Missouri ex rel. Ashcroft v. Department of the Army

672 F.2d 1297
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 9, 1982
DocketNos. 81-1224, 81-1225
StatusPublished
Cited by13 cases

This text of 672 F.2d 1297 (Missouri ex rel. Ashcroft v. Department of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Missouri ex rel. Ashcroft v. Department of the Army, 672 F.2d 1297 (8th Cir. 1982).

Opinion

STEPHENSON, Circuit Judge.

Plaintiff-appellants representing the state of Missouri and affected landowners appeal the district court’s1 denial of relief from defendants-appellees Department of the Army, Corps of Engineers. Appellants allege the Corps of Engineers acted without authority in constructing a 45,200 kilowatt (kw) generator on the Sac River near Stockton, Missouri. The district court, in a well-reasoned and thorough opinion, denied relief on all grounds. State of Missouri v. Department of the Army, Corps of Engineers, 526 F.Supp. 660 (W.D.Mo.1980). We affirm the district court’s denial of relief for the reasons set out in its opinion with some additional comment.

I. FACTS

Through the passage of the Flood Control Act of 1954, Congress authorized the Army Corps of Engineers to construct a dam and generator near Stockton, Missouri, on the Sac River. This authorization was pursuant to an extensive study completed during the 1940’s by the Corps of Engineers. It recommended an extensive construction program calling for the erection of a series of dams, primarily for flood control, on the Missouri, Kansas, and Osage Rivers and the tributaries of the Osage River.

Originally, the Corps of Engineers recommended a 7000 kw generator be placed at the Stockton dam. However, as the years passed, the Corps of Engineers increased the recommended size of the generator several times.2 Each of the changes in the generator size was included in the Corps of Engineers’ requested appropriation for that year and each time Congress approved the request.

The last increase was sought in 1963, when the Corps of Engineers requested an appropriation for a 45,200 kw generator with an overload capacity of 52,000 kw and Congress approved it. To operate the generator at 45,200 kw production, there must be a flowage of 11,000 c.f.s. and to operate the generator at the capacity of 52,000 kw requires a release of 14,000 c.f.s.

Construction of the project began soon after Congress passed the 1963 appropriation. A test release of water from the dam in 1972 revealed that the Corps of Engi[1300]*1300neers had grossly overestimated the channel capacity of the river below the dam. The release of 6,000 c.f.s. resulted in an overflow at several places along the Sac River. Upon further investigation, the Corps of Engineers discovered the flowage capacity of the river was 5,300 c.f.s. instead of the 12.000 c.f.s. that the Corps of Engineers had originally estimated. At the time the Corps discovered the miscalculation in the channel capacity of the Sac River, construction of the Stockton project was virtually complete.

As a result of the downstream flooding, the Corps of Engineers considered various solutions to the problem, including the construction of levees or a re-regulation structure, widening or deepening the channel, or constructing one or more channel cut-offs to shorten the stream’s length. Operation of the generator at rates between 15,000 kw and 40,000 kw is not a feasible alternative because of vibration. The Corps of Engineers, however, agreed to limit discharge to 5.000 c.f.s., pending resolution of the problem.

In the spring of 1976, after extensive investigation and discussion with state and federal agencies and persons living along the Sac River downstream of the dam, the Corps of Engineers proposed a solution composed of (1) purchasing flowage easements on 1337 acres of land downstream, (2) constructing one channel cut-off and (3) limiting discharges from the dam to 8,000 c.f.s. for six hours’ duration thereby generating some 40,000 kw of electricity. The Corps of Engineers presented testimony and reports to House and Senate committees and subcommittees from 1976 through 1978. Funds for the implementation of the proposed solution were subsequently appropriated by Congress.

Appellants filed this lawsuit on March 22, 1978, seeking declaratory, mandamus and injunctive relief from the operation and proposed operation of the Stockton dam power plant. Plaintiffs alleged that the defendants’ operation and the proposed operation of the hydropower facilities were not congressionally authorized, constituted an actionable nuisance, and were in violation of the Administrative Procedure Act (APA), the National Environmental Policy Act (NEPA), the Fish and Wildlife Coordination Act (FWCA), Federal Water Pollution Control Act (FWPCA), and the Missouri Clean Water Law (MCWL).

After a trial without a jury, the district court found that the Corps of Engineers had complied with all the necessary procedures and laws. It concluded the Corps of Engineers had acted within its authority in installing the 45,200 kw generator and in implementing the compromise solution regarding its operation.

