Stevens Construction & Design, L.L.C. v. St. Tammany Fire Protection District No. 1

CourtLouisiana Court of Appeal
DecidedJanuary 16, 2020
Docket2019CW0642
StatusUnknown

This text of Stevens Construction & Design, L.L.C. v. St. Tammany Fire Protection District No. 1 (Stevens Construction & Design, L.L.C. v. St. Tammany Fire Protection District No. 1) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stevens Construction & Design, L.L.C. v. St. Tammany Fire Protection District No. 1, (La. Ct. App. 2020).

Opinion

STATE OF LOUISIANA

COURT OF APPEAL

FIRST CIRCUIT

2019 CA 0431

2018 CW 1759 and 2019 CW 0642

STEVENS CONSTRUCTION & DESIGN, L.L.C.

VERSUS

ST. TAMMANY FIRE PROTECTION DISTRICT NO. 1

Judgment Rendered: WU 1 6 2020

Appealed from the 22nd Judicial District Court In and for the Parish of St. Tammany State of Louisiana Docket Number 2018- 14143

Honorable Martin E. Coady, Judge Presiding

Charles K. Chauvin Counsel for Plaintiff/Appellant Destrehan, LA Stevens Construction & Design, L.L.C.

Troy G. Ingram Counsel for Defendant/Appellee Slidell, LA St. Tammany Fire Protection District No. 1

Albert Dale Clary Counsel for Intervenor/Appellee Adrian G. Nadeau Domain Architecture, APAC, J. Weston Clark Greenleaf Lawson Architects, Baton Rouge, LA APAC, and Domain Architecture + Greenleaf Baton Rouge, Architects, A Joint Venture

BEFORE: WHIPPLE, C. J., GUIDRY, McDONALD, McCLENDON, WELCH, GINBOTHAM, CRAIN ' THERIOT, HOLDRIDGE, CHUTZ, PENZATO, AND LANIER, JJ.

Justice Will Crain is serving as judge ad hoc by special appointment of the Louisiana Supreme Court.

4#WA A-. WHIPPLE, C.J.

Plaintiff, Stevens Construction & Design, L.L.C., appeals a judgment of the

district court denying its petition for a preliminary injunction. For the following

reasons, we dismiss the appeal and decline to consider the related writ applications,

2018 CW 1759 and 2019 CW 0642, which were referred to the merits panel for

consideration, as untimely.

FACTS AND PROCEDURAL HISTORY

On May 11, 2017, Stevens Construction & Design, L.L.C. ( Stevens

Construction) entered into a contract with the St. Tammany Fire Protection District

No. 1 ( Fire District), wherein Stevens Construction would serve as the general

contractor for the construction of a new fire station and headquarters building

located at 522 Robert Boulevard and 530 Robert Boulevard in Slidell, Louisiana

for a total sum of $2, 845, 678. 00. The architect for the project was a joint venture

between two architectural firms, Domain Architecture, APAC and Greenleaf

Lawson Architects, APAC ( the Architect). The contract provided for completion

of the project in 365 calendar days. Construction work on the project began on

June 1, 2017, pursuant to a " notice to commence work" issued by the Fire District.

An additional 47 calendar days were added to the contract' s completion date

pursuant to approved change orders.

On July 19, 2018, the Architect sent a letter to Stevens Construction,

notifying it that the contractual date for substantial completion, July 18, 2018, had

passed and requesting that Stevens Construction provide a " realistic completion

plan by Monday, July 23." Stevens Construction, through owner Adam Stevens,

responded on July 23, 2018, with a " scheduled contractual completion response,"

which proposed that the project would be substantially complete by September 14,

2018. On July 27, 2018, Fire Chief Chris Kaufmann issued a letter to Stevens

2 Construction and its surety by electronic and certified mail to the addresses listed

in the contract, notifying them that the Fire District was considering declaring

Stevens Construction in default under the contract and requesting a meeting with

Stevens Construction and its surety within ten days. Counsel for Stevens

Construction responded on August 6, 2018, agreeing to a meeting. Subsequently,

the Architect outlined various concerns with the project in a letter dated August 15,

2018, which was sent to Stevens Construction, its surety, and the Fire District. On

August 22, 2018, Chief Kaufmann sent a letter to Stevens Construction and its

surety by electronic and certified mail, summarizing his concerns with Stevens

Construction' s performance on the project and directing Stevens Construction to

stop work on the project by 4: 00 p.m. on August 23, 2018.

