Stilloe v. Almy Bros., Inc.

782 F. Supp. 731, 22 Envtl. L. Rep. (Envtl. Law Inst.) 20871, 34 ERC (BNA) 1457, 1992 U.S. Dist. LEXIS 636, 1992 WL 10546
CourtDistrict Court, N.D. New York
DecidedJanuary 22, 1992
Docket90-CV-818
StatusPublished
Cited by11 cases

This text of 782 F. Supp. 731 (Stilloe v. Almy Bros., Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stilloe v. Almy Bros., Inc., 782 F. Supp. 731, 22 Envtl. L. Rep. (Envtl. Law Inst.) 20871, 34 ERC (BNA) 1457, 1992 U.S. Dist. LEXIS 636, 1992 WL 10546 (N.D.N.Y. 1992).

Opinion

MEMORANDUM-DECISION AND ORDER

McCURN, Chief Judge.

INTRODUCTION

The New York State Department of Environmental Conservation (“DEC”) seeks reconsideration or, in the alternative, certification pursuant to 28 U.S.C. section 1292(b) of this court’s March 19, 1991, order denying DEC’s motion to dismiss claims and counter-claims against DEC for its hazardous waste clean-up activity.

This court’s March 19th order denied DEC’s motion on the grounds that DEC may be liable as an “operator” within the meaning of section 101(20) of the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (“CERCLA”), 42 U.S.C. § 9601(20). The claims allege DEC is liable under section 107(d) for releases of hazardous substances found to be the result of “intentional or grossly negligent conduct,” 42 U.S.C. § 9607(d)(2), during a DEC response to environmental hazards at the Stilloe/Almy Brothers property in Binghamton, New York. This court held that the claims, if proved, could establish “operator” liability under CERCLA.

DISCUSSION

A. Timeliness of DEC’s Motion

As a preliminary matter, Stilloe and Almy Brothers argue that the court should deny DEC’s motion for reconsideration because it is untimely. In support of this contention, they cite local rule 10(m) which states that “[m]otions for reconsideration ... shall be filed and served not later than ten (10) days after the entry of the judgment, order, or decree concerned.” Local Rule 10(m). However, this rule must be read in conjunction with Fed.R.Civ.P. 60(b) which states that “[o]n motion and upon such terms as are just, the court may relieve a party ... from a final judgment, order, or proceeding for the following reasons: ... (6) any other reason justifying relief from the operation of the judgment. The motion shall be made within a reasonable time, ...” Fed.R.Civ.P. 60(b) (1991 Rev.Ed.). While district courts have the authority to promulgate local rules, these rules must be consistent with the Federal Rules of Civil Procedure. Moreover, any inconsistencies between a local and a federal rule must be resolved in favor of the federal rule. Therefore, although DEC’s motion was not made within the 10 day *733 period required by local rule 10(m), the court concludes that it was made within a reasonable time pursuant to Fed.R.Civ.P. 60(b). Accordingly, the court holds that DEC’s motion for reconsideration is timely.

B. Reconsideration

Generally, courts have accepted three grounds as justifying reconsideration of a matter already decided. In this regard, the Second Circuit has permitted reconsideration in those situations which involve “an intervening change of controlling law, the availability of new evidence, or the need to correct a clear error or prevent manifest injustice.” Doe v. New York City Dep’t of Soc. Servs., 709 F.2d 782, 789 (2d Cir.), cert. denied, 464 U.S. 864, 104 S.Ct. 195, 78 L.Ed.2d 171 (1983). In the present case, DEC seeks reconsideration in light of two recent federal district court decisions. Both of these decisions involved the dismissal of section 107(a) contribution counterclaims similar to the claims and counterclaims asserted against DEC in the present action. See United States v. Western Processing, Inc., 761 F.Supp. 725 (W.D.Wash. 1991) (dismissing a CERCLA counter-claim based on the Environmental Protection Agency’s clean-up activities); United States v. Azrael, 765 F.Supp. 1239 (D.Md. 1991) (dismissing a CERCLA counter-claim against both the United States and the State of Maryland). Although these decisions are not binding on this court, the court finds their reasoning persuasive. Accordingly, in order to prevent manifest injustice, the court grants DEC’s motion for reconsideration in light of these cases as well as its own further research.

At issue in this motion for reconsideration is whether DEC can be considered an operator for purposes of CERCLA liability when its only connection to a hazardous waste site results from its remedial cleanup efforts. Relying heavily on the court’s statement in CPC Int’l, Inc. v. Aerojet-General Corp., 731 F.Supp. 783, 788 (W.D.Mich.1989), that “where a party assumes control of an activity and then fails to perform, that party should bear the responsibility for any pollution which results,” this court held that DEC was an operator of the site at the time it broke open the barrels containing the hazardous waste. 1 Stilloe v. Almy Brothers, Inc., 759 F.Supp. 95, 103-04 (N.D.N.Y.1991). Accordingly, this court denied DEC’s motion to dismiss the claims against it. In so doing, however, this court limited DEC’s liability to those actions which were found “to have been the result of either intentional or grossly negligent conduct... since its actions were in response to an emergency situation which existed at the site.” Id. at 104 n. 8 (citing 42 U.S.C. § 9607(d)).

Having now had the opportunity to review the facts of Aerojet in light of the decisions in Azrael and Western Processing, this court finds that DEC’s activities are sufficiently different from those of the Michigan Department of Natural Resources (“MDNR”) in Aerojet to render that decision inapposite. In Aerojet, MDNR entered into a contract with the owner of a hazardous waste site under which MDNR assumed responsibility to operate groundwater purge wells to help reduce pollution and improve waste disposal at the site. See Stilloe, 759 F.Supp. at 102-03. In Aerojet, this contract provided the nexus between the owner of the property and MDNR by establishing an ongoing relationship. Here there is no such nexus. Nor do Stilloe nor Almy Brothers allege that DEC took control of the site for any reason other than to perform its statutory responsibility to clean up the site. Accordingly, the court now concludes that Aerojet does not provide a basis for holding that under the circumstances of this case DEC is an operator within the meaning of CERCLA.

On the contrary, although the court in Azrael was concerned with contribution counter-claims under CERCLA, the factual circumstances of that case are very similar to those present here. At issue in Azrael *734 was the clean-up of a site on which various hazardous substances had been deposited.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
782 F. Supp. 731, 22 Envtl. L. Rep. (Envtl. Law Inst.) 20871, 34 ERC (BNA) 1457, 1992 U.S. Dist. LEXIS 636, 1992 WL 10546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stilloe-v-almy-bros-inc-nynd-1992.