State of Missouri Ex Rel. John Ashcroft, Missouri Clean Water Commission, Department of Natural Resources, the Missouri Conservation Commission, Dale Rountree, Max A. Smith, Calvin C. Johnson, Alton Burns, James E. Jones, Kenneth D. McCall Ray Pinkman, Shelby A. Masters, Scott Johnson and David Johnson v. Department of the Army, Corps of Engineers, Clifford Alexander, Jr., Lt. Gen. John W. Morris and Col. Richard Curl, State of Missouri Ex Rel. John Ashcroft, Missouri Clean Water Commission, Department of Natural Resources, the Missouri Conservation Commission, Dale Rountree, Max A. Smith, Calvin C. Johnson, Alton Burns, James E. Jones, Kenneth D. McCall Ray Pinkman, Shelby A. Masters, Scott Johnson and David Johnson v. Department of the Army, Corps of Engineers, Clifford Alexander, Jr., Lt. Gen. John W. Morris and Col. Richard Curl

672 F.2d 1297
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 9, 1982
Docket81-1224
StatusPublished
Cited by4 cases

This text of 672 F.2d 1297 (State of Missouri Ex Rel. John Ashcroft, Missouri Clean Water Commission, Department of Natural Resources, the Missouri Conservation Commission, Dale Rountree, Max A. Smith, Calvin C. Johnson, Alton Burns, James E. Jones, Kenneth D. McCall Ray Pinkman, Shelby A. Masters, Scott Johnson and David Johnson v. Department of the Army, Corps of Engineers, Clifford Alexander, Jr., Lt. Gen. John W. Morris and Col. Richard Curl, State of Missouri Ex Rel. John Ashcroft, Missouri Clean Water Commission, Department of Natural Resources, the Missouri Conservation Commission, Dale Rountree, Max A. Smith, Calvin C. Johnson, Alton Burns, James E. Jones, Kenneth D. McCall Ray Pinkman, Shelby A. Masters, Scott Johnson and David Johnson v. Department of the Army, Corps of Engineers, Clifford Alexander, Jr., Lt. Gen. John W. Morris and Col. Richard Curl) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Missouri Ex Rel. John Ashcroft, Missouri Clean Water Commission, Department of Natural Resources, the Missouri Conservation Commission, Dale Rountree, Max A. Smith, Calvin C. Johnson, Alton Burns, James E. Jones, Kenneth D. McCall Ray Pinkman, Shelby A. Masters, Scott Johnson and David Johnson v. Department of the Army, Corps of Engineers, Clifford Alexander, Jr., Lt. Gen. John W. Morris and Col. Richard Curl, State of Missouri Ex Rel. John Ashcroft, Missouri Clean Water Commission, Department of Natural Resources, the Missouri Conservation Commission, Dale Rountree, Max A. Smith, Calvin C. Johnson, Alton Burns, James E. Jones, Kenneth D. McCall Ray Pinkman, Shelby A. Masters, Scott Johnson and David Johnson v. Department of the Army, Corps of Engineers, Clifford Alexander, Jr., Lt. Gen. John W. Morris and Col. Richard Curl, 672 F.2d 1297 (8th Cir. 1982).

Opinion

672 F.2d 1297

17 ERC 1001, 12 Envtl. L. Rep. 20,368

STATE OF MISSOURI ex rel. John ASHCROFT, Missouri Clean
Water Commission, Department of Natural Resources,
The Missouri Conservation Commission,
Appellants, Dale Rountree, Max A. Smith, Calvin C. Johnson,
Alton Burns, James E. Jones, Kenneth D. McCall,
Ray Pinkman, Shelby A. Masters, Scott
Johnson and David Johnson,
v.
DEPARTMENT OF THE ARMY, Corps of Engineers, Clifford
Alexander, Jr., Lt. Gen. John W. Morris and Col.
Richard Curl, Appellees.
STATE OF MISSOURI ex rel. John ASHCROFT, Missouri Clean
Water Commission, Department of Natural Resources,
The Missouri Conservation Commission,
Dale Rountree, Max A. Smith, Calvin C. Johnson, Alton Burns,
James E. Jones, Kenneth D. McCall, Ray Pinkman,
Shelby A. Masters, Scott Johnson and
David Johnson, Appellants,
v.
DEPARTMENT OF THE ARMY, Corps of Engineers, Clifford
Alexander, Jr., Lt. Gen. John W. Morris and Col.
Richard Curl, Appellees.

Nos. 81-1224, 81-1225.

United States Court of Appeals,
Eighth Circuit.

Submitted Nov. 12, 1981.
Decided March 9, 1982.

John Ashcroft, Atty. Gen., Jerry Short, Asst. Atty. Gen., Jefferson City, Mo., for appellants.

Joseph B. Phillips, Stockton, Mo., for Class Action appellants.

William B. Ellis, Hunton & Williams, Richmond, Va., for amici curiae.

