State Ex Rel. Utilities Commission v. Piedmont Natural Gas Co.

488 S.E.2d 591, 346 N.C. 558, 1997 N.C. LEXIS 487
CourtSupreme Court of North Carolina
DecidedJuly 24, 1997
Docket252PA96
StatusPublished
Cited by12 cases

This text of 488 S.E.2d 591 (State Ex Rel. Utilities Commission v. Piedmont Natural Gas Co.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Utilities Commission v. Piedmont Natural Gas Co., 488 S.E.2d 591, 346 N.C. 558, 1997 N.C. LEXIS 487 (N.C. 1997).

Opinion

WHICHARD, Justice.

This appeal involves competing applications filed by Frontier Utilities of North Carolina, Inc. (Frontier) and Piedmont Natural Gas Company, Inc. (Piedmont) to provide natural gas service to Surry, Wilkes, Watauga, and Yadkin Counties (Four-County area).

On 23 September 1994 Frontier, a newly formed local distribution company (LDC), filed an application for a certificate of public convenience and necessity to construct, own, and operate an intrastate pipeline facility and local distribution system and for establishment of rates for that system. Frontier requested authority to serve the Four-County area. On 27 September 1994 Piedmont also filed an *565 application seeking a certificate to serve the Four-County area or, in the alternative, a declaration that Piedmont’s existing certificates authorize it to construct the necessary facilities to extend natural gas service to the unserved counties. Frontier proposed to fund its project with traditional debt and equity financing. Piedmont’s application indicated that expansion of service into the Four-County area would be economically feasible only if Piedmont could use funds from an expansion fund. 1 Piedmont subsequently filed a petition requesting authority to use expansion funds for a project to serve the Four-County area.

By order dated 21 October 1994, the Commission consolidated the two applications for hearing, required public notice, and established intervention and filing deadlines. A public hearing was set for 1 December 1994 in Wilkesboro, with the hearing continuing in Raleigh on 31 January 1995. The Commission invited briefs on the question of whether Piedmont was entitled to extend natural gas service to the Four-County area under its existing certificates as territory contiguous to territory Piedmont already occupied. The Commission ultimately concluded that there was considerable “unoccupied” territory between those areas already serviced by Piedmont and the unserved Four-County area. The Commission therefore denied Piedmont’s alternative claim for authority to serve the Four-County area pursuant to the “contiguous” proviso of N.C.G.S. § 62-110(a).

Forty-eight persons testified as public witnesses at the hearing in Wilkesboro. During the second phase of the hearing in Raleigh, seven more public witnesses testified in addition to testimony presented by Piedmont, Frontier, and the Public Staff. At the conclusion of this hearing, the Commission ordered the Public Staff to file by 21 February 1995 supplemental testimony setting forth its recommendation. On 6 March 1995 Piedmont filed supplemental rebuttal testimony relating to Frontier’s inability to adequately service the Four-County area and relating to the desires of the citizens of the area. The hearing subsequently reconvened on 7 March 1995 to receive the supplemental testimony and recommendation of the Public Staff. Frontier objected to the majority of the supplemental evidence offered by Piedmont on the grounds that it was new, direct evidence. The Commission sustained the objection and limited presentation of *566 evidence to evidence intended to rebut the testimony of the Public Staff. Thereafter, the Public Staff recommended that Frontier be awarded a certificate, conditioned upon Frontier’s submitting ten specified studies, analyses, and other evidence, and that a further hearing be scheduled for the limited purpose of determining whether Frontier satisfied these conditions.

Contrary to the recommendation of the Public Staff, the Commission issued an order on 19 June 1995 giving Piedmont the option of accepting a certificate subject to the condition, inter alia, that Piedmont would not use any expansion funds for construction of the Four-County area project. The condition was based on the Commission’s conclusion that allowing the construction of a project using expansion fund financing when adequate service could be provided without resort to such nontraditional financing was inconsistent with the legislative intent expressed in N.C.G.S. § 62-158. By letter filed 10 July 1995, Piedmont declined to accept the conditional certificate, stating that it could not construct a safe, reliable, and economically viable transmission and distribution system in the Four-County area without the use of expansion funds.

