State ex rel. Elsass v. Shelby Cty. Bd. of Commrs.

2001 Ohio 1276, 92 Ohio St. 3d 529
Ohio Supreme Court·Decided August 15, 2001·No. 2000-2051·Published·Cited by 26 cases

Opinion

[This decision has been published in Ohio Official Reports at 92 Ohio St.3d 529.]

THE STATE EX REL. ELSASS ET AL., APPELLANTS, v. SHELBY COUNTY BOARD OF COMMISSIONERS ET AL., APPELLEES.

[Cite as State ex rel. Elsass v. Shelby Cty. Bd. of Commrs., 2001-Ohio-1276.] Mandamus—Appropriation proceedings—Drainage project—Neither petitioning for public improvement nor paying assessments related to the improvement precludes landowners from seeking compensation for the taking of their property in connection with the project—Cause remanded to permit property owners to establish loss of any economically viable use. (No. 00-2051—Submitted June 20, 2001—Decided August 15, 2001.) APPEAL from the Court of Appeals for Shelby County, No. 17-99-17.

Per Curiam.

{¶ 1} Appellant Robbie May Elsass has a life estate, and her son and daughter-in-law, appellants Murray E. Elsass and Janet E. Elsass, have a remainder as tenants in common in real property located in Dinsmore Township, Shelby County, Ohio, which is within the Shelby Soil and Water Conservation District (“district”). Appellants lease the property to others for agricultural purposes, i.e., growing crops. The Elsass property is located in the southeast area of a watershed in which rain falling in the area generally flows from the northwest to the southeast and drains into Loramie Creek, the eastern boundary of the Elsass property.

{¶ 2} Around 1990 or 1991, Timothy A. Byrd, the drainage coordinator for the district, received complaints from Clarence King and his wife about a standing water problem on their property, which is located northwest of and upstream from appellants’ property. A lack of maintenance of a downstream area of the watershed that is upstream from appellants’ property, including a rotted culvert pipe underneath a driveway on the King property, caused much of the flooding problem.

SUPREME COURT OF OHIO

At that time, appellants had both surface and subsurface drains on their property, and they claim that they had no drainage problem during this period.

{¶ 3} In response to the complaints, Byrd contacted the property owners in the watershed, and a meeting was held in September 1993. Because the property owners could not agree about forming a private group to rectify the drainage problems in the watershed, Byrd advised them to petition the district. The property owners, including appellant Murray E. Elsass, then signed a petition requesting that the district assist them in the planning and construction of works of improvement needed to “[i]mprove drainage an[d] reduce flooding” in the watershed. Although no construction plans had been drafted for the project at the time the petition was signed, Byrd explained to the property owners present at the meeting, including appellant Murray E. Elsass, that new surface and subsurface drains would have to be constructed on the property. On September 21, 1993, the district, through its board of supervisors, approved the project, which was known as the King-Elsass Ditch Drainage Improvement Project (“project”).

{¶ 4} The project was placed on a waiting list until 1997, and in July 1997, the district board of supervisors held a public meeting concerning the project. At this meeting, the details of the project were discussed. Appellant Murray E. Elsass attended the meeting and did not object to the proposed project.

{¶ 5} On August 19, 1997, the board of supervisors of the district certified the project to appellee Shelby County Board of Commissioners (“board”). In accordance with R.C. 1515.20 through 1515.24, the board determined that construction of the project would improve water management and development of the lands therein, that the costs of the project would be less than the benefits, and that the project would benefit the land by promoting its economic, agricultural, and social development. The purpose of the project was to relocate the surface flow of water in the area by correcting drainage conditions upstream from appellants’

January Term, 2001

property and channeling water through appellants’ property and into the creek through a drainage pipe.

{¶ 6} On December 11, 1997, the board accepted the project as certified by the district and as recommended by the county engineer. The board authorized the advertisement and legal notice for bids to perform the work required for the project, which included the installation of about one thousand four hundred feet of corrugated plastic tubing and the construction of approximately 1,375 feet of surface drain and various erosion-control structures. The board subsequently awarded the contract to Ruhenkamp Farm Drainage, Inc. for approximately $26,000. The board then assessed property owners in the watershed to pay for the cost of the project pursuant to R.C. 1515.24. Appellants were assessed approximately $1,518.