On August 23, 2018, Stevens Construction filed a verified petition for

temporary restraining order, preliminary injunction, permanent injunction, and writ

of mandamus. Pertinent to this appeal, Stevens Construction alleged that the Fire

District had invalidly issued a stop work order with the purported intent to

terminate Stevens Construction from the project; therefore, Stevens Construction

was seeking a temporary restraining order and injunctive relief to prohibit the Fire

District' s purportedly invalid actions. On August 24, 2018, the district court

signed a temporary restraining order, enjoining the Fire District from taking any

further action to enforce the subject stop work order or otherwise bar Stevens

Construction from continuing to complete its work on the project. That same day,

the Architect issued a certification in its role as the initial decision maker under the

General Conditions of the contract, providing reasons why sufficient cause existed

for terminating Stevens Construction under the terms of the contract. After

receiving the certification -of c-ause letter from the Architect, the Fire District

issued a letter to Stevens Construction and its surety, dated August 24, 2018, via

3 electronic and certified mail, providing seven days written notice prior to the Fire

District' s termination for cause of Stevens Construction. On September 4, 2018,

the Fire District issued a Notice of Termination to Stevens Construction and its

surety by both electronic and certified mail, citing Articles 14.2. 1. and 14. 2. 2 of the

General Conditions and Article 3. 10.3 of the Supplementary Conditions of the

contract, detailing the reasons the Fire District found sufficient cause for

terminating Stevens Construction and attaching the Architect' s certification.

The district court held a hearing on the preliminary injunction on September

4 and 6, 2018.' Following the hearing, wherein the court heard testimony and

received evidence, the district court took the matter under advisement. On

September 13, 2018, the district court issued its reasons for judgment, finding that

in the time between the issuance of the temporary restraining order and the hearing

on the preliminary injunction, the Fire District had complied with the terms of the

contract between it and Stevens Construction in order to terminate Stevens

Construction. Accordingly, the district court found that Stevens Construction' s

request for a preliminary injunction should be denied, and that its temporary

restraining order should likewise be dissolved. The district court instructed

counsel for the Fire District to submit a judgment reflecting the court' s ruling.

A judgment submitted by the Fire District was signed by the district court, 2 with a date of September 20, 2018. On October 4, 2018, Stevens Construction

filed a motion for new trial from the district court' s September 20, 2018 judgment

denying its request for preliminary injunction and dissolving its temporary

restraining order. The following day, the district court signed a rule ordering the

Fire District and Architect to show cause as to why Stevens Construction' s motion

The hearing began on September 4, 2018, but was continued to September 6, 2018, due to approaching Tropical Storm Gordon.

2The district court apparently dated this judgment in error, as it was actually signed on September 21, 2018. 4 should not be granted. The district court specifically wrote on the order that the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bayou Hunting Club of Hunter v. DeSoto Parish Police Jury
569 So. 2d 252 (Louisiana Court of Appeal, 1990)
Ex Parte Burr & Forman, LLP
5 So. 3d 557 (Supreme Court of Alabama, 2008)
Baton Rouge v. DEPART. OF SOCIAL SERVICES
970 So. 2d 985 (Louisiana Court of Appeal, 2007)
Morris v. Transtates Petroleum, Inc.
246 So. 2d 183 (Supreme Court of Louisiana, 1971)
VaSalle v. Wal-Mart Stores, Inc.
801 So. 2d 331 (Supreme Court of Louisiana, 2001)
Zulu v. Washington
487 So. 2d 1248 (Louisiana Court of Appeal, 1986)
First Bank and Trust v. Duwell
70 So. 3d 15 (Louisiana Court of Appeal, 2011)
Roba, Inc. v. Courtney
47 So. 3d 509 (Louisiana Court of Appeal, 2010)
First Guaranty Bank v. Perilloux
498 So. 2d 239 (Louisiana Court of Appeal, 1986)
In re Harrier Trust
259 So. 3d 402 (Louisiana Court of Appeal, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Stevens Construction & Design, L.L.C. v. St. Tammany Fire Protection District No. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stevens-construction-design-llc-v-st-tammany-fire-protection-lactapp-2020.