State Ex Rel. State Highway Commission v. City of Sullivan

520 S.W.2d 186, 1975 Mo. App. LEXIS 1595
CourtMissouri Court of Appeals
DecidedFebruary 4, 1975
Docket35914
StatusPublished
Cited by15 cases

This text of 520 S.W.2d 186 (State Ex Rel. State Highway Commission v. City of Sullivan) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. State Highway Commission v. City of Sullivan, 520 S.W.2d 186, 1975 Mo. App. LEXIS 1595 (Mo. Ct. App. 1975).

Opinions

GUNN, Judge.

Plaintiff, State Highway Commission, appeals from a jury verdict and judgment in favor of defendant, City of Sullivan, in a suit for recovery of costs for the alteration and relocation of a utility pipeline within the corporate limits of the City. The sole issue we consider on appeal is whether the trial court erred in excluding two documents from evidence: 1) a utility agreement executed by the Highway Commission and the City’s mayor; 2) a City journal minute entry allegedly referring to the utility agreement. We find no error in the trial court’s rulings and affirm the judgment.

In the construction of Interstate Highway 44 through the City of Sullivan, existing sewer utility pipelines were required to be relocated. Procedures normally followed by the Highway Commission in highway construction through a municipality provided that the municipality involved could itself arrange for the necessary relocation of municipal owned pipelines and other municipal owned utilities along the highway construction, or the municipality could participate in the overall Highway Commission construction contract with the municipality paying its share of the cost of relocating its own facilities.

On October 3, 1967, the Highway Commission wrote to Mayor George Hayes of the City of Sullivan advising him that the estimated total cost of relocating the sewer pipelines within the City would be $17,764.t 12 with the City to bear 55% of the total cost, or $9,770.27 according to preliminary estimates. The Highway Commission would bear the other 45% of the relocation costs, as 45% of the sewer pipeline relocation was the Highway Commission’s responsibility. On November 21, 1967 the Highway Commission again wrote Mayor Hayes and requested “a firm yes or no from the City” about the City’s inclusion in the Highway Commission’s roadway construction contract and the City’s participation in 55% of the cost of sewer pipeline relocation. On January 23, 1968, the City’s Board of Aldermen adopted Ordinance No. 1062, reading as follows:

“BILL NO. 1062
ORDINANCE NO. 1062
AN ORDINANCE AUTHORIZING AND DIRECTING THE CITY OF SULLIVAN TO ENTER INTO A CONTRACT WITH THE STATE HIGHWAY COMMISSION OF MISSOURI CONCERNING ROUTE 1-44 Crawford County (Route WW to Franklin County) (Crawford Co. to Route 185 S) Projects No. 1-44 — 3 (18) & (20) [188]*188AND PRESCRIBING THE EFFECTIVE DATE OF SAID ORDINANCE.
BE IT ORDAINED BY THE BOARD OF ALDERMEN OF THE CITY OF SULLIVAN AS FOLLOWS:
SECTION 1. The Mayor -of the City of Sullivan and City Clerk of said City are authorized to execute a contract as pertains in the caption of this ordinance with the State of Missouri Highway Commission.
SECTION 2. This ordinance shall be in full force and effect from and after the day of its passage by the Board and approval by the Mayor.
PASSED BY THE BOARD AND APPROVED BY THE MAYOR THIS 23rd DAY OF JANUARY, 1968.”

Also on January 23, 1968, Mayor Hayes executed an urban agreement pertaining to construction of the Interstate Highway 44 improvement which was also executed by the Highway Commission, with the contract specifically reciting that “the City executes same (the contract) pursuant to Ordinance No. 1062 of said City, approved on the 23rd Day of Jan., 1968.” The January 23 contract contained no provisions for the payment of costs of alteration or relocation of any facilities but related primarily to the City’s obligations during the highway construction to grant necessary rights of way, construction easements and provide for traffic and advertising controls in accord with State regulations. The City in accord with the letters of October 3 and November 21, 1967 then deposited the sum of $9,770.20 with the Highway Commission as its 55% share of the estimated total cost of the relocation project, the total cost estimate being $17,764.12.

