribe, Inc.
490 F.3d 92 (First Circuit, 2007)
Maine Eye Care Associates P.A. v. Gorman
2006 ME 15 (Supreme Judicial Court of Maine, 2006)
General Motors Acceptance Corporation v. Anacone
197 A.2d 506 (Supreme Judicial Court of Maine, 1964)
Forrest Associates v. Passamaquoddy Tribe
2000 ME 195 (Supreme Judicial Court of Maine, 2000)
Tucci v. City of Biddeford
2005 ME 7 (Supreme Judicial Court of Maine, 2005)
A.F.A.B., Inc. v. Town of Old Orchard Beach
610 A.2d 747 (Supreme Judicial Court of Maine, 1992)
Paffhausen v. Balano
1998 ME 47 (Supreme Judicial Court of Maine, 1998)
Surplec, Inc. v. Maine Public Service Co.
495 F. Supp. 2d 147 (D. Maine, 2007)
June Roberts Agency, Inc. v. Venture Properties, Inc.
676 A.2d 46 (Supreme Judicial Court of Maine, 1996)
Nancy W. Bayley, Inc. v. Maine Employment Security Commission
472 A.2d 1374 (Supreme Judicial Court of Maine, 1984)
Pendleton v. Sard
297 A.2d 889 (Supreme Judicial Court of Maine, 1972)
Withers v. Hackett
1998 ME 164 (Supreme Judicial Court of Maine, 1998)
Glenwood Farms, Inc. v. Ivey
228 F.R.D. 47 (D. Maine, 2005)