In The Matter of The Application of Laclede Gas Company D/B/A Missouri Gas Energy, For Approval to Change its Infrastructure System Replacement Surcharge Public Service Commission of The State of Missouri v. The Office of Public Counsel

CourtMissouri Court of Appeals
DecidedJanuary 14, 2014
DocketWD76509
StatusPublished

This text of In The Matter of The Application of Laclede Gas Company D/B/A Missouri Gas Energy, For Approval to Change its Infrastructure System Replacement Surcharge Public Service Commission of The State of Missouri v. The Office of Public Counsel (In The Matter of The Application of Laclede Gas Company D/B/A Missouri Gas Energy, For Approval to Change its Infrastructure System Replacement Surcharge Public Service Commission of The State of Missouri v. The Office of Public Counsel) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In The Matter of The Application of Laclede Gas Company D/B/A Missouri Gas Energy, For Approval to Change its Infrastructure System Replacement Surcharge Public Service Commission of The State of Missouri v. The Office of Public Counsel, (Mo. Ct. App. 2014).

Opinion

In the Missouri Court of Appeals Western District

 IN THE MATTER OF THE  APPLICATION OF LACLEDE GAS  WD76509 COMPANY D/B/A MISSOURI GAS ENERGY, FOR APPROVAL TO  OPINION FILED: CHANGE ITS INFRASTRUCTURE  SYSTEM REPLACEMENT  January 14, 2014 SURCHARGE;   Respondent,   PUBLIC SERVICE COMMISSION OF  THE STATE OF MISSOURI,   Respondent,   v.    THE OFFICE OF PUBLIC COUNSEL,  Appellant.  

APPEAL FROM THE PUBLIC SERVICE COMMISSION

Before Division Four: James Edward Welsh, C.J., Cynthia L. Martin, J., and Patrick Robb, Sp. J.

The Office of Public Counsel appeals the Missouri Public Service Commission's order

approving the petition of Laclede Gas Company ("Laclede") to change its "Infrastructure System

Replacement Surcharge" ("ISRS"). The Office of Public Counsel contends that the

Commission's order was unlawful because it approved an increase in the ISRS more than three

years after Laclede's most recent general rate case, in violation of its statutory authority. We

affirm. Background

Laclede is a natural gas provider serving approximately 500,000 customers in Missouri.1

It is a "public utility" and a "gas corporation," as defined in sections 386.020(43) and (18),

RSMo.2 The Public Service Commission is a state administrative agency responsible for the

regulation of public utilities, including gas corporations, in Missouri, pursuant to sections

386.040 and 386.250(1). State ex rel. MoGas Pipeline, LLC v. Mo. Pub. Serv. Comm'n 366

S.W.3d 493, 496 (Mo. banc 2012). The Office of Public Counsel is a state agency that represents

consumers in all utility proceedings before the Commission and in all appeals of Commission

orders. §§ 386.700 and 386.710; Pub. Serv. Comm'n of State v. Mo. Gas Energy, 388 S.W.3d

221, 224 (Mo. App. 2012).

In 2003, the Missouri Legislature enacted sections 393.1009, 393.1012, and 393.1015

("the ISRS statutes") as part of House Bill 208. Those statutes provide a method, outside of a

formal rate case, for a gas corporation to recover the cost of certain government-mandated

infrastructure system replacement projects via a petition to establish or change an ISRS. On

February 8, 2013, pursuant to the ISRS statutes, Laclede filed an "Application and Petition to

Change Its Infrastructure System Replacement Surcharge" and a revised tariff sheet.3 Laclede

sought the Commission's approval to adjust the rate elements on its already established ISRS rate

1 The original gas company respondent in this case was Southern Union Company D/B/A Missouri Gas Energy ("MGE"). Following the acquisition of MGE by Laclede Gas Company, this court sustained the companies' motion to substitute Laclede for MGE as a respondent in this case on November 26, 2013.

2 Statutory references are to the Revised Statutes of Missouri (RSMo) 2000, as updated by the 2012 Cumulative Supplement. 3 "A tariff is a document which lists a public utility['s] services and the rates for those services." In re KCP & L Greater Mo. Operations Co., 408 S.W.3d 175, 178 (Mo. App. 2013). The Commission must review the proposed tariff sheets and approve them before the proposed tariffs take effect. Id. (citing 4 CSR 240–3.010(28)).

2 schedule to recover an additional $1,741,862 in infrastructure system replacement costs that it

incurred during the last seven months of 2012.

