Suitt Construction Co. v. Ripley's Aquarium, LLC

108 F. App'x 309
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 17, 2004
DocketNo. 03-5070
StatusPublished

This text of 108 F. App'x 309 (Suitt Construction Co. v. Ripley's Aquarium, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Suitt Construction Co. v. Ripley's Aquarium, LLC, 108 F. App'x 309 (6th Cir. 2004).

Opinion

GIBBONS, Circuit Judge.

Defendant-appellant Blalock Lumber Co. (“Blalock”) brought this appeal for review of a district court decision denying Blalock’s motion for a new trial, or alternatively, to alter or amend a jury verdict in favor of plaintiff-appellee Suitt Construction Co. (“Suitt”). For the following reasons, we affirm the judgment of the district court.

I.

On March 29, 1999, defendant Ripley’s Aquarium, LLC (“Ripley’s”) entered into a contract with Suitt for the construction of Ripley’s Aquarium in Gatlinburg, Tennessee (the “Aquarium”). The Aquarium has 110,000 square feet of enclosed space with numerous exhibits, a gift shop, and a kitchen. It has several themed display tanks, including: Dangerous Reef, Tropical Rainforest, Rainbow Reef, Ray Bay, and Groupers and Eels. The Aquarium is built primarily of concrete, which is reinforced with steel. Suitt, the general contractor, entered into agreements with several subcontractors. Most importantly for purposes of this appeal, Suitt entered into an agreement with Blalock, pursuant to which Blalock agreed to supply the concrete for the project. Suitt also entered into separate subcontracts with Worley Construction Co., Inc. (“Worley”) and Schaefer Interstate Railing, Inc. (“Schaefer”). Ripley’s hired a separate contractor, Manwarren, to install the underwater theming in the tanks.

The date of substantial completion refers to the date at which the- Aquarium was to be ready to open for business. The contract between Ripley’s and Suitt originally established the date of substantial completion as July 10, 2000. Due to delays for which Ripley’s was responsible, the parties agreed to push the substantial completion date back to July 31, 2000. The contract provided for liquidated damages of $15,000 per day for each calendar day after the date of substantial completion until the work actually was substantially completed. The contract also provided for a grace period and a liquidated damages cap. The grace period allowed that no liquidated damages would accrue during the first fourteen days after the substantial completion date specified in the contract. The cap provided that liquidated damages would in no event exceed $705,000, or forty-seven days of liquidated damages at $15,000 per day.

The contract specified certain requirements for the concrete. The two most important requirements concerned the compressive strength of the concrete and its water/cement ratio. The compressive strength of the concrete refers to how many pounds of pressure per square inch (“psi”) the concrete can withstand before it breaks. The concrete to be supplied by Blalock for the aquarium tanks was to have a compressive strength of 5,000 psi. The water/cement ratio is calculated by dividing the weight of water in a cubic yard of concrete by the weight of the cement and fly ash, a filler used in concrete. The water/cement ratio was to be no higher than .40. The project specifications required that a 5,000 psi, .40 water/cement ratio concrete mix be used in all applications of “concrete against water,” including the aquarium tanks. Blalock does not dispute that it contracted to provide concrete with these characteristics.

On August 5, 1999, Suitt sent Blalock concrete test reports which showed that the concrete used to pour the Dangerous Reef tank did not meet the specified strength of 5,000 psi. The concrete used in the Dangerous Reef was especially important because, besides being very large, the Dangerous Reef supported other parts of the budding. Blalock responded that the [312]*312concrete was of good quality and the low measurements must have been caused by testing inconsistencies.

Each load of concrete delivered to the project had a corresponding “batch ticket” which gave information about the load. Batch tickets in Blalock’s possession showed that the water/cement ratio in many of the batches exceeded .40. Suitt contends that it did not have access to this information at the time it received each load of concrete. It alleges that Blalock representatives tore off the bottom portion of each batch ticket as each truck left the plant and sent only the top portion of the batch ticket to the project site. Kevin Blalock, manager of Blalock’s concrete operations, acknowledged at trial that Suitt had no knowledge of the defective nature of the concrete until September 9, 1999, when Blalock faxed copies of the batch tickets to Suitt.

Upon receipt, Suitt showed the batch tickets indicating the high water content to Ripley’s structural engineer, Miklos Peller. Peller was concerned about the higher porosity, lower density, and decreased durability of the concrete due to its deviation from Suitt’s specifications. Because of the high water content of the concrete, the walls made from it would be less impervious to the water contained in the tanks. Over time, water would seep in and damage the steel encased in the concrete. Because of the defective concrete, Ripley’s and Peller determined that, pursuant to the contract, Suitt would either have to coat the Dangerous Reef tank walls with a liner with the brand name “Polibrid” or remove and replace the concrete.

The Dangerous Reef tank contains a moving sidewalk encased in an acrylic tunnel which allows patrons to literally walk through the tank. Before the Polibrid liner could be installed, Nipurra, the company supplying the acrylic tunnel, had to conduct tests to determine whether the acrylic and the liner were compatible and would create a watertight seal. The delay involving the acrylic installation delayed Manwarren’s theming work, which included painting the tanks and installing simulated underwater plant life. Theming was originally scheduled to begin on October 15, 1999, but was delayed until February 16, 2000. Suitt asserts that Blalock’s defective concrete delayed substantial completion by ninety-two calendar days, but that by rescheduling projects not on the “critical path,” Suitt reduced the delay to seventy-nine days.1 On January 24, 2000, Suitt issued a revised construction schedule which showed that the substantial completion date had been pushed back to October 18, 2000, as a result of delays associated with the concrete. Blalock admits that its defective concrete caused the entire seventy-nine day delay. The project was not substantially completed on October 18, 2000, either. Further delays attributable to Ripley’s and Manwarren delayed the actual substantial completion date until December 15, 2000. Suitt does not contend that Blalock was responsible for this further delay.

II.

On March 30, 2001, Suitt filed a complaint in the United States District Court for the Eastern District of Tennessee against Ripley’s, Blalock, Worley, Schaefer, and the bonding companies for Worley [313]*313and Schaefer. Suitt’s complaint sought judgment against Ripley’s for the contract balance of over $3,000,000 plus interest; judgment against Blalock for breach of the concrete purchase contract and for breach of implied warranties of merchantability and fitness for a particular purpose in an amount over $1,000,000 plus interest; judgment against Worley for breach of contract and express warranties in an amount over $500,000 plus costs, expenses, attorney fees, and interest; and judgment against Schaefer for breach of contract and express warranties in an amount over $500,000 plus costs, expenses, attorney fees, and interest.

On May 9, 2001, Ripley’s filed an answer and counterclaim against Suitt seeking judgment against Suitt in an amount over $12,360,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
First Tennessee Bank National Ass'n v. Hurd Lock & Manufacturing Co.
816 S.W.2d 38 (Court of Appeals of Tennessee, 1991)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Conte v. General Housewares Corp.
215 F.3d 628 (Sixth Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
108 F. App'x 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/suitt-construction-co-v-ripleys-aquarium-llc-ca6-2004.