In June 1969, in accordance with the lowest and best bid procedures of § 227.100 RSMo 1969, V.A.M.S., the Highway Commission entered into a roadway construction contract with Boyd Construction Company for all of the roadway construction work through the City, including the relocation of the sewer pipeline facilities. The sewer pipeline work was completed on April 15, 1971, and it was then determined that the total actual cost of such work was $33,545.17, not $17,764.12 as originally estimated; that, therefore, according to the Highway Commission’s calculations, 55% of the total actual cost would be $18,449.84, or $8,679.57 more than the $9,770.27 already paid by the City as its estimated share of the actual cost.

Demand was made by the Highway Commission upon the City for the payment of the additional $8,670.57, but the City refused to make payment on the grounds that it had not agreed to pay the additional sum and that it had never been notified that its costs would vary from the $9,770.-27 it had deposited; that the City, had it known that the work would have exceeded the original estimate, could have contracted to have had the sewer pipeline relocation project completed at a substantially lower cost than that charged by the Highway Commission.

The Highway Commission filed suit in five counts to recover the $8,670.57: 1) on contract; 2) under § 227.240 RSMo 1969, which provides that the costs and expenses of the relocation and removal of pipelines be recovered from the owners of such pipelines; 3) quantum meruit; 4) and 5) representations of warranty made by May- or Hayes that he had authority to contract with the Highway Commission for the full actual costs of the pipeline relocation. One of the counts against Mayor Hayes for representation of warranty was dismissed by the trial court. The jury returned a verdict in favor of the City on all other counts.

The only point which the Highway Commission has preserved for review on appeal is concerned with the contract issue. The Highway Commission alleges that it had a firm contract with the City for the payment of 55% of the actual cost of the relocation of the pipeline. The City contends that if any such contract had been executed by any City official, such execution was [189]*189without authority, and the contract was therefore void.

At trial the Highway Commission, in an effort to demonstrate the contractual obligations of the City, attempted to introduce a so-called “utility agreement” executed by Mayor Hayes on July 11, 1968. The critical portion of the utility agreement provided :

“(5) The total cost of the work to be performed by Commission in its roadway contract for the alteration of City’s sanitary sewer facilities that exist from approximately 340 feet left of centerline Station 26+13 to approximately 240 feet right of centerline Station 25+40 is now estimated to be $17,764.12. City is obligated for 55.0 percent of the total cost of the work, with City’s portion now estimated to be $9,770.27. City, upon notice by Commission approximately 30 days prior to the receipt of bids for this project, will immediately deposit with Commission a check to cover City’s obligation which will include 10 percent for engineering, supervision and contingencies. Upon the completion of the work, City’s final obligation to Commission based upon final measurements of facilities constructed at the unit contract prices plus 10 percent for engineering, supervision and contingencies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Dardenne Prairie v. Adams Concrete & Masonry, LLC
529 S.W.3d 12 (Missouri Court of Appeals, 2017)
Moynihan v. City of Manchester
265 S.W.3d 350 (Missouri Court of Appeals, 2008)
Langlois v. Pemiscot Memorial Hospital
185 S.W.3d 711 (Missouri Court of Appeals, 2006)
Coleman v. Director of Revenue
970 S.W.2d 394 (Missouri Court of Appeals, 1998)
Kennedy v. City of St. Louis
749 S.W.2d 427 (Missouri Court of Appeals, 1988)
Shadowood Development Co. v. City of Lake St. Louis
668 S.W.2d 647 (Missouri Court of Appeals, 1984)
O'Laughlin v. Barstow
654 S.W.2d 95 (Missouri Court of Appeals, 1983)
United Cooperatives, Inc. v. City of Smithville
630 S.W.2d 255 (Missouri Court of Appeals, 1982)
Phillips Pipe Line Co. v. Ashley
605 S.W.2d 514 (Missouri Court of Appeals, 1980)
Allen v. City of Fredericktown
591 S.W.2d 723 (Missouri Court of Appeals, 1979)
Walker v. Multi-Wood Products, Inc.
581 S.W.2d 617 (Missouri Court of Appeals, 1979)
State v. Laws
547 S.W.2d 162 (Missouri Court of Appeals, 1977)
Glastris v. Union Electric Co.
542 S.W.2d 65 (Missouri Court of Appeals, 1976)
Schmid v. Langenberg
526 S.W.2d 940 (Missouri Court of Appeals, 1975)
State Ex Rel. State Highway Commission v. City of Sullivan
520 S.W.2d 186 (Missouri Court of Appeals, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
520 S.W.2d 186, 1975 Mo. App. LEXIS 1595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-state-highway-commission-v-city-of-sullivan-moctapp-1975.