In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri West Service Territory v. Missouri Public Service Commission Missouri Office of Public Counsel

Missouri Court of Appeals·Decided September 1, 2020·No. WD83159, WD83162·Published

Opinion

IN THE MISSOURI COURT OF APPEALS WESTERN DISTRICT

IN THE MATTER OF THE ) APPLICATION OF SPIRE ) MISSOURI, INC., TO CHANGE ) ITS INFRASTRUCTURE SYSTEM ) REPLACEMENT SURCHARGE ) IN ITS SPIRE MISSOURI EAST ) SERVICE TERRITORY; IN THE ) MATTER OF THE APPLICATION ) OF SPIRE MISSOURI, INC., TO ) CHANGE ITS ) WD83159 INFRASTRUCTURE SYSTEM ) Consolidated with WD83162 REPLACEMENT SURCHARGE ) IN ITS SPIRE MISSOURI WEST ) FILED: September 1, 2020 SERVICE TERRITORY, )

Appellant-Respondent,

)

v. )

)

MISSOURI PUBLIC SERVICE ) COMMISSION, )

Respondent, )

)

MISSOURI OFFICE OF PUBLIC ) COUNSEL, )

Respondent-Appellant. )

Appeal from the Public Service Commission Before Division Four: Cynthia L. Martin, C.J., and Alok Ahuja and Thomas N. Chapman, JJ.

Spire Missouri, Inc. appeals from a Report and Order issued by the Public

Service Commission. The Report and Order addressed Spire’s applications to adjust

the Infrastructure System Replacement Surcharge for its East and West service territories, to reflect costs Spire incurred between October 2017 and January 2019.

The Commission granted Spire’s applications in large measure. It found, however, that it had no jurisdiction to address part of Spire’s applications because the applications concerned costs which were the subject of a pending appeal in this Court. The Commission also found that certain of Spire’s claimed costs were not eligible to be included in an Infrastructure Surcharge, because they related to Spire’s replacement of plastic piping which was not worn out or deteriorated.

Spire appeals. The Office of Public Counsel cross-appeals, arguing that the Commission’s Report and Order allows Spire to include certain ineligible costs in its Infrastructure Surcharge. We affirm.

Factual Background

On January 14, 2019, Spire filed applications with the Commission in which

it requested an increase in the Infrastructure Surcharge it was permitted to charge customers, to reflect the cost of pipeline replacement projects it had conducted in its East and West service territories.1 Spire’s applications sought to adjust its Infrastructure Surcharge to recover costs incurred during two separate time periods: October 1, 2017, through June 30, 2018; and July 1, 2018, through January 31, 2019.

By statute, “[g]as corporations are permitted to recover certain infrastructure system replacement costs outside of a formal rate case through a surcharge on their customers’ bills.” In re Verified Application & Petition of Liberty Energy (Midstates) Corp., 464 S.W.3d 520, 522 (Mo. 2015). As explained in § I of the Discussion which follows, this Court has held that Spire is entitled to include in its Infrastructure Surcharge only the cost of replacing worn or deteriorated cast iron or bare steel pipes to comply with state or federal safety requirements. We held that Spire is not

1 Spire was formerly known as Laclede Gas Company. It acquired Missouri Gas Energy in 2013. Spire’s East service territory comprises the area formerly served by Laclede Gas Company, while its West service territory was formerly operated by Missouri Gas Energy.

entitled to include in its Infrastructure Surcharge the cost for replacing newer plastic piping which is not itself worn or deteriorated, and which is not subject to a governmental safety mandate.

Until approximately ten years ago, Spire replaced older cast iron or steel pipes in a piecemeal fashion. Beginning in approximately 2010 or 2011, Spire implemented a strategic program to redesign and replace its gas distribution facilities on a system-wide basis. Under its new strategic replacement program, Spire abandons existing distribution facilities on a neighborhood-wide basis, and bypasses and replaces the existing piping with smaller-diameter plastic pipes operating at a higher pressure than the old system. In re Application of Laclede Gas Co. to Change its Infrastructure Sys. Replacement Surcharge v. Office of Pub. Counsel, 539 S.W.3d 835, 837 (Mo. App. W.D. 2017) (“Spire I”) (noting the gas utility’s new strategy “focused on replacing entire neighborhood systems at one time”). The Commission found that, under its strategic replacement program, Spire was replacing between 60 and 65 miles of cast-iron piping in its Missouri East service territory per year, and approximately 120 miles of such piping in its Missouri West territory.

Most of the costs Spire sought to recover in its January 2019 applications arose from its strategic replacement program. By retiring existing piping in place

and replacing it on a neighborhood-wide basis, this systematic program replaces worn out or deteriorated cast-iron or steel pipes, and newer plastic piping, in a single project. Because we have held that only the cost of replacing the metal piping is eligible for inclusion in Spire’s Infrastructure Surcharge, its strategic replacement program gives rise to cost-allocation issues.

