In re: Stanly Solar

CourtCourt of Appeals of North Carolina
DecidedMay 3, 2022
Docket21-188
StatusPublished

This text of In re: Stanly Solar (In re: Stanly Solar) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re: Stanly Solar, (N.C. Ct. App. 2022).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

2022-NCCOA-286

No. COA21-188

Filed 3 May 2022

North Carolina Utilities Commission, Nos. SP-9590, Sub 0; E-2, Sub 1159; E-7, Sub 1156

STATE OF NORTH CAROLINA EX REL. UTILITIES COMMISSION; DUKE ENERGY PROGRESS, LLC; DUKE ENERGY CAROLINAS, LLC; ACCION GROUP, LLC, Appellees,

v.

STANLY SOLAR, LLC, Appellant.

Appeal by Appellant from Order entered 20 October 2020 by the North

Carolina Utilities Commission. Heard in the Court of Appeals 30 November 2021.

The Allen Law Offices, by Dwight W. Allen, Britton H. Allen, and Brady W. Allen, and Jack Jirak, Deputy General Counsel Duke Energy Corporation, for Appellees Duke Energy Carolinas, LLC and Duke Energy Progress, LLC.

Burns, Day & Presnell, P.A., by James J. Mills and Daniel C. Higgins, for Appellee Accion Group, LLC.

Kilpatrick Townsend Stockton LLP, by Benjamin L. Snowden, for Appellant Stanly Solar, LLC.

GORE, Judge.

¶1 Stanly Solar, LLC (“Stanly Solar”) appeals from the Order Denying Motion for

Return of CPRE Proposal Security (“Order”) entered by the North Carolina Utilities

Commission (“Commission”). For the following reasons, we affirm the Commission’s

order. STATE EX REL. UTILS. COMM’N V. STANLY SOLAR, LLC

Opinion of the Court

I. Background

A. Competitive Procurement of Renewable Energy Program

¶2 On 27 July 2017, North Carolina Governor Roy Cooper signed into law North

Carolina Session Law 2017-192. Session Law 2017-192, in conjunction with the

Commission’s Rule R8-71 and the Commission’s Order Modifying and Approving

Joint CPRE Program allowed for the implementation of the Competitive Procurement

of Renewable Energy (“CPRE”) Program by Duke Energy Carolinas, LLC (“DEC”)

and Duke Energy Progress, LLC (“DEP” and, together with DEC, the “Companies”).

¶3 The CPRE Program was to be implemented in multiple tranches. As part of

Tranche 1 the Companies issued a Request for Proposals (“RFP”) for electric

generating facilities, subject to a set criterion, from eligible market participants

(“MPs”) in 2018. MPs for this RFP included third-party renewable developers, the

DEC/DEP Proposal Team, and any affiliate of DEC or DEP that elects to submit a

proposal. Proposals were due 11 September 2018.

¶4 The RFP was administered by an Independent Administrator, the Accion

Group, LLC (“Accion”). Accion was responsible for developing and utilizing the CPRE

Program Methodology to evaluate all Proposals in accordance with the evaluation

process established under Commission Rule R8-71(f)(3)(iii) and ensuring that all

Proposals are treated equitably throughout the RFP. STATE EX REL. UTILS. COMM’N V. STANLY SOLAR, LLC

¶5 Accion hosted a website (“IA RFP Website”) as a base for all RFP

communications. Among other things, the IA RFP Website was available to all MPs

to provide comments on the RFP process, submit questions concerning the RFP

(questions and responses were available to be viewed by all registered persons on the

IA RFP Website), and provided a confidential message board to allow MPs to ask

project specific questions to Accion without those questions being disclosed to all MPs.

¶6 Proposals to the Tranche 1 RFP were due by 11 September 2018. The

evaluation process was to be split into two Steps. The full evaluation process of

proposals and notification of winning bids was projected to be completed by 25

February 2019, with the contracting period to be completed by 24 April 2019.

