State Ex Rel. Utilities Commission v. Thornburg

342 S.E.2d 28, 316 N.C. 238, 1986 N.C. LEXIS 2062
CourtSupreme Court of North Carolina
DecidedApril 2, 1986
Docket278A85
StatusPublished
Cited by15 cases

This text of 342 S.E.2d 28 (State Ex Rel. Utilities Commission v. Thornburg) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Utilities Commission v. Thornburg, 342 S.E.2d 28, 316 N.C. 238, 1986 N.C. LEXIS 2062 (N.C. 1986).

Opinion

MEYER, Justice.

On 21 February 1984, Carolina Power & Light Company (hereinafter “CP&L”) filed an application with the North Carolina Utilities Commission (hereinafter “Commission”) for an increase in its rates for electric service to its retail customers in North Carolina so as to increase annual revenue by approximately $151.6 million, or 12.6%. In the application, CP&L proposed to make the rate increase effective 22 March 1984. In an order issued 21 March 1984, the Commission determined that the application constituted a general rate case and suspended the proposed rate increase for a period of up to 270 days. On 29 March 1984, the Commission issued an order scheduling public hearings on the proposed rate increase and establishing the test period as the twelve-month period ending 30 September 1983. The Public Staff-North Carolina Utilities Commission (hereinafter “the Public Staff”) filed a notice of intervention, and the Commission permitted various parties to intervene in the proceeding. Public hearings were held by the Commission in various areas of the state in June, July, and August 1984.

On 21 September 1984, the three-member Commission panel which heard the evidence issued an order which granted CP&L an increase in gross annual revenues of $64,339,000 from its North Carolina retail operations. However, due to the fact that two of the members of the panel dissented from different portions *241 of the order, the decision constituted only a recommended order pursuant to N.C.G.S. § 62-60.1(c). Subsequently, various parties requested a review by the full Commission.

Additional hearings were held before the full Commission in November 1984. On 20 November 1984, the Commission issued its final order which affirmed the $64,339,000 rate increase that had been recommended by the panel. The Attorney General appealed, and CP&L cross-appealed.

I.

Intervenor Attorney General argues that the Commission erred in calculating the amount of construction work in progress (hereinafter “CWIP”) which was to be included in CP&L’s rate base. CP&L requested the inclusion of $695,275,923 of CWIP in its rate base. This entire amount is attributable to Unit One of CP&L’s Shearon Harris Nuclear Power Plant and constituted an increase of approximately $155,500,000 above the CWIP which the Commission included in the company’s rate base in its 1983 general rate case, Docket No. E-2, Sub 461.

The Public Staff, however, contended that the amount of CWIP which had been included in CP&L’s rate base was $496,597,912. 1 The Public Staff recommended that the Commission continue to allow CP&L to include this amount of CWIP in its rate base.

In its recommended order, the hearing panel found that $692,604,000 of CWIP should be included in CP&L’s rate base. Subsequent to the issuance of the panel’s recommended order, this Court issued its opinion in Utilities Comm. v. Conservation Council, 312 N.C. 59, 320 S.E. 2d 679 (1984), which held that it was *242 error to include CWIP in the rate base to the extent that it was comprised of allowance for funds used during construction accrued subsequent to 1 July 1979 on construction work which occurred prior to 1 July 1979. Therefore, at the November hearings before the full Commission, CP&L adjusted the amount of CWIP which it was requesting to be included in the rate base so as to exclude the expenses held to be ineligible for rate base inclusion in the Conservation Council case. The adjusted request was $675,306,000. The Public Staff continued to adhere to its position that $496,597,912 was the proper amount of CWIP which should be included in CP&L’s rate base.

In its final order, the Commission found that $663,167,000 of CWIP should be included in CP&L’s rate base. The Commission stated that the inclusion of this amount of CWIP was in the public interest and was necessary to the financial stability of CP&L.

