State v. Messer

2017 Ohio 1223
CourtOhio Court of Appeals
DecidedMarch 31, 2017
DocketL-16-1109
StatusPublished
Cited by10 cases

This text of 2017 Ohio 1223 (State v. Messer) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Messer, 2017 Ohio 1223 (Ohio Ct. App. 2017).

Opinion

[Cite as State v. Messer, 2017-Ohio-1223.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT LUCAS COUNTY

State of Ohio Court of Appeals No. L-16-1109

Appellee Trial Court No. CR0201502616

v.

Ernest Keith Messer DECISION AND JUDGMENT

Appellant Decided: March 31, 2017

*****

Julia R. Bates, Lucas County Prosecuting Attorney, and Claudia A. Ford, Assistant Prosecuting Attorney, for appellee.

W. Alex Smith, for appellant.

MAYLE, J.

{¶ 1} Defendant-appellant, Ernest K. Messer, appeals the May 12, 2016 judgment

of the Lucas County Court of Common Pleas convicting him of grand theft by deception.

Finding no error, we affirm. I. Background

{¶ 2} On September 29, 2015, Messer was indicted on one count of grand theft, in

violation of R.C. 2913.02(A)(3) and (B)(2). The following facts were elicited at the

January 28, 2016 jury trial.

{¶ 3} In late 2014, Rebecca Moorman solicited bids for a bathroom remodeling

project from three contractors, including Messer. In determining which to hire, Moorman

testified that she considered each contractor’s total price, proposed date of completion,

and licensure status. Messer’s bid was several thousand dollars less than the other bids

and his proposed completion date for the project was several weeks earlier. He also

assured Moorman that he was licensed, bonded, and insured, and that he would obtain the

building permits required for the project. Moorman hired Messer for the remodeling

project based on these representations.

{¶ 4} Messer and Moorman signed a contract for the project on November 8,

2014. The contract required Messer to move plumbing; replace the toilet and bathtub;

retile the floor, walls, and shower; move a wall and a door; build a double sink vanity

with cabinets; and paint the walls and ceiling. Moorman testified that Messer agreed to

use her payments to purchase any fixtures and supplies that were needed for the project.

The parties agreed to a total price of $27,500, with $8,250 due at the time of signing the

contract, $8,250 due the day Messer started work, $8,250 due on January 27, 2015, and

$2,750 due upon completion of the job. Messer told Moorman that he would start work

on January 5, 2015, have the majority of the project finished before Moorman and her

2. husband left for a vacation at the beginning of February, and complete the project by the

end of February.

{¶ 5} Moorman paid Messer $8,250 on November 8, 2014, the day she signed the

contract. On January 7, 2015, she paid Messer $9,250, representing the second

installment payment plus $1,000 for Messer to use to purchase tile. Moorman made the

third installment payment of $8,250 on January 26, 2015. In total, Moorman paid Messer

$25,750.

{¶ 6} Messer began work on January 6, 2015. Although Messer performed some

work in January, Moorman testified that the project was very incomplete when she and

her husband left for their trip at the beginning of February and that Messer performed no

work while they were gone. Messer nonetheless assured Moorman that the project was

still on schedule to be finished by the end of February. He did not, however, perform as

promised. He routinely failed to appear for work, and when he did appear (either

personally or by sending employees) it was only for a few hours at a time. Messer also

became increasingly difficult to reach because he stopped answering Moorman’s phone

calls and text messages. On the rare occasions that he was at the house, Moorman would

ask when he planned to complete the project and when the supplies for the project would

be delivered to the house. Messer assured her that he would get it done. Sometime in

March, the parties agreed to a new completion deadline of April 1, 2015, which Messer

did not meet.

3. {¶ 7} Messer’s pattern of dilatory behavior continued for the next several months.