To comply with our prior decisions holding that the cost of replacing plastic

pipe must be excluded from the Infrastructure Surcharge, Spire supported its January 2019 applications with cost studies for each individual project conducted

pursuant to its strategic replacement program – 509 separate cost studies in all. These project-specific cost studies compared the costs of retiring and replacing the plastic pipe as part of a neighborhood-wide project, with the cost of reusing the existing plastic pipe (while replacing only the worn out or deteriorated metal pipe). Where one of its cost studies showed that the cost of replacing plastic piping was less than the cost of replacing only the metal pipe, Spire sought to recover the entire cost of the specific project through its Infrastructure Surcharge. Spire justified the recovery of the entire project cost by arguing that replacing the plastic piping added no incremental cost to the particular project, and actually resulted in a cost savings for ratepayers compared to replacing the metal pipe alone. On the other hand, when its cost analysis showed that it was more expensive to replace the plastic pipe than to reuse the existing pipe on a particular project, Spire excluded the increased cost from its Infrastructure Surcharge request (on the theory that the increased incremental cost was attributable solely to the replacement of plastic components which were not eligible for inclusion in the surcharge).

The PSC’s Staff agreed with Spire’s cost-allocation approach. It argued, however, that the Commission lacked jurisdiction to adjust Spire’s Infrastructure

Surcharge for costs incurred between October 1, 2017, and June 30, 2018, because the Commission had addressed those same costs in an earlier proceeding, and the

Commission’s Report and Order addressing Spire’s prior surcharge-adjustment request was pending on appeal in this Court. See Nos. WD82302 and WD82373.

The Office of Public Counsel (or “OPC”) objected to Spire’s applications, and requested an evidentiary hearing.

The Commission held an evidentiary hearing on April 3 and 4, 2019, in which Spire, PSC Staff, and OPC participated. Following the hearing, the Commission

ordered Staff to perform calculations allocating the costs of Spire’s strategic replacement projects based on the relative length of the cast-iron or steel pipes

replaced in a particular project, as compared to the length of plastic piping replaced in the project. In its final Report and Order, the Commission explained that it requested these percentage-based calculations because “no party had provided a calculation as to what that party believed was the specific cost of the replacement of ineligible plastic mains and service lines to be removed from Spire’s” surcharge- adjustment request, “even though all parties to the case had access to the work orders and other information necessary to identify that cost.”

Free access — add to your briefcase to read the full text and ask questions with AI

In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri West Service Territory v. Missouri Public Service Commission Missouri Office of Public Counsel, (Mo. Ct. App. 2020).

In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri West Service Territory v. Missouri Public Service Commission Missouri Office of Public Counsel (In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri East Service Territory In the Matter of the Application of Spire Missouri, Inc., to Change Its Infrastructure System Replacement Surcharge In Its Spire Missouri West Service Territory v. Missouri Public Service Commission Missouri Office of Public Counsel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kilbane v. Director of the Department of Revenue
544 S.W.2d 9 (Supreme Court of Missouri, 1976)
State Ex Rel. Sprint Missouri, Inc. v. Public Service Commission
165 S.W.3d 160 (Supreme Court of Missouri, 2005)
Andresen v. Board of Regents
58 S.W.3d 581 (Missouri Court of Appeals, 2001)
Self v. Midwest Orthopedics Foot & Ankle, P.C.
272 S.W.3d 364 (Missouri Court of Appeals, 2008)
State Ex Rel. Aquila, Inc. v. Public Service Commission
326 S.W.3d 20 (Missouri Court of Appeals, 2011)
State Ex Rel. Praxair, Inc. v. Public Service Commission
328 S.W.3d 329 (Missouri Court of Appeals, 2010)
State Ex Rel. Outcom, Inc. v. City of Peculiar
350 S.W.3d 57 (Missouri Court of Appeals, 2011)
State ex rel. Edu-Dyne Systems, Inc. v. Trout
781 S.W.2d 84 (Supreme Court of Missouri, 1989)
State ex rel. Office of the Public Counsel v. Public Service Commission
938 S.W.2d 339 (Missouri Court of Appeals, 1997)
McAlister v. Strohmeyer
395 S.W.3d 546 (Missouri Court of Appeals, 2013)
Office of Public Counsel v. Public Service Commission
422 S.W.3d 358 (Missouri Court of Appeals, 2013)
Missouri Public Service Commission v. Office of the Public Counsel
516 S.W.3d 823 (Supreme Court of Missouri, 2017)
Laclede Gas Co. v. Office of Pub. Counsel
539 S.W.3d 835 (Missouri Court of Appeals, 2017)