Before examining the Attorney General’s contentions, we deem it wise to take note of certain fundamental principles. The Commission, not the courts, has been given the authority to regulate the rates of public utilities. N.C.G.S. § 62-2 (1982 and Cum. Supp. 1985). The rates established by the Commission must, however, be fair to both the utility and the customer. N.C.G.S. § 62433(a) (1982 and Cum. Supp. 1985). Rates fixed by the Commission are deemed prima facie just and reasonable. N.C.G.S. § 62-94(e) (1982 and Cum. Supp. 1985). The party attacking the rates established by the Commission bears the burden of proving that they are improper. Utilities Comm. v. Duke Power Co., 305 N.C. 1, 287 S.E. 2d 786 (1982). The order of the Commission will not be disturbed if, upon consideration of the entire record, we find the decision is not affected by error of law and the facts found by the Commission are supported by competent, material, and substantial evidence, taking into account any contradictory evidence or evidence from which conflicting inferences could be drawn. Id. Naturally, an appellant may show on appeal that the order is not supported by competent, material, and substantial evidence. Id.; Utilities Comm. v. Edmisten, 291 N.C. 424, 230 S.E. 2d 647 (1976). The credibility of testimony and the weight to be accorded it are matters to be determined by the Commission. Utilities Comm. v. City of Durham, 282 N.C. 308, 193 S.E. 2d 95 (1972). However, a summary disposition which indicates that the *243 Commission accorded only. minimal consideration to competent evidence constitutes error at law and is correctable on appeal. Utilities Comm. v. Edmisten, 299 N.C. 432, 263 S.E. 2d 583 (1980).

N.C.G.S. § 62-133(b)(l) provides that, in fixing the rates for any public utility, the Commission must:

Ascertain the reasonable original cost of the public utility’s property used and useful, or to be used and useful within a reasonable time after the test period, in providing the service rendered to the public within the State, less that portion of the cost which has been consumed by previous use recovered by depreciation expense plus the reasonable original cost of investment in plant under construction (construction work in progress). In ascertaining the cost of the public utility’s property, construction work in progress as of the effective date of this subsection shall be excluded until such plant comes into service but reasonable and prudent expenditures for construction work in progress after the effective date of this subsection may be included, to the extent the Commission considers such inclusion in the public interest and necessary to the financial stability of the utility in question, subject to the provisions of subparagraph (b)(4a) of this section.

This provision clearly commits to the discretion of the Commission the determination of what amount of CWIP, if any, to include in the utility’s rate base.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Utilities Commission v. Carolina Water Service, Inc.
738 S.E.2d 187 (Court of Appeals of North Carolina, 2013)
State Ex Rel. Utilities Commission v. Carolina Utility Customers Ass'n
524 S.E.2d 10 (Supreme Court of North Carolina, 2000)
State Ex Rel. Utilities Commission v. Piedmont Natural Gas Co.
488 S.E.2d 591 (Supreme Court of North Carolina, 1997)
State ex rel. Utilities Commission v. Thornburg
385 S.E.2d 451 (Supreme Court of North Carolina, 1989)
STATE EX REL. UTIL. COM'N v. Thornburg
385 S.E.2d 463 (Supreme Court of North Carolina, 1989)
Campos v. Flaherty
377 S.E.2d 282 (Court of Appeals of North Carolina, 1989)
State Ex Rel. Utilities Commission v. North Carolina Natural Gas Corp.
375 S.E.2d 147 (Supreme Court of North Carolina, 1989)
State Ex Rel. Utilities Commission & Duke Power Co. v. Eddleman
358 S.E.2d 339 (Supreme Court of North Carolina, 1987)
State ex rel. Utilities Commission v. Carolina Power & Light Co.
358 S.E.2d 35 (Supreme Court of North Carolina, 1987)
State ex rel. Utilities Commission v. Thornburg
353 S.E.2d 413 (Court of Appeals of North Carolina, 1987)
STATE EX REL. UTILITIES COM'N v. Thornburg
353 S.E.2d 413 (Court of Appeals of North Carolina, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
342 S.E.2d 28, 316 N.C. 238, 1986 N.C. LEXIS 2062, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-utilities-commission-v-thornburg-nc-1986.