Sundance Mechanical & Utility Corp. v. Atlas

880 P.2d 861, 118 N.M. 250
CourtNew Mexico Supreme Court
DecidedAugust 9, 1994
Docket21159
StatusPublished
Cited by14 cases

This text of 880 P.2d 861 (Sundance Mechanical & Utility Corp. v. Atlas) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sundance Mechanical & Utility Corp. v. Atlas, 880 P.2d 861, 118 N.M. 250 (N.M. 1994).

Opinion

OPINION

BACA, Justice.

Plaintiff-Appellant, Sundance Mechanical & Utility Corporation (“Sundance”), appeals from the district court’s decision concluding that Defendants-Appellees, Marvin and Carole Atlas (the “Atlases”), were entitled to the benefit of NMSA 1978, Section 48-2-10.1(A) (Repl.Pamp.1987) (mandating the conditions for discharge of a materialman’s lien). On appeal we decide whether the district court erred when it determined that the Atlases were entitled to the benefit of Section 48-2-10.1(A). We review this case under SCRA 1986, 12-102(A)(1) (Repl.Pamp.1992), and reverse.

I.

This lawsuit arises out of a house-building contract between the Atlases and Robert Eden, doing business as R.J. Eden Construction Company (“Eden”). On November 19, 1985, the Atlases entered into a contract with Eden for the construction of a residence on certain real property owned by the Atlases. The original contract payment amount was $331,554.09. The contract required Eden to furnish labor, services, and materials for construction of the house.

On December 31, 1985, Eden, acting as general contractor, entered into a written contract with Sundance that, in essence, called for Sundance to perform certain subcontract work on the Atlases’ house. Between September 2, 1986, and October 13, 1986, Eden and Sundance performed work on the residence. On October 13, 1986, before construction was completed, the Atlases terminated Eden’s contract as general contractor and began personally supervising the construction of the residence. Between September 19, 1986, and June 18, 1987, the Atlases paid various subcontractors and suppliers $43,412.20 for work performed and materials supplied.

Sundance completed its work on the residence on October 30, 1986. At this time Eden owed Sundance $14,637.80 for the work performed. On October 31, 1986, Sundance filed a claim of lien against the Atlases in the County Clerk’s office in Bernalillo County. On February 17, 1987, the Atlases paid Sun-dance $3,000 to reduce the claim of lien to $11,637.80.

On March 19, 1987, Sundance filed a complaint for debt and money due and sought to foreclose its claim of lien against the Atlases’ residence. On June 12, 1987, Sundance filed a motion for summary judgment with respect to certain counts in its complaint. The district court granted Sundance’s motion on March 9, 1988, and awarded Sundance a judgment against the real property of Eden and the Atlases in the amount of $18,557.39. The court also ordered foreclosure of Sun-dance’s lien and appointed a special master to sell the property. On March 10,1988, and March 18, 1988, the Atlases paid Sundance a total of $18,557.39 to satisfy the judgment. Sundance accepted this amount as payment in full and subsequently filed a satisfaction and release of judgment.

On March 21, 1988, despite having paid the judgment amount, the Atlases filed a pro se motion to set aside the judgment in favor of Sundance. On October 14, 1988, the Atlases, through an attorney, filed a second motion seeking relief from the district court’s grant of summary judgment in favor of . Sundance. On December 7, 1988, the district court issued an order finding that because of a serious illness suffered by Marvin Atlas, the judgment in favor of Sundance was improvidently entered. The court set aside the judgment and ordered a rehearing on the matter at a later date.

A hearing was held on November 18,1992. The district court filed its findings of fact, conclusions of law, and decision on January 4, 1993. The court incorporated in its decision certain findings made in a May 25, 1988, arbitration proceeding between the Atlases and Eden. The arbitration proceeding adjudicated issues pertaining to the construction contract between those parties, and the final arbitration award was confirmed by the district court on September 8, 1988. Based upon the findings of the arbitrator, the court determined that Eden “was paid all amounts due and owing in full prior to the time that [Sundance] ... filed its Claim of Lien.” The court also determined that “[the Atlases were] unaware of any unpaid [subcontractor] at the time of final payment to Eden” and that the date of full and final payment under the contract was September 2, 1986. The court concluded that the Atlases were “entitled to the benefit of [Section 48-2-10.1(A) and that Sundance’s lien was] discharged from the [s]ubject [r]eal [property.” Accordingly, the court ruled that Sundance “should take nothing by virtue of its Claim of Lien” and required Sundance to “refund to the [Atlases the] amounts paid to it.” Sun-dance appeals the district court’s decision to this Court.

