Painesville Township Local School District v. National Energy Management Institute

681 N.E.2d 1369, 113 Ohio App. 3d 687
CourtOhio Court of Appeals
DecidedAugust 26, 1996
DocketNo. 96-L-014.
StatusPublished
Cited by12 cases

This text of 681 N.E.2d 1369 (Painesville Township Local School District v. National Energy Management Institute) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Painesville Township Local School District v. National Energy Management Institute, 681 N.E.2d 1369, 113 Ohio App. 3d 687 (Ohio Ct. App. 1996).

Opinion

*690 Christley, Judge.

This is an accelerated calendar appeal, stemming from a final judgment of the Lake County Court of Common Pleas. Appellants, National Energy Management Institute (“NEMI”) and NEMI Services Corporation (“NSC”), seek the reversal of the trial court’s decision, which denied their joint motion to stay the trial proceedings pending arbitration.

In August 1992, NEMI entered into an agreement with appellee, Painesville Township Local School District, to provide certain energy management services. As part of this agreement, NEMI promised to conduct a preliminary assessment of the energy consumption “characteristics” of appellee’s buildings, and to design a plan under which the buildings would be made more energy efficient. NEMI further agreed to oversee the installation of energy efficient equipment in the buildings.

As part of the preliminary assessment, NEMI was obligated to give appellee a statement of the amount of funds it would save in energy costs if the proposed plan were followed. In conjunction with this particular obligation, NEMI “warranted” that appellee would save the specified amount.

In addition to the foregoing warranty, the agreement contained a provision which gave appellee the option of purchasing a second warranty covering the specified amount of energy savings. Under this second warranty, which would be issued by a separate company, appellee would be entitled to recover the difference between the projected savings and the actual savings in any given year.

Besides the foregoing provisions, the agreement between NEMI and appellee had an arbitration provision. This provision stated, in part:

“Any dispute, controversy or claim arising out of or in connection with or relating to this Agreement or any breach or alleged breach hereof, shall, upon request of either party (and without regard to whether or not any provision of this Agreement expressly provides for arbitration), be submitted to and settled by arbitration in the county where the Premises are situated in conformance with rules of the American Arbitration Association then in effect (or at any other place or under any other form of arbitration mutually acceptable to the parties).”

After NEMI had conducted the preliminary assessment and had given appellee the statement of the projected energy savings, appellee hired two contractors to install the new equipment. These contractors were approved by NEMI. In addition, at some point after the preliminary assessment had been completed, appellee decided to purchase the second warranty. This warranty was issued to appellee by NSC.

*691 Approximately thirty months after the primary agreement between NEMI and appellee had been executed, a dispute developed concerning whether appellee’s actual energy savings during the first year had been equal to the projected amount. When this dispute could not be settled amicably, appellee brought the instant action in November 1995. In its complaint, appellee named NEMI, NSC, and the two contractors, Roth Brothers, Inc., and Traditional Building Systems, Inc., as the defendants in this action.

Appellee’s complaint contained thirteen separate causes of action, nine of which were applicable to both NEMI and NSC. These nine causes of action set forth claims which sounded in breach of warranty, breach of contract, conversion, fraud, wrongful termination, and unjust enrichment.

Prior to answering the complaint, NEMI and NSC moved to stay the trial proceedings on the basis that the entire action should be submitted to arbitration. The two contractors also joined in this motion. In support of this motion, NEMI and NSC argued that the arbitration provision in the agreement between NEMI and appellee was controlling because all of the causes of action in the complaint were based upon the basic contractual relationship between NEMI and appellee.

In opposing the motion, appellee primarily asserted that the case could not be submitted to arbitration because its causes of action against NEMI and NSC were not the type of claims which could be resolved by an arbitrator. Specifically, appellee contended that its causes of action were not arbitrable because the resolution of those causes involved the application of Ohio statutory law pertaining to insurance contracts. As a separate argument, appellee maintained that the motion should be denied because NEMI and NSC had not properly perfected their demand for arbitration.

After NEMI and NSC had filed a reply brief on the matter, the trial court denied the motion to stay. In doing so, the trial court did not set forth the basis of its decision in its judgment entry.

Even though the two contractors had originally joined in the motion, they did not appeal from the foregoing judgment. As a result, the only appellants in the instant appeal are NEMI and NSC. In their brief, they have raised the following as error:

“The trial court erred to the prejudice of defendants-appellants National Energy Management Institute and NEMI Services Corp. in overruling their motion to stay pending the resolution of arbitration.”

In maintaining that their motion to stay should have been granted, appellants have essentially restated the argument which formed the basis of their motion. Specifically, they contend that a stay was warranted in this instance because all of appellee’s causes of actions could be submitted to arbitration under *692 the arbitration provision in the basic agreement between NEMI and appellee. Stated differently, appellants assert that each of the nine causes of action pertaining to them were arbitrable because each arose from the agreement between NEMI and appellee.

R.C. 2711.02 governs the issuance of a stay of trial proceedings when one party to an action has initiated an arbitration proceeding. This statute provides:

“If any action is brought upon any issue referable to arbitration under an agreement in writing for arbitration, the court in which the action is pending, upon being satisfied that the issue involved in the action is referable to arbitration under an agreement in writing for arbitration, shall on application of one of the parties stay the trial of the action until the arbitration of the issue has been had in accordance with the agreement, provided the applicant for the stay is not in default in proceeding with arbitration. * * * ”

Under R.C. 2711.02, a trial court is obligated to stay the trial proceedings once the court has determined that the issues raised in the action are referable to arbitration. In addition, the statute indicates that the determination of whether an issue is subject to arbitration is controlled by the language of the arbitration provision in the agreement between the parties.

In applying R.C. 2711.02, this court has held that any dispute concerning whether a particular issue is covered under an arbitration provision should be resolved in favor of coverage, ie., arbitration provisions should be interpreted in a broad manner. Grcar v. Lanmark Homes, Inc. (June 12,1992), Lake App. No. 91-L-128, unreported, 1992 WL 134235.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yoby v. Cleveland
2025 Ohio 5853 (Ohio Court of Appeals, 2025)
Epps v. State Farm Auto. Ins.
2022 Ohio 4084 (Ohio Court of Appeals, 2022)
Estate of Westover v. Wilson, 2007 Ca 00177 (3-17-2008)
2008 Ohio 1250 (Ohio Court of Appeals, 2008)
Peltz v. Moyer, 06 Be 11 (9-17-2007)
2007 Ohio 4998 (Ohio Court of Appeals, 2007)
Maestle v. Best Buy Co., Unpublished Decision (8-11-2005)
2005 Ohio 4120 (Ohio Court of Appeals, 2005)
Juhasz v. Costanzo
761 N.E.2d 679 (Ohio Court of Appeals, 2001)
Smith v. Whitlatch & Co.
739 N.E.2d 857 (Ohio Court of Appeals, 2000)
Boedeker v. Rogers
736 N.E.2d 955 (Ohio Court of Appeals, 1999)
Ohio Patrolmen's Benevolent Ass'n v. Village of Lordstown
691 N.E.2d 1069 (Ohio Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
681 N.E.2d 1369, 113 Ohio App. 3d 687, Counsel Stack Legal Research, https://law.counselstack.com/opinion/painesville-township-local-school-district-v-national-energy-management-ohioctapp-1996.