On 20 July 1995 the Commission issued an order granting a conditional certificate to Frontier and scheduling a further hearing. The Commission required Frontier to complete and file ten specified items, including market and economic feasibility studies conducted by an independent consultant, information concerning system design, gas supply and capacity arrangements, construction contracts, and financing plans. A hearing limited to whether Frontier had met the conditions was scheduled to commence 12 December 1995. 2

Frontier timely filed testimony and exhibits in satisfaction of the ten conditions on 18 October 1995. On 7 November 1995 Piedmont filed a motion to dismiss the filing on the grounds that Frontier’s market study evaluated a proposal substantially different than Frontier’s original proposal. The Commission deferred ruling pending the 12 December hearing already scheduled. During November a number of towns, economic development groups, and individuals filed petitions to intervene. The Commission denied these petitions on the grounds *567 that they were untimely and would result in delay in the proceedings. The order provided, however, for additional public witness testimony, and any persons and groups who filed petitions to intervene were permitted to testify as public witnesses.

The second phase of the proceedings came on for hearing on 12 December 1995 as scheduled. The Commission issued a prehearing order stressing that the 12 December hearing would be limited to the issue of the adequacy of the information filed by Frontier in satisfaction of the ten conditions enumerated in the conditional certificate granted to Frontier. Nine public witnesses testified at the hearing. Frontier and the Public Staff presented the testimony of four and three witnesses, respectively. On 30 January 1996 the Commission issued an order awarding a final certificate to Frontier to provide natural gas service to the Four-County area.

On 28 February 1996 Piedmont requested a rehearing of the 30 January order and an opportunity for oral argument on this request. The Commission denied the request without hearing oral argument. On 15 March 1996 Piedmont filed its notice of appeal of the Commission orders that culminated in the 30 January order granting a final certificate to Frontier. The record on appeal was filed with the Court of Appeals on 28 May 1996. On 26 June 1996 this Court allowed petitions by Frontier, the Public Staff, and Piedmont for discretionary review prior to a determination by the Court of Appeals.

Piedmont first challenges two substantive aspects of the Commission’s findings of fact and resulting conclusions of law. Piedmont argues that the Commission erred by failing to consider the expressed preferences of the citizens of the Four-County area and by failing to adopt any findings of fact or conclusions of law with respect to this public sentiment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Utils. Comm'n v. Virginia Elec.
Supreme Court of North Carolina, 2022
In re: Stanly Solar
Court of Appeals of North Carolina, 2022
State ex rel. Utils. Comm'n v. Cooper, Att'y Gen.
767 S.E.2d 305 (Supreme Court of North Carolina, 2015)
STATE EX REL. UTIL. COM'N v. CAROLINA WATER
598 S.E.2d 179 (Court of Appeals of North Carolina, 2004)
State ex rel. Utilities Commission v. Buck Island, Inc.
592 S.E.2d 244 (Court of Appeals of North Carolina, 2004)
State ex rel. Utilities Commission v. NUI Corp.
572 S.E.2d 176 (Court of Appeals of North Carolina, 2002)
State Ex Rel. Utilities Commission v. Thrifty Call, Inc.
571 S.E.2d 622 (Court of Appeals of North Carolina, 2002)
State Ex Rel. Utilities Commission v. Carolina Utility Customers Ass'n
524 S.E.2d 10 (Supreme Court of North Carolina, 2000)
State Ex Rel. Utilities Commission v. North Carolina Gas Service
494 S.E.2d 621 (Court of Appeals of North Carolina, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
488 S.E.2d 591, 346 N.C. 558, 1997 N.C. LEXIS 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-utilities-commission-v-piedmont-natural-gas-co-nc-1997.