State Ex Rel. Utilities Commission v. Conservation Council

320 S.E.2d 679, 312 N.C. 59, 1984 N.C. LEXIS 1777
Supreme Court of North Carolina·Decided October 2, 1984·No. 126A84·Published·Cited by 28 cases

Opinion

COPELAND, Justice.

I.

Appellants argue that the Commission erred in including the sum of $144,841,000 in Duke’s retail rate base for construction work in progress (hereinafter CWIP) because its findings on this matter were inadequate as a matter of law. Appellants base their argument on both G.S. § 62-79(a) and G.S. § 62-133(b)(l) (1977) (amended 1981). Each statute will be considered separately.

G.S. § 62-79(a) provides that:

All final orders and decisions of the Commission shall be sufficient in detail to enable the court on appeal to determine the controverted questions presented in the proceedings and shall include:
(1) Findings and conclusions and the reasons or bases therefor upon all the material issues of fact, law, or discretion presented in the record, and
(2) The appropriate rule, order, sanction, relief or statement of denial thereof.

The appellants contend that the final order of the Commission falls short of this standard because its finding of Fact *62 Number 7 is simply a recitation of the factors in G.S. § 62-133 (b)(1). 1 We disagree.

The purpose of the findings required by G.S. § 62-79(a) is to provide the reviewing court with sufficient information to allow it to determine the controverted questions presented in the proceedings. In the section of its order entitled “Evidence and Conclusions for Finding of Fact No. 7” the Commission summarized and rejected the statutory interpretation arguments made by the appellants. The Commission then concluded that all of Duke’s CWIP expenditures, in particular those for the Cherokee plant and allowance for funds used during construction accrued after 1 July 1979, were reasonable and prudent expenditures under G.S. § 62-133(b)(l). The Commission further concluded that the expenditures were needed to insure adequate service to Duke’s customers in the future. The Court of Appeals properly noted that such scant findings and conclusions barely pass muster. State ex rel. Utilities Commission v. Conservation Council, 64 N.C. App. at 273, 307 S.E. 2d at 379. We do not approve the practice of using such sparse evidence and conclusions to support the Commission’s findings of fact, but we hold that they were adequate to meet the requirements of G.S. § 62-79(a). The Commission’s summary of the appellant’s argument and its rejection of the same is sufficient to enable the reviewing court to ascertain the controverted questions presented in the proceeding. That is all that G.S. § 62-79(a) requires.

A somewhat more difficult issue is posed by appellants’ contention that G.S. § 62-133(b)(l) first requires the Commission to make findings on the reasonableness and prudence of including CWIP expenses in the rate base before it considers the reasonableness of the CWIP costs incurred. G.S. § 62-133(b)(l) as it read at the relevant time provides that the Commission shall:

Ascertain the reasonable original cost of the public utility’s property used and useful, or to be used and useful within a *63 reasonable time after the test period, in providing the service rendered to the public within this State .... In ascertaining the cost of the public utility’s property, construction work in progress as of the effective date of this subsection shall be excluded until such plant comes into service but reasonable and prudent expenditures for construction work in progress after the effective date of this subsection shall be included subject to the provisions of subparagraph (b)(5) 2 of this section.

Appellants argue that before the Commission may include CWIP expenses in the rate base it must first find that the plant under construction is necessary and will be completed in a reasonable time.

We hold that G.S. § 62-133(b)(l) does not require the Commission to make new findings on the need for the construction. Before any public utility begins the construction of a facility for generating electricity for use by the public it must first obtain from the Commission a certificate stating that “public convenience and necessity requires, or will require such construction.” G.S. § 62-110.1(a). Before such a certificate can be granted the applicant must file an estimate of construction costs and the Commission must hold public hearings. G.S. § 62-110.1(e). This procedure satisfies appellant’s argument that the construction must be necessary.

The wording used by the legislature makes it clear that the Commission must include all reasonable CWIP expenditures in the rate base. The only matter left to the discretion of the Commission is whether such expenditures are reasonable and prudent. Evidence of whether the plant under construction will be completed within a reasonable time is pertinent to deciding if expenditures for such construction are reasonable and prudent. While it is the better practice for the Commission to specifically find that the construction will be completed within a reasonable time, the statute does not require it so long as there is evidence in the record that the plant would be completed within a reasonable *64 time. There was sufficient evidence in the record to allow the Commission to conclude that the Cherokee units would be completed within a reasonable time. We are not persuaded by the appellants’ argument that the Commission must make findings as to the cost of each project and when it will be needed. Nowhere in G.S. § 62-133(b)(l) is there such a requirement. To require such extensive evidence would put an undue burden on Duke and cause the ratemaking process to be more time consuming and difficult of administration.

Costs are presumed to be reasonable unless challenged. Utilities Commission v. Intervenor Residents, 305 N.C. 62, 76-77, 286 S.E. 2d 770, 779 (1982), and there was no challenge to the reasonableness of the prices paid by Duke. Further, the Commission found that Duke’s construction expenditures were reasonably incurred and were needed to provide adequate electric service to its customers. The Commission’s findings on this point are supported by competent, material, and substantial evidence and are conclusive on appeal. Utilities Commission v. Intervenor Residents, 305 N.C. at 77, 286 S.E. 2d at 779.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

State Ex Rel. Utilities Commission v. Conservation Council, 320 S.E.2d 679, 312 N.C. 59, 1984 N.C. LEXIS 1777 (N.C. 1984).

320 S.E.2d 679 (State Ex Rel. Utilities Commission v. Conservation Council) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re: Blue Heron Asset Mgmt., LLC
Court of Appeals of North Carolina, 2026
In re: Duke Energy Carolinas, LLC
Court of Appeals of North Carolina, 2026
State ex rel. Utils. Comm'n v. Virginia Elec.
Supreme Court of North Carolina, 2022
In re: Stanly Solar
Court of Appeals of North Carolina, 2022
State ex rel. Utils. Comm'n v. Stein
Supreme Court of North Carolina, 2020
In Re Island Hi-Speed Ferry, LLC.
852 A.2d 524 (Supreme Court of Rhode Island, 2004)
State Ex Rel. Utilities Commission v. Carolina Utility Customers Ass'n Inc.
500 S.E.2d 693 (Supreme Court of North Carolina, 1998)
Kansas Pipeline Partnership v. Kansas Corporation Comm'n
941 P.2d 390 (Court of Appeals of Kansas, 1997)
State ex rel. Utilities Commission v. Carolina Utility Customers Ass'n
446 S.E.2d 348 (Supreme Court of North Carolina, 1994)
Dennis v. Duke Power Co.
442 S.E.2d 104 (Court of Appeals of North Carolina, 1994)
Alsup v. Pitman
390 S.E.2d 750 (Court of Appeals of North Carolina, 1990)
State Ex Rel. Utilities Commission & Duke Power Co. v. Eddleman
358 S.E.2d 339 (Supreme Court of North Carolina, 1987)
State Ex Rel. Utilities Commission v. Public Staff
343 S.E.2d 898 (Supreme Court of North Carolina, 1986)
State Ex Rel. Utilities Commission v. MacKie
338 S.E.2d 888 (Court of Appeals of North Carolina, 1986)
State ex rel. Utilities Commission v. Thornburg
334 S.E.2d 772 (Supreme Court of North Carolina, 1985)
STATE EX REL. UTILITIES COM'N v. Thornburg
334 S.E.2d 772 (Supreme Court of North Carolina, 1985)
State Ex Rel. Utilities Commission v. North Carolina Textile Manufacturers Ass'n
328 S.E.2d 264 (Supreme Court of North Carolina, 1985)