In May and June 2015, Messer gave Moorman numerous excuses for not working on her

bathroom, including serious family issues, car troubles, spending time with his wife on

their anniversary, returning rental equipment, “taking care of business,” spending the day

at the University of Toledo, building a casket for and mourning the death of his cat, and

attending his daughter’s graduation. He often failed to appear at the house on the days

and times he told Moorman he would be there.

{¶ 8} At the end of July 2015, Moorman learned that Messer had not paid his

granite supplier for the countertop he installed in the bathroom and that the supplier

intended to place a lien on her property for the $1,795.50 balance. On July 30, 2015,

Moorman and her husband sent Messer a letter demanding that he deliver all remaining

supplies, including faucets, cabinets, hardware, shower fixtures, mirrors, a Jacuzzi

bathtub and a toilet, and that he complete the remodel by August 14, 2015. Messer did

neither.

{¶ 9} Moorman contacted the Washington Township Police Department around

August 14, 2015. Detective Sergeant John Van Hersett came to her home to investigate.

He found an unfinished bathroom, which he photographed. He did not find the faucets,

fixtures, or bathtub.

{¶ 10} The photographs admitted at trial by both the state and the defense show

that Messer did perform some work: he tore out the old floor and fixtures; tiled the floor,

walls, and shower; moved the door; and installed the cabinet frame, granite countertop,

4. sink, and bathtub frame during the seven-month period from the time Messer began the

project to the day Moorman called the police. There was, however, still a substantial

amount of additional work that remained unfinished in August 2015. Messer had not

purchased or installed a toilet, purchased or installed a Jacuzzi tub, installed sink faucets,

installed a showerhead or shower handle, finished the bathtub frame, covered the exposed

pipes, or mounted the cabinet doors. Moorman testified that she paid another contractor

$22,000 to complete the bathroom remodel.

{¶ 11} Moorman later learned that, contrary to Messer’s pre-contract

representations, he did not have any type of contractor’s license or insurance, he was not

registered as a contractor in Lucas County, and he did not apply for or receive any

permits for the project. Christopher Kiel, Lucas County’s chief building official,

confirmed that Messer is not licensed as a contractor in Lucas County and that he did not

apply for any permits relating to the project. Moorman testified she would not have hired

Messer if she had known he was not licensed, bonded, and insured, though she did not

ask him to see any licenses or insurance paperwork.

{¶ 12} Daniel Crigger Jr., one of Messer’s laborers, testified that he worked at

Moorman’s house for 30 to 40 days in December 2014 and January 2015, but could not

remember if he worked at the house in the spring. According to Crigger, Moorman’s

bathroom was 90 percent finished the last time he was in it and the state’s photographs

did not depict the way he recalled the bathroom. He claimed that when Messer and his

5. employees were asked to leave the house, everything was complete except for installing

the lights, switches, bathtub, toilet, and possibly some cabinet doors.

{¶ 13} After the state presented its evidence, Messer moved for dismissal under

Crim.R. 29, which the court denied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Jones
2026 Ohio 634 (Ohio Court of Appeals, 2026)
State v. Hagerman
2025 Ohio 5820 (Ohio Court of Appeals, 2025)
State v. Cortez
2025 Ohio 5736 (Ohio Court of Appeals, 2025)
State v. Howard
2025 Ohio 5486 (Ohio Court of Appeals, 2025)
State v. Syph
2025 Ohio 5075 (Ohio Court of Appeals, 2025)
State v. Gonzales
2025 Ohio 3305 (Ohio Court of Appeals, 2025)
State v. Cavin
2025 Ohio 1578 (Ohio Court of Appeals, 2025)
State v. Haas
2025 Ohio 683 (Ohio Court of Appeals, 2025)
State v. Brown
2020 Ohio 1650 (Ohio Court of Appeals, 2020)
State v. Ridley
2020 Ohio 402 (Ohio Court of Appeals, 2020)
State v. Jefferson
2017 Ohio 7272 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 1223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-messer-ohioctapp-2017.