¶7 If, at the conclusion of Step 1 of the evaluation process, a third-party MP was

notified by Accion that their Proposal was selected to move on to Step two of the

evaluation process, that MP would be required to post a Proposal Security in the

amount of $20/kW, based on the proposed facility’s inverter nameplate capacity. The

Proposal Security would only be released (i) if the Proposal is eliminated by Accion

due to failure to meet any required RFP criteria or action; (ii) if the MP elects to

withdraw the Proposal pursuant to Section VI(A) of the RFP; (iii) if the Proposal is

not selected as a winning proposal, upon closure of the RFP; or (iv) if the Proposal is

selected as a winning Proposal, upon completion of the contracting phase of the RFP,

including execution of the applicable contract and posting of security as required in STATE EX REL. UTILS. COMM’N V. STANLY SOLAR, LLC

the applicable agreement. The Companies will be entitled to draw on the full amount

of the Proposal Security if the MP (a) withdraws its Proposal during Step 2 of the

evaluation process; or (b) if the Proposal is selected as a winning Proposal but the MP

fails to complete the contracting phase.

¶8 Accion evaluated the Proposals in accordance with Commission Rule R8-

71(f)(3). Commission Rule R8-71(f)(3) required Accion to perform an initial ranking

of Proposals based on economic and noneconomic criteria in evaluation Step 1.

Noneconomic criteria considered included facility permitting, financing experience,

technical development and operational experience, and historically underutilized

businesses. Step 2 of the evaluation process required the T&D Sub-Team to assess

the system impact of the Proposals and assign any System Upgrade costs to each

Proposal.

¶9 If during the Step 2 evaluation process the T&D Sub-Team determined that

any required Interconnection Facilities or System Upgrades could not be completed

by 1 January 2021, but could be completed by 1 July 2021, the IA was to notify the

MP of the projected completion date of the Interconnection Facilities and System

Upgrades, then the MP would have the option to either elect to allow the Proposal to

remain in the RFP or withdraw the Proposal. However, if it was determined that any

required Interconnection Facilities or System Upgrades could not be completed by 1

July 2021, the IA would remove the Proposal from further consideration. STATE EX REL. UTILS. COMM’N V. STANLY SOLAR, LLC

B. Stanly Solar’s Bid

¶ 10 Stanly Solar is a 50 MW solar project under development in Stanly County,

North Carolina. Stanly Solar had received a system impact study in December 2017

and was designated as a “Late-Stage Proposal,” meaning that it was not included in

the Tranche 1 “grouping study” and would solely bear the costs of its own network

upgrades.

¶ 11 Stanly Solar submitted a third-party PPA bid into the CPRE. On 6 December

2018, Stanly Solar was notified that it had been selected in Step 1. At that time, it

appeared that the project likely would not be able to achieve interconnection by the 1

January 2021 in-service deadline. However, Stanly Solar opted to proceed to Step 2

and posted a $1 million surety bond as Proposal Security on 4 January 2019. Stanly

Solar’s initial surety bond was rejected for failure to comply with the proper form.

Stanly Solar posted a revised surety bond on 5 February 2019, which was accepted.

On 10 April 2019, Stanly Solar was notified that it had been selected as a winning

bid and would have to sign a PPA or withdraw from the CPRE and forfeit its Proposal

Security.

¶ 12 On 7 June 2019, Stanly Solar received a Facilities Study Report which

indicated that it would take approximately two years from the start of construction

to achieve interconnection. At a construction planning meeting on 21 June 2019,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Utilities Commission v. Champion Papers, Inc.
130 S.E.2d 890 (Supreme Court of North Carolina, 1963)
State Ex Rel. Utilities Commission v. Piedmont Natural Gas Co.
488 S.E.2d 591 (Supreme Court of North Carolina, 1997)
State Ex Rel. Utilities Commission v. Conservation Council
320 S.E.2d 679 (Supreme Court of North Carolina, 1984)
State Ex Rel. Utilities Commission v. Ray
73 S.E.2d 870 (Supreme Court of North Carolina, 1953)
State ex rel. Utilities Commission v. Carolina Water Service, Inc.
738 S.E.2d 187 (Court of Appeals of North Carolina, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
In re: Stanly Solar, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-stanly-solar-ncctapp-2022.