State Ex Rel. Utilities Commission v. Virginia Electric & Power Co.

206 S.E.2d 283, 285 N.C. 398, 6 P.U.R.4th 373, 1974 N.C. LEXIS 999
CourtSupreme Court of North Carolina
DecidedJuly 1, 1974
Docket76
StatusPublished
Cited by32 cases

This text of 206 S.E.2d 283 (State Ex Rel. Utilities Commission v. Virginia Electric & Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Utilities Commission v. Virginia Electric & Power Co., 206 S.E.2d 283, 285 N.C. 398, 6 P.U.R.4th 373, 1974 N.C. LEXIS 999 (N.C. 1974).

Opinion

LAKE, Justice.

APPEAL OF THE MUNICIPALITIES

The appellant municipalities contend: (1) By reason of their respective contracts with Vepco for service at specified rates, the Commission has no authority to enter an order approving increases in those rates until the expiration of such contracts; (2) if this be not so, G.S. 62-135 does not authorize Vepco to increase such rates prior to the entry of an order by the Commission approving the increase. We find no merit in either of these contentions.

Each of the contracts in question contains this provision: “The provisions of this agreement are on file with the North *406 Carolina Utilities Commission and this agreement is subject to modification or cancellation by the Commission in the manner prescribed by law.” The increases in the rates charged the municipalities were made by an order entered after a full hearing, held upon due notice and in which the appellant municipalities intervened as parties. The procedure prescribed by Chapter 62 of the General Statutes was followed. Thus, by the terms of the contracts, themselves, the provisions thereof fixing the rate for the service were subject to the change made by the order of the Commission.

Furthermore, even in the silence of the rate fixing contract upon this question, it is well settled in this State that rates for public utility service fixed by an order of the Commission, otherwise lawful, supersede contrary provisions in private contracts concerning rates for such service. Corporation Commission v. Water Co., 190 N.C. 70, 128 S.E. 465; Corporation Commission v. Manufacturing Co., 185 N.C. 17, 116 S.E. 178; In re Utilities Co., 179 N.C. 151, 101 S.E. 619. The enforcement of such an order of the Commission does not constitute an impairment of the obligation of such contract, in violation of the Contract Clause of the United States Constitution, since contracts of public utilities, fixing rates for service, are subject to the police power of the State. Union Dry Goods Co. v. Georgia Public Service Corp., 248 U.S. 372, 39 S.Ct. 117, 63 L.Ed. 309; Atlantic Coast Line Railroad v. Goldsboro, 232 U.S. 548, 34 S.Ct. 364, 58 L.Ed. 721; In re Utilities Co., supra. In this respect, there is no distinction between a contract made by the public utility with a municipality and one made by it with any other user of its service. Corporation Commission v. Water Co., supra; In re Utilities Co., supra.

The appellant municipalities cite in support of their position Federal Power Commission v. Sierra-Pacific Power Co., 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388, and United Gas Pipeline Co. v. Mobile Gas Service Corp., 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373. These cases do not support the contention of the appellant municipalities. While holding that the Federal Power Act and the Federal Natural Gas Act do not evince a purpose to abrogate private contracts fixing rates and that.such contracts may not be terminated by the unilateral act of the public utility company (see also, Southern Utilities Company v. Palatka, 268 U.S. 232, 45 S.Ct. 488, 69 L.Ed. 930), these cases recognize the authority of the Federal Power Commission to *407 prescribe a change in the rates fixed by such contracts whenever the Commission determines such rates to be unlawful. See also, United Gas Company v. Memphis Light, Gas and Water Division, 358 U.S. 103, 76 S.Ct. 368, 3 L.Ed. 2d 153.

It is in the public interest that a public utility company charge for its services rates which will enable it to maintain its financial ability to render adequate service and to attract the capital necessary for expansion and improvement of its service as needed. It is also in the public interest that there be no unreasonable discrimination between the users of such service. The police power of the state extends to the raising of rates fixed by private contract so as to accomplish either or both of these purposes.

G.S. 62-135 was enacted for the purpose of minimizing the effect of the unavoidable time lag between the filing of an application by a utility company for an increase in its rates for service and the entry of an order of the Commission finding such increase' proper. This statute authorizes the utility to put its proposed rates into effect after the passage of six months from the filing of its application, if no order has been entered by the Commission determining the validity of the proposed rates, and if the utility company files its undertaking, approved by the Commission, for a refund of any portion of such rates ultimately disapproved by the Commission. Vepco did so in this case.