{¶ 7} At the request of appellant Murray E. Elsass, Ruhenkamp Farm Drainage, Inc. waited for appellants’ tenant to harvest his crops before it began construction of the project in mid-August 1998. Appellees, the board and the individual commissioners, did not obtain an easement, right-of-way, or license from appellants before constructing the project. During the construction, the contractor entered appellants’ property and installed surface and subsurface drains across and under the property. The surface drain or swale constructed on appellants’ property is approximately eight hundred fifty feet long and fifty feet wide, with a maximum depth of two and a half feet. The preexisting surface drain on appellants’ property was straightened and deepened to make it easier to farm through and across the drain. The contractor also constructed a subsurface drain that followed the approximate path of the old underground drain on appellants’ property and a rock shoot that emptied into Loramie Creek.

{¶ 8} During the construction of the project, appellants did not complain about it, and Byrd explained to appellant Murray E. Elsass what the project would look like upon its completion. The contractor complied with appellant Murray E.

SUPREME COURT OF OHIO

Elsass’s request to correct a farm driveway so that appellants’ tenant would not tip his farm equipment. The project was completed in September 1998. The board paid the contractor after it was satisfied that the project was completed in accordance with plans presented by the district and the county engineer. Under R.C. 1515.29, the board has a continuing duty to maintain the completed improvement.

{¶ 9} In October 1998, appellant Murray E. Elsass, through counsel, asserted that the drainage project had resulted in a “taking” of his real property and requested that the board compensate him. Appellants had not objected to the construction of the project before that time. Appellees refused to initiate appropriation proceedings or otherwise compensate appellants for their use of appellants’ property in the construction of the project.

{¶ 10} In July 1999, appellants filed a complaint in the Court of Appeals for Shelby County for a writ of mandamus to compel appellees to institute appropriation proceedings for the uncompensated taking of their property in connection with the project and for other relief. Appellees filed an answer claiming that appellants consented to the construction of the project and were therefore estopped from claiming damages from the county. In October 1999, the court of appeals ordered the parties to file all evidence on or before November 15, 1999.

{¶ 11} On the date specified by the court, the parties submitted evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

State ex rel. Elsass v. Shelby Cty. Bd. of Commrs., 2001 Ohio 1276, 92 Ohio St. 3d 529 (Ohio 2001).

2001 Ohio 1276 (State ex rel. Elsass v. Shelby Cty. Bd. of Commrs.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

TMS Ents., Ltd. v. Cleveland
Ohio Court of Appeals, 2026
Craig v. Cromes
2025 Ohio 5759 (Ohio Court of Appeals, 2025)
State ex rel. Boggs v. Cleveland
2025 Ohio 5094 (Ohio Supreme Court, 2025)
Logan v. Champaign Cty. Bd. of Elections
2025 Ohio 297 (Ohio Court of Appeals, 2025)
State ex rel. Boggs v. Cleveland
2023 Ohio 3871 (Ohio Court of Appeals, 2023)
State ex rel. Hemphill v. Ohio State Emp. Relations Bd.
2022 Ohio 2299 (Ohio Court of Appeals, 2022)
Banford v. Aldrich Chem. Co., Inc.
2010 Ohio 2470 (Ohio Supreme Court, 2010)
Smith v. State Emp. Relations Bd., 08ap-759 (3-31-2009)
2009 Ohio 1556 (Ohio Court of Appeals, 2009)
Gilbert v. City of Cincinnati, C-070166 (3-13-2009)
2009 Ohio 1078 (Ohio Court of Appeals, 2009)
State ex rel. Hilltop Basic Resources, Inc. v. City of Cincinnati
118 Ohio St. 3d 131 (Ohio Supreme Court, 2008)
State v. Ahmed, Unpublished Decision (6-16-2005)
2005 Ohio 2999 (Ohio Court of Appeals, 2005)
State v. Paige, Unpublished Decision (12-23-2004)
2004 Ohio 7029 (Ohio Court of Appeals, 2004)
State Ex Rel. Craig v. Luebbe, Unpublished Decision (12-20-2004)
2004 Ohio 6933 (Ohio Court of Appeals, 2004)
Proctor v. Thieken, Unpublished Decision (12-23-2004)
2004 Ohio 7281 (Ohio Court of Appeals, 2004)
Sipusic v. City of Girard, Unpublished Decision (9-17-2004)
2004 Ohio 5008 (Ohio Court of Appeals, 2004)