State Ex Rel. Office of the Public Counsel & Missouri Industrial Energy Consumers v. Missouri Public Service Commission

331 S.W.3d 677, 2011 Mo. App. LEXIS 84
CourtMissouri Court of Appeals
DecidedFebruary 1, 2011
DocketWD 72498, WD 72508
StatusPublished
Cited by11 cases

This text of 331 S.W.3d 677 (State Ex Rel. Office of the Public Counsel & Missouri Industrial Energy Consumers v. Missouri Public Service Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Office of the Public Counsel & Missouri Industrial Energy Consumers v. Missouri Public Service Commission, 331 S.W.3d 677, 2011 Mo. App. LEXIS 84 (Mo. Ct. App. 2011).

Opinion

MARK D. PFEIFFER, Presiding Judge.

Appellants, Office of Public Counsel 1 (“OPC”) and Missouri Industrial Energy Consumers 2 (“MIEC”) appeal from the judgment of the Circuit Court of Cole County affirming the Public Service Commission (“PSC”) Order promulgating 4 CSR 240-3.162 and 4 CSR 240-20.091 (the “Regulations”) as lawful and reasonable. OPC and MIEC raise four points of error on appeal. They argue: (1) the PSC failed to timely adopt the Regulations pursuant to section 386.266.9; 3 (2) the Regulations allow electric utilities to earn more than a fair rate of return on equity for each periodic rate adjustment, thereby violating section 386.266.4(1); (3) the Regulations are contrary to the true-up mechanism required, in section 386.266.4(2); and (4) *681 the cap on annual adjustments in the Regulations conflicts with section 386.266.2. We disagree and affirm.

Factual and Procedural Background

The PSC is the state agency responsible for regulation of public utilities operating in the State of Missouri. § 386.040. The PSC has jurisdiction over the manufacture, sale, and distribution of electricity. § 386.250(1); see also § 393.140. The PSC is authorized to approve rate schedules for electrical corporations, typically during a general rate case, as long as the rate is just and reasonable both to the utility and to its customers. § 393.150. Only after providing reasonable notice to interested persons, a full hearing on the matter, and consideration of all relevant factors, including operating expenses, depreciation of plant, taxes, and the utilities’ approved rate of return on equity, may the PSC approve the new rate. Id.

During the 2005 legislative session, the Missouri legislature passed Senate Bill 179, later codified at section 386.266. Section 386.266 authorizes the PSC to establish an environmental cost recovery mechanism (“ECRM”) 4 to reflect increases and decreases in a utility’s prudently incurred costs to comply with any federal, state, or local environmental law, regulation, or rule. Pursuant to section 386.266, the PSC drafted two proposed rules, 4 CSR 240-20.091 and 4 CSR 240-3.162. 4 CSR 240-20.091 provides for the establishment of an ECRM in an electric utility’s rate schedule which allows periodic rate adjustments to reflect net increases or decreases in a utility’s prudently incurred costs directly related to compliance with any federal, state, or local environmental law, regulation, or rule. 5 4 CSR 240-3.162 implements section 386.266 by providing electric utility ECRM filing and submission requirements.

On December 17, 2008, the PSC initiated the rulemaking proceeding to consider the adoption of the rules. The notice of proposed rulemaking was transmitted to the Secretary of State on January 2, 2009, and published in the Missouri Register on February 3, 2009. After the public comment time period ended on March 4, 2009, a public hearing was held on that same day. A second comment period ended on April 15, 2009, followed by another hearing. Among the participants who commented at the hearings were the OPC, MIEC, Union Electric Company (“Amer-enUE”), and the PSC Staff (“Staff’). While OPC and MIEC opposed the proposed rules, AmerenUE and Staff supported them. Proposals to change the language and operation of the rules were made by both supporters and opponents of the rules; however, no significant changes were made.