The appellant municipalities contend that this is a mere unilateral termination of its contracts by Vepco. It is true that the mere existence in the Commission of authority to increase the rates specified in its contract does not authorize Vepco at its own will to disregard such contract and to charge the other party thereto a higher rate. Southern Utilities Company v. Palatka, supra. If the rate put into effect by the utility, pursuant to G.S. 62-135, is completely disallowed by the Commission, after a hearing, the contract remains in effect and the utility must refund the excess so collected. Thus Vepco cannot, by its own decision alone, free itself from its contract.

G.S. 62-135 is a direct exercise of the police power of the State by the Legislature itself. Thus, it too prevails over a private contract in conflict therewith. In Midland Realty Cocpany v. Kansas City Power & Light Co., 300 U.S. 109, 57 S.Ct. 345, 81 L.Ed. 540, the Supreme Court of the United States said:

“[The plaintiff] here insists that the contracts could not be abrogated ‘without a proper hearing, finding, and *408 order of the Commission with respect thereto.’ It does not, and reasonably could not, contend that immediate exertion by the legislature of the state’s power to prescribe and enforce reasonable and non-discriminatory rates depends upon or is conditioned by specific adjudication in respect of existing contract rates. It is clear that, as against those specified in the contract here involved, the rates first filed by the plaintiff and those promulgated by the Commission in accordance with the statute have the same force and effect as if directly prescribed by the legislature.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Utils. Comm'n v. Stein
Supreme Court of North Carolina, 2020
State Ex Rel. Utilities Commission v. North Carolina Natural Gas Corp.
375 S.E.2d 147 (Supreme Court of North Carolina, 1989)
State Ex Rel. Utilities Commission & Duke Power Co. v. Eddleman
358 S.E.2d 339 (Supreme Court of North Carolina, 1987)
Kansas Gas & Electric Co. v. Kansas Corporation Comm'n
720 P.2d 1063 (Supreme Court of Kansas, 1986)
State Ex Rel. Utilities Commission v. Carolina Utility Customers Ass'n
333 S.E.2d 259 (Supreme Court of North Carolina, 1985)
Colorado Municipal League v. Public Utilities Commission
687 P.2d 416 (Supreme Court of Colorado, 1984)
State Ex Rel. Utilities Commission v. Southern Bell Telephone & Telegraph Co.
299 S.E.2d 763 (Supreme Court of North Carolina, 1983)
State Ex Rel. Utilities Commission v. Duke Power Co.
287 S.E.2d 786 (Supreme Court of North Carolina, 1982)
State Ex Rel. Utilities Commission v. Springdale Estates Ass'n
265 S.E.2d 647 (Court of Appeals of North Carolina, 1980)
Bowman v. Maine State Employees Appeals Board
408 A.2d 688 (Supreme Judicial Court of Maine, 1979)
State Ex Rel. Utilities Commission v. Mebane Home Telephone Co.
257 S.E.2d 623 (Supreme Court of North Carolina, 1979)
State ex rel. Utilities Commission v. Farmers Chemical Ass'n
257 S.E.2d 439 (Court of Appeals of North Carolina, 1979)
People's Counsel v. Public Service Commission
399 A.2d 43 (District of Columbia Court of Appeals, 1979)
State ex rel. Utilities Commission
245 S.E.2d 787 (Court of Appeals of North Carolina, 1978)
State ex rel. Utilities Commission v. Mebane Home Telephone Co.
242 S.E.2d 165 (Court of Appeals of North Carolina, 1978)
United Telephone Co. of Iowa v. Iowa State Commerce Commission
257 N.W.2d 466 (Supreme Court of Iowa, 1977)
State Ex Rel. Util. Com'n v. Farmers Chemical Association, Inc.
235 S.E.2d 398 (Court of Appeals of North Carolina, 1977)
State Ex Rel. Utilities Commission v. Edmisten
230 S.E.2d 651 (Supreme Court of North Carolina, 1976)
SEN. CIT. CLUBS OF WINSTON-SALEM, ETC. v. Duke Power Co.
425 F. Supp. 411 (W.D. North Carolina, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
206 S.E.2d 283, 285 N.C. 398, 6 P.U.R.4th 373, 1974 N.C. LEXIS 999, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-utilities-commission-v-virginia-electric-power-co-nc-1974.