II.

On appeal we address whether the district court erred by concluding that the Atlases were entitled to the benefit of Section 48-2-10.1(A). This Section, which has subsequently been repealed by 1989 N.M. Laws, chapter 301, section 13, stated in pertinent part that

[p]ayment by the owner or his successor in interest to any person entitled to such payment of all amounts due and owing for any construction, improvement, landscaping or other actions the performance of which could give rise to a lien pursuant to [NMSA 1978, Section 48-2-2 (Repl.Pamp. 1987) ] to be performed upon a residence containing not more than four dwelling units shall discharge all such liens unless prior to such payment any person who is entitled to such lien has filed for record his lien pursuant to [NMSA 1978, Section 48-2-6 (Repl.Pamp.1987) ].

Section 48-2-10.1(A). Stated in straightforward terms, Section 48-2-10.1(A) discharges any subcontractor lien filed after a property owner has paid all amounts due and owing to the general contractor. See Aztec Wood Interiors, Inc. v. Andrade Homes, Inc., 104 N.M. 45, 46, 716 P.2d 236, 237 (1986) (holding that in order to achieve the benefit of Section 48-2-10.1(A), the subcontractor “must have filed its lien prior to the time the [homeowners] made the final payment”). Furthermore, to receive the benefit of Section 48-2-10.1(A), the owner must be an “innocent owner.” See Pyburn v. Kirkpatrick, 106 N.M. 247, 248-49, 741 P.2d 1368, 1369-70 (1987); C & D Plumbing, Inc. v. Armstrong, 106 N.M. 155, 156, 740 P.2d 705, 706 (1987); Aztec Wood Interiors, 104 N.M. at 47, 716 P.2d at 238. Contrary to the district court’s decision, we conclude that the Atlases neither paid “all amounts due and owing” under the contract nor constituted “innocent owners” as this term has been defined by our case law. We hold that the court erred in deciding that the Atlases were entitled to the benefit of Section 48-2-10.1(A).

A.

Section 48-2-10.1(A) first requires that an owner pay the general contractor “all amounts due and owing” on the contract before the owner can avail itself of the benefit of the statute. We have interpreted payment of “all amounts due and owing” to mean final payment rather than partial payment. C & D Plumbing, 106 N.M. at 156, 740 P.2d at 706. According to the facts stipulated by the parties prior to trial, the amount due on the contract between the Atlases and Eden was $331,554.09.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis Construction Corp. v. FTJ
Supreme Court of Virginia, 2020
Abraham v. WPX Energy Production, LLC
20 F. Supp. 3d 1244 (D. New Mexico, 2014)
Mid-Valley Airpark v. K.L.A.S.
New Mexico Court of Appeals, 2011
Ideal v. Burlington Resources Oil & Gas Co. LP
2010 NMSC 022 (New Mexico Supreme Court, 2010)
J.R. Hale Contracting Co. v. Union Pacific Railroad
2008 NMCA 037 (New Mexico Court of Appeals, 2007)
Ontiveros Insulation Co., Inc. v. Sanchez
3 P.3d 695 (New Mexico Court of Appeals, 2000)
Spear v. McDermott
916 P.2d 228 (New Mexico Court of Appeals, 1996)
Carter v. City of Las Cruces
915 P.2d 336 (New Mexico Court of Appeals, 1996)
Carter v. CITY OF LAS CRUCES, NEW MEXICO
915 P.2d 336 (New Mexico Court of Appeals, 1996)
Rex, Inc. v. Manufactured Hous. Comm. of NM
892 P.2d 947 (New Mexico Supreme Court, 1995)
State v. Ware
884 P.2d 1182 (New Mexico Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
880 P.2d 861, 118 N.M. 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sundance-mechanical-utility-corp-v-atlas-nm-1994.