Sunrise Electric, Inc. v. Zachman Homes, Inc.

425 N.W.2d 848, 1988 Minn. App. LEXIS 585, 1988 WL 58902
CourtCourt of Appeals of Minnesota
DecidedJune 14, 1988
DocketC1-87-2251
StatusPublished
Cited by8 cases

This text of 425 N.W.2d 848 (Sunrise Electric, Inc. v. Zachman Homes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunrise Electric, Inc. v. Zachman Homes, Inc., 425 N.W.2d 848, 1988 Minn. App. LEXIS 585, 1988 WL 58902 (Mich. Ct. App. 1988).

Opinion

OPINION

LANSING, Judge.

Sunrise Electric seeks enforcement of a mechanic’s lien against property in a Lake Eden condominium development. Sunrise received partial payment of the lien amount *849 in the bankruptcy action of the developer, Zachman Homes. Sunrise now seeks to enforce the lien against property within the development which had been sold prior to the bankruptcy action. The trial court found the lien invalid, and we affirm.

FACTS

Zachman Homes, Inc., is a developer and builder of residential housing units. On November 2, 1983, Zachman filed for relief under Chapter 11 of the Bankruptcy Code. The petition was later converted to a regular Chapter 7 bankruptcy. At the time Zachman filed the petition, it had under construction approximately 50 housing units in four housing developments: Lake Eden, Cinnamon Ridge, Fox Glen and Wo-odcliff. The mechanic’s lien at issue in this case is one general lien for all of Sunrise’s electrical work on residential units in the Lake Eden development.

The bankruptcy court established procedures which allowed Zachman to complete and sell the housing units under construction free from all liens. The sale proceeds from the units would be distributed first to suppliers and laborers who provided work and material after the date of the bankruptcy petition, then applied to construction and selling costs. Construction lenders, including Bell Investment Co., would receive balances owing on their construction mortgages with the proviso that if the court later determined that the pre-petition mechanics’ liens were prior to the construction mortgages, the money would be paid back.

The principal claimants in the bankruptcy action agreed to submit sample cases to determine the relative rights of the creditors. The sample cases submitted for the Lake Eden development were units 42, 44, 46, 47 and 48. Although the record before this court does not disclose how these units were selected, all of the sample units were located in building F. Sunrise Electric claimed a lien of $45,530.48.

The bankruptcy court, in a November 30, 1984, order, held that because there were actual and visible beginnings of improvements preceding the recording of the mortgages, including Bell Investment’s, the mortgages were subordinated to the mechanics’ liens. To determine the amounts due each lien claimant, the court prorated each lien over all claimed units in the development. On appeal the federal district court affirmed the bankruptcy court order.

After this ruling, Sunrise moved in bankruptcy court for summary judgment on the issue of the validity and priority of its mechanic’s lien claim against the remaining Lake Eden units subject to the bankruptcy action: one unit in building D and all units in building E. The bankruptcy court denied the motion for summary judgment. The court held that its November 1984 order established the priority of Sunrise’s mechanic’s lien over the mortgage of Bell Investment, but did not establish the validity of the lien. The court concluded that a fact issue remained on whether Sunrise’s lien arose from a single general contract for the entire Lake Eden project or from a series of separate contracts which required separate mechanics’ lien filings on each building or each unit.

On motion for reconsideration, the bankruptcy court reversed its position and entered summary judgment. The court stated that the issue of whether Zachman Homes and Sunrise had a general contract or separate contracts had not been raised or litigated, but concluded that the validity of Sunrise’s liens was essential to the November 30, 1984, order and Bell Investment’s failure to raise the issue collaterally estopped it from raising it now. 1

After this ruling, the dispute between Sunrise and Bell Investment moved from *850 federal to state court. In September 1984 Sunrise filed a mechanic’s lien action in Hennepin County against 189 defendants, primarily individual condominium owners and mortgagees, including Bell Investment. In its statement of the case and its arguments to the trial court, Sunrise narrowed its lien foreclosure to the non-bankruptcy property, buildings A, B, C and all but unit 29 in building D. These units had all been sold by Zachman prior to the filing of the bankruptcy petition. Sunrise limited its claim to $29,000 — apparently the amount still owing after the recovery permitted in bankruptcy court.

Sunrise moved for summary judgment, arguing that the bankruptcy action decided the validity of Sunrise’s lien and its priority over Bell Investment’s mortgage and prevented relitigation of those issues between parties to the bankruptcy action and those in privity with them. The trial court denied the motion, finding that the bankruptcy court’s orders did not have preclusive effect. The parties offered to submit the issue of the lien’s validity on the written record, but the court scheduled a trial, noting that the remaining dispute — whether Sunrise had a single general contract or a series of contracts — would turn on the understanding and intent of the parties and was particularly subject to credibility determinations.

At trial the parties included Sunrise, various mortgagees including Bell Investment and various owners of the individual condominium units. They agreed that the sole issue was whether Sunrise’s work was done under a general contract or a series of separate contracts.

The evidence included testimony from Keith Hesli of Sunrise Electric that Mike Zachman of Zachman Homes contacted him in 1982 to obtain a bid on the Lake Eden development. Zachman showed Hesli blueprints of four different types of units which would be built in the Lake Eden project. Hesli submitted a written bid for a price for each type of unit. Hesli testified that these unit prices took into account a discount because they were doing the work for the whole project. According to Hesli, Mike Zachman later called him and told him that Sunrise’s bid was accepted and that Sunrise would be doing the work for the Lake Eden project. However, Hesli also testified that the contract was formalized the first day Sunrise showed up for work.

Sunrise began work on August 12, 1982. Except for the per-unit bids, Sunrise and Zachman had no written agreement. When buildings became ready for rough electrical work, Zachman called Sunrise and Sunrise sent workers to the job site. The same process was used when units were ready for finishing electrical work. Sunrise worked in more than one building at a time completing various stages of work, roughing in units at the same time they were finishing other units.

During 1983, Zachman stopped paying Sunrise and Sunrise stopped working. At that time, Sunrise was the only electrical contractor that had worked on the Lake Eden project. On October 7, 1983, Sunrise filed a single mechanic’s lien on all the units on which it had worked in Lake Eden. The lien lists the units individually by building.

The trial court found that Sunrise’s work in the Lake Eden development was not done pursuant to a general contract and consequently the lien was not valid on the units involved in the trial. Sunrise and the mortgagees and homeowners moved for amended findings and judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arbitration of Olson v. Auto-Owners Insurance Co.
659 N.W.2d 283 (Court of Appeals of Minnesota, 2003)
Paulos v. Johnson
597 N.W.2d 316 (Court of Appeals of Minnesota, 1999)
Austin v. Super Valu Stores, Inc.
31 F.3d 615 (Eighth Circuit, 1994)
Occhino v. Lannon
150 F.R.D. 613 (D. Minnesota, 1993)
Glass v. IDS Financial Services, Inc.
798 F. Supp. 1411 (D. Minnesota, 1992)
Demers v. City of Minneapolis
486 N.W.2d 828 (Court of Appeals of Minnesota, 1992)
Myers Through Myers v. Price
463 N.W.2d 773 (Court of Appeals of Minnesota, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
425 N.W.2d 848, 1988 Minn. App. LEXIS 585, 1988 WL 58902, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunrise-electric-inc-v-zachman-homes-inc-minnctapp-1988.