This was Laclede's fourth request to adjust its existing ISRS since its most recent general

rate case was decided almost three years earlier, on February 10, 2010. Laclede's initial petition

to establish an ISRS, filed in July 2010, was approved by the Commission and became effective

on September 18, 2010.4 The Commission subsequently approved three adjustments to that

ISRS, with effective dates of May 17, 2011, February 14, 2012, and October 3, 2012.

On February 13, 2013, in response to Laclede's fourth petition to change its ISRS, the

Commission suspended the proposed tariff change and directed its Staff to submit a

recommendation. The Staff recommended an adjustment to Laclede's ISRS to increase the

"incremental revenue requirement" by $1,741,740.5 The Staff noted that, if the Commission

approved the petition, Laclede's "total ISRS revenue requirement will amount to $6,343,452," a

"composite amount" of $1,741,740 from the instant case and the sum of Laclede's four prior

ISRS rate increases.

The Commission, sua sponte, asked the parties to address whether the Commission had

the statutory authority to approve Laclede's petition to change its ISRS in light of the time

limitation in section 393.1012. Section 393.1012.2 provides that "[t]he commission shall not

approve an ISRS for any gas corporation that has not had a general rate proceeding decided or

dismissed . . . within the past three years." Noting that Laclede's most recent general rate case

was decided on February 10, 2010, and its petition in this case was filed on February 8, 2013

4 That ISRS was set to terminate on September 17, 2013, unless Laclede filed a new general rate case, which would allow the ISRS to be collected until resolution of that case. See § 393.1012.3. Laclede filed such a rate case on July 7, 2013. 5 The Staff's recommendation reflected a downward adjustment of $122.

3 (just under three years later), the Commission observed that section 393.1012.2 "does not

clarify" whether the petition must be filed within three years of the most recent rate case decision

or if the Commission's approval of the petition is the relevant date. Public Counsel responded

with the contention that section 393.1012.2 prohibits the Commission from approving Laclede's

petition because more than three years had passed since Laclede's last general rate case had been

decided. Laclede and the Staff argued that the three-year limitation in section 393.1012.2 applies

only to the approval of the initial ISRS rate increase, not to subsequent petitions to change an

existing ISRS.

On May 1, 2013, the Commission issued its "Order Approving Change in Infrastructure

System Replacement Surcharge, Rejecting Tariff, and Approving New Tariff," essentially

adopting the Staff's and Laclede's positions on the three-year limitation in section 393.1012.2.

The Commission found that the statutory definition of "ISRS"6 is "ambiguous" because it is

unclear whether the term "an ISRS," as used in section 393.1012.2, means the "initial" ISRS

surcharge and "each subsequent change to the surcharge," or if it refers only to the "initial" ISRS.

Applying the rules of statutory construction, the Commission found that the three-year limitation

on its authority to approve "an ISRS" applies only to the establishment of the initial ISRS, and

not to subsequent changes or adjustments to the ISRS. The Commission concluded that it had

the statutory authority to approve Laclede's petition to change its ISRS because the initial ISRS,

approved in September 2010, "was within three years of the decision in [Laclede's] most recent

general rate proceeding." Both the Commission's order approving a change to the ISRS and the

revised tariff sheet became effective on May 15, 2013.

6 Section 393.1009(6) defines "ISRS" simply as an "infrastructure system replacement surcharge."

4 The Commission denied Public Counsel's application for rehearing but granted its request

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Public Counsel v. Missouri Public Service Commission
289 S.W.3d 240 (Missouri Court of Appeals, 2009)
State Ex Rel. Public Counsel v. Pub. Service Com'n, State
259 S.W.3d 23 (Missouri Court of Appeals, 2008)
State Ex Rel. MoGas Pipeline LLC v. Missouri Public Service Commission
366 S.W.3d 493 (Supreme Court of Missouri, 2012)
Public Service Commission v. Missouri Gas Energy
388 S.W.3d 221 (Missouri Court of Appeals, 2012)
State ex rel. LaClede Gas Co. v. Public Service Commission
392 S.W.3d 24 (Missouri Court of Appeals, 2012)
State ex rel. Union Electric Co. v. Public Service Commission
399 S.W.3d 467 (Missouri Court of Appeals, 2013)
AG Processing Inc. v. Missouri Public Service Commission
408 S.W.3d 175 (Missouri Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
In The Matter of The Application of Laclede Gas Company D/B/A Missouri Gas Energy, For Approval to Change its Infrastructure System Replacement Surcharge Public Service Commission of The State of Missouri v. The Office of Public Counsel, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-the-matter-of-the-application-of-laclede-gas-company-dba-missouri-gas-moctapp-2014.