Allen v. City of Fredericktown

591 S.W.2d 723, 1979 Mo. App. LEXIS 2613
Missouri Court of Appeals·Decided October 30, 1979·No. No. 40651·Published·Cited by 5 cases

Opinion

GUNN, Presiding Judge.

Appellants brought suit against respondent City of Fredericktown to recover the cost of the installation of water and sewer lines within a subdivision development. Appellants grounded their action on a municipal ordinance providing for reimbursement by the City, under certain conditions, of the cost of, construction of water and sewer lines placed in subdivisions by developers. The City defended the action for a variety of reasons, among which were: that there had been a repeal of the reimbursement ordinance; that no written contract existed upon which to base their liability; and that the five year statute of limitations of § 516.120(2), RSMo 1978, barred appellants’ claim. In inditing detailed findings of fact and conclusions of law, the trial court ruled in the City’s favor. We affirm on the ground that there was no written contract.

Appellants are developers in Frederick-town. In the course of developing certain [724] additions and subdivisions they incurred costs in the installation of water and sewer lines. Recoupment of such costs was sought and obtained from the City until May 27,1968 under Fredericktown’s municipal Ordinance No. 202 which provided for the reimbursement by the City to developers for sewer and water line installation costs. Both parties agree that there is no controversy regarding expenses incurred prior to May 27, 1968.1 Ordinance No. 68— 10, enacted May 27, 1968 has spawned the litigation now before us. Ordinance No. 68-10 required a subdivider seeking to develop land within the City to submit and obtain approval of development plans by the Board of Aldermen. Following approval of the preliminary plans the subdivider was required, among other things, to furnish a bond or provide for an assessment to guarantee the cost of such improvements, including water and sewer lines. Some of the provisions of Ordinance No. 68 — 10 were as follows:

No final or official plat of any subdivision shall be approved unless: (a) the subdivider agrees with the Board of Aldermen upon an assessment whereby the city is put in an assured position to install the improvements listed below at the cost of the owners of property within the subdivision, or (b) the improvements listed below have been installed prior to such approval, or (c) the subdivider filed with the Board of Aldermen a surety bond, cashier’s check, or a certified check upon a solvent bank located ' in the City of Fredericktown conditioned to secure the construction of the improvements listed below in a satisfactory manner and within a period specified by the Board of Aldermen, such period not to exceed two years. No such bond or check shall be accepted unless it be enforceable by or payable to the city in a sum at least equal to the cost of constructing the improvements- as estimated by the City Engineer and in form with surety and conditions approved by the City Attorney.

Appellants were reimbursed by the City under Ordinance No. 2022 for subdivision water and sewer line improvement costs incurred prior to the adoption of Ordinance No. 68-10. Subsequent to the passage of this latter ordinance, there has been no reimbursement to appellants of the $16,-568.36 expended by them for water and sewer line improvements in subdivision development. It is this sum which forms the seedbed of controversy between the parties and for which appellants seek recovery.

The trial court in its well written findings of fact, conclusions of law and judgment found, among other reasons, that appellants’ claim for recovery was deficient as they had failed to obtain the requisite Ordinance No. 68-10 final approval of their development plans or by failure to fulfill conditions of preliminary plans which had been given conditional approval. The .trial court found that appellants were not entitled to any recovery for any costs expended subsequent to May 27, 1968. Appellants recognize that there has been a failure of compliance in certain aspects with Ordinance Nos. 202 and 68-10 but have based their claim on an alleged contractual obligation by the City to reimburse them for their expenses. However, the trial court concluded, inter alia, that there was no written contract between the parties; that without a written contract appellants have no right of recovery under § 432.070, RSMo 1978, which specifically provides:

No . . city . . . shall make any contract, unless the same shall be within the scope of its powers or be expressly authorized by law . . . ; and such contract, including the consideration, shall be in writing and dated when made, and shall be subscribed by the parties thereto, or their agents authorized by law and duly appointed and authorized in writing.

Free access — add to your briefcase to read the full text and ask questions with AI

Allen v. City of Fredericktown, 591 S.W.2d 723, 1979 Mo. App. LEXIS 2613 (Mo. Ct. App. 1979).

591 S.W.2d 723 (Allen v. City of Fredericktown) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Howard Cnty. Ambulance Dist. v. City of Fayette
549 S.W.3d 1 (Missouri Court of Appeals, 2018)
Gill Construction, Inc. v. 18th & Vine Authority
157 S.W.3d 699 (Missouri Court of Appeals, 2005)
Pace v. Land Clearance for Redevelopment Authority of Kansas City
713 S.W.2d 34 (Missouri Court of Appeals, 1986)
City of Warrensburg v. RCA Corp.
550 F. Supp. 1364 (W.D. Missouri, 1982)