Stehli v. Action Custom Homes Inc., Unpublished Decision (9-24-1999)

CourtOhio Court of Appeals
DecidedSeptember 24, 1999
DocketNo. 98-G-2189.
StatusUnpublished

This text of Stehli v. Action Custom Homes Inc., Unpublished Decision (9-24-1999) (Stehli v. Action Custom Homes Inc., Unpublished Decision (9-24-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stehli v. Action Custom Homes Inc., Unpublished Decision (9-24-1999), (Ohio Ct. App. 1999).

Opinion

OPINION
This is an accelerated appeal taken from a final judgment of the Geauga County Court of Common Pleas. Appellants, John and Marie Stehli, appeal from the trial court's issuance of a stay pending arbitration.

In April 1997, appellants entered into a contract with appellee, Action Custom Homes, Inc. Appellee is an Ohio corporation engaged in the business of building custom homes. Pursuant to the contract with appellants, appellee agreed to construct a single-family residence on real property located in Chardon, Ohio. The purchase price of the house was to be $340,027.

During the construction process, appellants and appellee disagreed over the quality of the work and whether the company was building the house in accordance with the specifications listed in the contract. Upon mutual agreement of the parties, appellee eventually ceased construction of the house.

On August 11, 1998, appellants filed a lawsuit against appellee in the trial court. In their complaint, appellants set forth three claims for relief: (1) breach of contract and express warranty; (2) negligence; and (3) violations of the Consumer Sales Practices Act ("CSPA"), R.C. 1345.01 et seq. Appellants attached a copy of the contract to the complaint.

Instead of preparing an answer, appellee responded by filing a motion to dismiss the complaint on August 21, 1998. As grounds for the motion, appellee asserted that the contract contained an arbitration clause which provided the sole method for resolving any controversy or claim relating to the contractual relationship between the parties. Given the existence of this clause, appellee maintained that the trial court had a duty to dismiss the pending complaint.

Appellee appended various documentary exhibits to its motion to dismiss the complaint. These documents demonstrated that appellee previously filed a demand for arbitration with the American Arbitration Association ("AAA") on June 12, 1998. Appellants submitted an answering statement on July 1, 1998. Appellants, however, attached a memorandum to their answer in which they objected to arbitration based on the fact that they intended to assert non-contract claims against appellee. Despite the lodging of this objection, the arbitration procedure continued with the parties selecting acceptable arbitrators from a list of names prepared by AAA. In August 1998, AAA appointed a mutually acceptable arbitrator and scheduled the arbitration to take place in Cuyahoga County, Ohio.1

Appellee relied on these documents to establish not only that the contract contained an arbitration clause, but that the company had commenced the process of arbitrating the dispute prior to appellants' filing of the complaint. The trial court treated appellee's motion to dismiss as a motion for stay of the judicial proceedings pending arbitration. After being granted an extension of time in which to respond, appellants filed a memorandum in opposition to the request for a stay.

Appellants offered three primary reasons as to why the trial court should not stay the proceedings pending the submission of the dispute to arbitration. First, appellants argued that the complaint encompassed causes of action that were beyond the contract. Second, appellants suggested that the complaint alleged claims that were within the exclusive jurisdiction of the state court system, thereby making such matters inappropriate for resolution through AAA procedures. Third, appellants asserted that the entire contract was void because there had been fraud in its inducement, thereby making the arbitration clause itself a nullity.

On September 16, 1998, the trial court granted the motion to stay the proceedings pending arbitration. In doing so, the trial court concluded that appellants had not pled any cause of action beyond the contract. The trial court also ruled that it did not have exclusive jurisdiction over the particular claims for relief that had been set forth in appellants' complaint.

With regard to the issue of fraudulent inducement, the trial court agreed that arbitration would not have been the appropriate forum had appellants actually sought rescission of the entire contract. After reviewing the complaint, however, the trial court concluded that appellants had not included such a claim for relief. Instead, the trial court determined that the claims subsumed within the complaint related exclusively to appellee's performance of its obligations under the contract. The trial court deemed the arbitration clause to remain in effect since all of the claims arose out of or related to the parties' contractual agreement. Given the continuing validity of this clause, the trial court stayed any further action on the complaint pending arbitration.

From this judgment, appellants filed a timely notice of appeal with this court. They now assert the following assignment of error:

"The trial court committed reversible error when it issued an order staying the case pending arbitration."

In their sole assignment of error, appellants posit that the trial court erred by issuing the stay pending arbitration. Appellants submit that arbitration is improper in this case. The threefold basis for appellants' position before this court is the same as they advanced in the trial court, to wit: the complaint included causes of action that were beyond the contract, the complaint alleged claims that were within the exclusive jurisdiction of the courts, and the arbitration clause was invalid because the entire contract was void for fraud in its inducement.

As an initial matter, it must be noted that public policy in Ohio encourages the resolution of disputes through arbitration.Kelm v. Kelm (1993), 68 Ohio St.3d 26, 27; Youghiogheny OhioCoal Co. v. Oszust (1986), 23 Ohio St.3d 39, 41; Dayton TeachersAssn. v. Dayton Bd. of Edn. (1975), 41 Ohio St.2d 127, 132-133. Any uncertainty regarding the applicability of an arbitration clause should be resolved in favor of coverage. An arbitration clause should not be denied effect unless it can be determined to a high degree of certainty that the clause does not cover the asserted dispute. Grcar v. Lanmark Homes, Inc. (June 12, 1992), Lake App. No. 91-L-128, unreported, at 1, 1992 WL 134235. See, also, Independence Bank v. Erin Mechanical (1988), 49 Ohio App.3d 17,18; Gibbons-Grable Co. v. Gilbane Bldg. Co. (1986), 34 Ohio App.3d 170,173.

The validity of arbitration provisions has been codified by the General Assembly. R.C. 2711.01 provides in part:

"(A) A provision in any written contract, except as provided in division (B) of this section, to settle by arbitration a controversy that subsequently arises out of the contract, or out of the refusal to perform the whole or any part of the contract, * * * shall be valid, irrevocable, and enforceable, except upon grounds that exist at law or in equity for the revocation of any contract."

R.C. 2711.03 states that a party aggrieved by the failure of another to submit to arbitration may petition a common pleas court for an order directing that arbitration proceed in the manner provided for by a written agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Independence Bank v. Erin Mechanical
550 N.E.2d 198 (Ohio Court of Appeals, 1988)
Mid-America Acceptance Co. v. Lightle
579 N.E.2d 721 (Ohio Court of Appeals, 1989)
Gibbons-Grable Co. v. Gilbane Building Co.
517 N.E.2d 559 (Ohio Court of Appeals, 1986)
Dayton Classroom Teachers Ass'n v. Dayton Board of Education
323 N.E.2d 714 (Ohio Supreme Court, 1975)
Youghiogheny & Ohio Coal Co. v. Oszust
491 N.E.2d 298 (Ohio Supreme Court, 1986)
Kelm v. Kelm
623 N.E.2d 39 (Ohio Supreme Court, 1993)
ABM Farms, Inc. v. Woods
692 N.E.2d 574 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Stehli v. Action Custom Homes Inc., Unpublished Decision (9-24-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/stehli-v-action-custom-homes-inc-unpublished-decision-9-24-1999-ohioctapp-1999.