J. Whitfield Moody, U. S. Atty., E. Eugene Harrison, Asst. U. S. Atty., August V. Spallo, Terence J. Kelley, Asst. Dist. Counsels, U. S. Army Corps of Engineers, Kansas City, Mo., for appellees.

Before ROSS and STEPHENSON, Circuit Judges, and HOWARD,* District Judge.

STEPHENSON, Circuit Judge.

Plaintiff-appellants representing the state of Missouri and affected landowners appeal the district court's1 denial of relief from defendants-appellees Department of the Army, Corps of Engineers. Appellants allege the Corps of Engineers acted without authority in constructing a 45,200 kilowatt (kw) generator on the Sac River near Stockton, Missouri. The district court, in a well-reasoned and thorough opinion, denied relief on all grounds. State of Missouri v. Department of the Army, Corps of Engineers, 526 F.Supp. 660 (W.D.Mo.1980). We affirm the district court's denial of relief for the reasons set out in its opinion with some additional comment.

I. FACTS

Through the passage of the Flood Control Act of 1954, Congress authorized the Army Corps of Engineers to construct a dam and generator near Stockton, Missouri, on the Sac River. This authorization was pursuant to an extensive study completed during the 1940's by the Corps of Engineers. It recommended an extensive construction program calling for the erection of a series of dams, primarily for flood control, on the Missouri, Kansas, and Osage Rivers and the tributaries of the Osage River.

Originally, the Corps of Engineers recommended a 7000 kw generator be placed at the Stockton dam. However, as the years passed, the Corps of Engineers increased the recommended size of the generator several times.2 Each of the changes in the generator size was included in the Corps of Engineers' requested appropriation for that year and each time Congress approved the request.

The last increase was sought in 1963, when the Corps of Engineers requested an appropriation for a 45,200 kw generator with an overload capacity of 52,000 kw and Congress approved it. To operate the generator at 45,200 kw production, there must be a flowage of 11,000 c.f.s. and to operate the generator at the capacity of 52,000 kw requires a release of 14,000 c.f.s.

Construction of the project began soon after Congress passed the 1963 appropriation. A test release of water from the dam in 1972 revealed that the Corps of Engineers had grossly overestimated the channel capacity of the river below the dam. The release of 6,000 c.f.s. resulted in an overflow at several places along the Sac River. Upon further investigation, the Corps of Engineers discovered the flowage capacity of the river was 5,300 c.f.s. instead of the 12,000 c.f.s. that the Corps of Engineers had originally estimated. At the time the Corps discovered the miscalculation in the channel capacity of the Sac River, construction of the Stockton project was virtually complete.

As a result of the downstream flooding, the Corps of Engineers considered various solutions to the problem, including the construction of levees or a re-regulation structure, widening or deepening the channel, or constructing one or more channel cut-offs to shorten the stream's length. Operation of the generator at rates between 15,000 kw and 40,000 kw is not a feasible alternative because of vibration. The Corps of Engineers, however, agreed to limit discharge to 5,000 c.f.s., pending resolution of the problem.

In the spring of 1976, after extensive investigation and discussion with state and federal agencies and persons living along the Sac River downstream of the dam, the Corps of Engineers proposed a solution composed of (1) purchasing flowage easements on 1337 acres of land downstream, (2) constructing one channel cut-off and (3) limiting discharges from the dam to 8,000 c.f.s. for six hours' duration thereby generating some 40,000 kw of electricity. The Corps of Engineers presented testimony and reports to House and Senate committees and subcommittees from 1976 through 1978. Funds for the implementation of the proposed solution were subsequently appropriated by Congress.

Appellants filed this lawsuit on March 22, 1978, seeking declaratory, mandamus and injunctive relief from the operation and proposed operation of the Stockton dam power plant. Plaintiffs alleged that the defendants' operation and the proposed operation of the hydropower facilities were not congressionally authorized, constituted an actionable nuisance, and were in violation of the Administrative Procedure Act (APA), the National Environmental Policy Act (NEPA), the Fish and Wildlife Coordination Act (FWCA), Federal Water Pollution Control Act (FWPCA), and the Missouri Clean Water Law (MCWL).

After a trial without a jury, the district court found that the Corps of Engineers had complied with all the necessary procedures and laws. It concluded the Corps of Engineers had acted within its authority in installing the 45,200 kw generator and in implementing the compromise solution regarding its operation.

II. ISSUES

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hedel-Ostrowski v. City of Spearfish
2004 SD 55 (South Dakota Supreme Court, 2004)
North Dakota v. United States Army Corps of Engineers
270 F. Supp. 2d 1115 (D. North Dakota, 2003)
Kuper v. Lincoln-Union Electric Co.
1996 SD 145 (South Dakota Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
672 F.2d 1297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-missouri-ex-rel-john-ashcroft-missouri-clean-water-commission-ca8-1982.