II. ISSUES

Appellants landowners and the state of Missouri argue three general grounds for reversal based on the district court’s alleged errors in failing to hold that (1) the Corps of Engineers abused its discretion by acting in bad faith in the planning and installation of the 45,200 kw generator or, even if the action was not in bad faith, it was outside the congressional authorization; (2) the Corps of Engineers had not complied with the APA, NEPA and FWCA through its filing of the Final Environmental Impact Statement (FEIS) and the Final Supplemental Environmental Impact Statement (FSEIS); and (3) the solution would violate the FWPCA and state and local water pollution laws.

Appellant state of Missouri argues three additional grounds for reversal based on the district court’s alleged errors in failing to hold that (1) the changes in the project were not within the, congressional authorization, thus violating the APA and NEPA; (2) the Corps of Engineers had not fully complied with the FWCA for the reason that they did not adequately consult with the United States Fish and Wildlife Service and state agencies regarding adverse impacts; and (3) the operation and proposed operation of the. dam constituted a nuisance.

[1301]*1301III. DISCUSSION

A. Abuse of Discretion — Outside Congressional Authorization3

Appellant landowners contend that the installation of the large capacity generator was either grossly negligent or intentional. As evidence, they point to the Corps of Engineers’ reliance on an inexperienced employee for the study of the river, the extreme misestimate of the flowage of the river, and the Corps of Engineers’ numerous expansions of the capacity of the generator.

We find no error in the district court’s finding that there was no gross negligence or intentional misconduct. Obviously, mistakes were made in the design of the project. However, appellants have not provided convincing evidence that these errors constituted grossly negligent or intentional actions.

Appellants landowners and the state of Missouri argue that even if the construction of the larger generator was not an abuse of discretion by being grossly negligent or intentional, it was action outside the authority granted to the Corps of Engineers by Congress.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kurt Froebel v. George E. Meyer
217 F.3d 928 (Seventh Circuit, 2000)
Bettis v. Town of Ontario, NY
800 F. Supp. 1113 (W.D. New York, 1992)
In Re Ohio River Disaster Litigation
579 F. Supp. 1273 (S.D. Ohio, 1984)
Union Mechling Corp. v. United States
579 F. Supp. 1273 (S.D. Ohio, 1984)
Avoyelles Sportsmen's League, Inc. v. Marsh
715 F.2d 897 (Fifth Circuit, 1983)
National Wildlife Federation v. Anne Gorsuch, in Her Official Capacity as Administrator of the United States Environmental Protection Agency, Idaho Power Company, Montana Power Company, Puget Sound Power and Light Company, Eugene Water and Electric Board, Portland General Electric Company, Public Utility District No. 1 of Chelan County, Washington, Public Utility District No. 1 of Douglas County, Washington, City of Seattle, Department of Lighting, City of Tacoma, Department of Public Utilities, Washington Water Power Company, National Wildlife Federation v. Anne Gorsuch, in Her Official Capacity as Administrator of the United States Environmental Protection Agency, Northern Colorado Water Conservancy District, City and County of Denver Acting Through the Board of Water Commissioners, City of Colorado Springs, Southwestern Water Conservation District, City of Aurora, Board of Water Works for the City of Pueblo, Colorado River Water Conservation District, Association of California Water Agencies, National Wildlife Federation v. Anne Gorsuch, in Her Official Capacity as Administrator of the United States Environmental Protection Agency, American Water Works Association and National Association of Water Companies, National Wildlife Federation v. Anne Gorsuch, in Her Official Capacity as Administrator of the United States Environmental Protection Agency, Blachly-Lane Electric Cooperative Association, Central Electric Cooperative, Inc., Clearwater Power Company, Columbia Rural Electric Association, Inc., Consumers Power, Inc., Inland Power & Light Company, Kootenai Electric Cooperative, Inc., Lane Electric Cooperative, Inc., Lower Valley Power & Light, Inc., Public Utility District No. 1 of Cowlitz County, Washington Raft River Rural Electric Cooperative, Inc., Umatilla Electric Cooperative Association, Benton Rural Electric Association, Big Bend Electric Cooperative, Inc., Coos-Curry Electric Cooperative, Inc., Lincoln Electric Cooperative, National Wildlife Federation v. Anne Gorsuch, in Her Official Capacity as Administrator of the United States Environmental Protection Agency. Appeal of National Water Resources Association. National Wildlife Federation v. Anne Gorsuch, in Her Official Capacity as Administrator of the United States Environmental Protection Agency, National Wildlife Federation v. Anne Gorsuch, in Her Official Capacity as Administrator of the United States Environmental Protection Agency. Appeal of Alabama Power Company
693 F.2d 156 (D.C. Circuit, 1982)
National Wildlife Federation v. Gorsuch
693 F.2d 156 (D.C. Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
672 F.2d 1297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/missouri-ex-rel-ashcroft-v-department-of-the-army-ca8-1982.