Structural Metals, Inc. v. S & C Electric Co.

590 F. App'x 298
Court of Appeals for the Fifth Circuit·Decided October 6, 2014·No. Nos. 13-50332, 13-50666·Published·Cited by 7 cases

Opinion

PER CURIAM: *

Appellant S & C Electric Company appeals the district court’s denial of its motion for remittitur as well as the district court’s award of attorney’s fees to Appel-lee Structural Metals, Inc. For the following reasons, we AFFIRM the judgment of the district court.

I. Factual and Procedural Background

Plaintiff-Appellee Structural Metals, Inc. operates a steel recycling plant in Seguin, Texas. Steel recycling is, as one might imagine, a process that demands a significant amount of power. Yet the amount of power required is not constant. Smaller pieces of scrap require less power, while larger pieces require more. That fluctuation in the demand for power can cause dips in the overall flow of electricity throughout the plant. When Structural Metals acquired a new caster,1 which was unable to tolerate variances in voltage of more than 5 per cent, it began looking for a solution that would make the flow of electricity throughout the plant more reliable.

To that end, Structural Metals began negotiating with Defendant-Appellant S & C Electric Company. Between 2003 and 2005, Structural Metals and S & C Electric negotiated various proposals for the purchase of Adaptive VAR Compensators (“AVC”), which were meant to ensure that the amount of power flowing throughout the steel recycling plant remained consistent. Some of the proposals involved the purchase of the AVCs and all of the additional facilities, products, and installation required to make them work. Other pro-posáis were simply for the purchase of the AVCs themselves. Structural Metals ended up accepting the proposal for the AVC units only, electing to purchase the additional products elsewhere and to have another company install the AVCs and build the necessary facility. The purchase price for the AVCs was $806,500.

Nevertheless, Structural Metals has maintained throughout this action that its contract was for an “AVC System,” by which it presumably meant that S & C Electric had sold it an overall design to regulate its power flow, not just the AVC units that were the centerpiece of that design. Structural Metals’s argument was that even though Structural Metals did not purchase all of the components of that design from S & C Electric, S & C Electric was responsible for making sure the overall design worked. S & C Electric hotly contested that interpretation of the contract, alleging that it only promised to sell the two individual AVC units, and that Structural Metals was responsible for implementing them after rejecting an offer to have S & C Electric build and install the entire system.

In January of 2006, S & C Electric commissioned the two AVC units. From that point forward, Structural Metals began experiencing problems. Structural Metals contends that the AVC units never regulated the power level in the plant to the degree that S & C Electric had warranted. It also claims that the AVC units constantly overheated, causing damage to the capacitors and other components of the AVC system. S & C Electric responded to these concerns by promising to stand by its equipment. In November, 2006, it ex[301] tended the warranty and promised to bring its equipment “to an acceptable condition.”

Before it could follow through, however, a fire broke out in the AVC system on December 2, 2006 and caused extensive damage. Structural Metals blamed S & C Electric’s AVC units for causing the fire, and demanded its money back.

When S & C Electric refused, Structural Metals sued for breach of contract and breach of warranty under Texas law. Under both theories of recovery, Structural Metals sought not just the value of the AVC units, but the value of the entire “AVC System,” including components purchased from other companies.

After the litigation began, the cause of the fire continued to be a major issue. Structural Metals contended that the AVC units caused the fire, whereas S & C Electric claimed that the electrical cables running from one of the AVC units to one of the transformers — which had not been installed by S & C Electric — were the cause. S & C Electric claimed that the cables used were rated for too low a current and were overtaxed by the AVC system, causing them to overheat and arc, causing the fire.

The electric cables ran through an underground culvert from the building housing the AVC units to the transformers. After the fire, Structural Metals retrieved the electric cables from the burned out, melted culvert and stored them in a locked building on the plant’s premises. Yet, before S & C Electric was able to investigate the cables in connection with this litigation, the cables disappeared.2 As a spoliation remedy, the district court approved Structural Metals’s proposal that it not be allowed to contest that the fire started in the cables at-trial.

After the fire, Structural Metals filed a claim with its insurance company, Liberty Mutual. Liberty Mutual investigated the-fire damage and prepared a list of items that needed to be repaired or replaced and proposed a settlement of the insurance claim. After some negotiation, Liberty Mutual agreed to settle the claim for $475,650, which, after Structural Metals’s $200,000 deductible, resulted in a net insurance payment of $275,650.

The case went to trial in November 2009, with Structural Metals asserting a breach of contract claim that also included theories of breach of an express warranty, breach of the implied warranty of merchantability, and breach of the implied .warranty of fitness for a particular purpose. On the breach of warranty claims, the jury was instructed that the measure of damages is “[t]he difference, if any, at the time and place of acceptance, between the value of the AVC system accepted and the value that the AVC system would have had if it had been as warranted.”

The jury found S & C Electric liable -for breach of an express warranty, breach of the implied warranty of merchantability, and breach of the implied warranty of fitness for a particular purpose.3 The jury awarded Structural Metals $306,500 in damages.

After the verdict, S & C Electric moved the court to remit the damages award under Federal Rule of Civil Procedure [302]*30259(e).4 S & C Electric argued that its damages should be remitted by the amount of the insurance payment that Structural Metals received from Liberty Mutual. The district court denied that motion, ruling that, under Texas law, the collateral source rule bars consideration of insurance payments in contract actions as well as in tort actions and, alternatively, that S & C Electric failed to show that the insurance payment compensated Structural Metals for the same loss as the damages award.

Structural Metals then moved for attorney’s fees under section 38.001 of the Texas Civil Practice and Remedies Code. The district court awarded Structural Metals attorney’s fees in the amount of $727,487.32 and costs in the amount of $11,910.77.

Free access — add to your briefcase to read the full text and ask questions with AI

Structural Metals, Inc. v. S & C Electric Co., 590 F. App'x 298 (5th Cir. 2014).

590 F. App'x 298 (Structural Metals, Inc. v. S & C Electric Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related