The PSC transmitted orders of rulemak-ing to the Secretary of State on April 23, 2009. On May 22, 2009, OPC filed its *682 Application for Rehearing of the two orders of rulemaking for the proposed rules. The PSC transmitted the final orders of rulemaking to the Secretary of State on May 26, 2009, and denied OPC’s application for rehearing on June 10, 2009. The rules were published in the Missouri Register on July 1, 2009, as 4 CSR 240-20.091 and 4 CSR 240-3.162 and became effective on August 30, 2009.

OPC filed a timely petition for writ of review in the Circuit Court of Cole County (“circuit court”). MIEC and AmerenUE both filed motions to intervene which were sustained by the circuit court. On March 31, 2010, the circuit court affirmed the final orders of rulemaking, holding that the Regulations were lawful and reasonable. OPC and MIEC filed separate notices of appeal, which were consolidated by this court. 6

Standard of Review

When a party appeals from an order of the PSC, we review the PSC’s findings and decision and not the circuit court’s judgment. State ex rel. Mo. Gas Energy v. Pub. Serv. Comm’n, 186 S.W.3d 376, 381 (Mo.App. W.D.2005). Our review of the PSC’s order is two-fold: first, we must determine “whether the [PSC’s] order is lawful, and second, whether the order is reasonable[.]” Id. Additionally, the party seeking to set aside the PSC’s order has the burden to prove by clear and satisfactory evidence that the order was unlawful or unreasonable. E.g., § 386.430; State ex rel. Util. Consumers’ Council of Mo., Inc. v. Pub. Serv. Comm’n, 585 S.W.2d 41, 47 (Mo. banc 1979); State ex rel. BPS Tel. Co. v. Mo. Pub. Serv. Comm’n, 285 S.W.3d 395, 401-02 (Mo.App. W.D.2009).

Lawfulness is determined by whether or not the PSC had the statutory authority to act as it did. Mo. Gas Energy, 186 S.W.3d at 382. When determining whether the order is lawful, we exercise independent judgment and must correct erroneous interpretations of the law. Burlington N. R.R. v. Dir. of Revenue, 785 S.W.2d 272, 273 (Mo. banc 1990). Because the PSC “is purely a creature of statute, [its] powers are limited to those conferred by [statute] either expressly, or by clear implication as necessary to carry out the powers specifically granted.” Util. Consumers’ Council of Mo., 585 S.W.2d at 49. While section 386.266 should be liberally construed in order to effectuate its purpose, “ ‘neither convenience, expediency or necessity are proper matters for consideration in the determination of whether or not an act of the [PSC] is authorized by the statute.” Id. (quoting State ex rel. Kansas City v. Pub. Serv. Comm’n, 301 Mo. 179, 257 S.W. 462 (Mo. banc 1923)).

However, “[o]nce it is determined that an act is within the [PSC’s] authority ... these considerations and others become part of the broad discretion accorded the [PSC] to set just and reasonable rates.” Id. The reasonableness of the order setting new rates is dependent upon whether or not “(i) the order is supported *683

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kan. City Power & Light Co. v. Mo. Pub. Serv. Comm'n
557 S.W.3d 460 (Missouri Court of Appeals, 2018)
Public Service Commission v. Office of Public Counsel
417 S.W.3d 815 (Missouri Court of Appeals, 2014)
State ex rel. Union Electric Co. v. Public Service Commission
399 S.W.3d 467 (Missouri Court of Appeals, 2013)
AG Processing Inc. v. Missouri Public Service Commission
408 S.W.3d 175 (Missouri Court of Appeals, 2013)
State ex rel. Public Counsel v. Public Service Commission
397 S.W.3d 441 (Missouri Court of Appeals, 2013)
State Ex Rel. Noranda Aluminium, Inc. v. Public Service Com'n of State
356 S.W.3d 293 (Missouri Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
331 S.W.3d 677, 2011 Mo. App. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-office-of-the-public-counsel-missouri-industrial-energy-moctapp-2011.