State, Department of Transportation v. Douglas Asphalt Co.

677 S.E.2d 699, 297 Ga. App. 470, 2009 Fulton County D. Rep. 1370, 2009 Ga. App. LEXIS 455
CourtCourt of Appeals of Georgia
DecidedApril 10, 2009
DocketA09A0552
StatusPublished
Cited by5 cases

This text of 677 S.E.2d 699 (State, Department of Transportation v. Douglas Asphalt Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State, Department of Transportation v. Douglas Asphalt Co., 677 S.E.2d 699, 297 Ga. App. 470, 2009 Fulton County D. Rep. 1370, 2009 Ga. App. LEXIS 455 (Ga. Ct. App. 2009).

Opinion

BLACKBURN, Presiding Judge.

In this civil action arising out of an interstate construction and paving project, Douglas Asphalt Company sued the Georgia Department of Transportation (“DOT”) for breach of contract, claiming that DOT wrongfully declared Douglas Asphalt to have defaulted on the contract and that DOT failed to pay for various project cost over-runs. DOT counterclaimed on breach of contract grounds, alleging that Douglas Asphalt had defaulted on its obligations under the contract. DOT appeals the trial court’s order partially granting Douglas Asphalt’s motion in limine to exclude evidence of DOT’s calculations of its damages, arguing that the court wrongly ruled on the sufficiency of its damages evidence rather than on its admissi *471 bility, and that its damages evidence, including evidence of attorney fees incurred, is admissible. For the reasons set forth below, we reverse.

"The admission of evidence, including a ruling on a motion in limine, is a matter resting within the sound discretion of the trial court, and we will not disturb the exercise of that discretion absent evidence of its abuse." (Punctuation omitted.) Mon Ami Intl. v. Gale. 1 However~

[b]y its very nature, the grant of a motion in limine excluding evidence suggests that there is no circumstance under which the evidence under scrutiny is likely to be admissible at trial. In light of that absolute, the grant of a motion in limine excluding evidence is a judicial power which must be exercised with great care.

(Citation omitted.) Andrews v. Wilbanks. 2 See Hand v. Pettitt. 3 In this matter~ the record shows that in 2000, DOT entered into a contract with Douglas Asphalt, in which the latter was hired to widen and re-pave parts of Interstate 75 in Crisp and Turner Counties. Within a year or two after the highway improvement project's commencement, some initial testing by DOT caused it to suspect that some of the hot-mix asphalt, which had been used by Douglas Asphalt for re-paving Interstate 75 and other similar projects, contained less than the minimum amount of hydrated lime required by the contract. Under the contract, hydrated lime was to be added to the asphalt mix at a minimum rate of one percent of the total dry aggregate weight. Because hydrated lime added to an asphalt mix containing granite helps to make the finished pavement less susceptible to moisture and thus more durable, this deficiency caused DOT to further test Douglas Asphalt's product. Thereafter, an investigation and audit of various Douglas Asphalt records, including the records related to its Cordele plant, indicated that in 2002, Douglas Asphalt had procured less than 58 percent of the hydrated lime that was required by the contract for the Crisp and Turner highway improvement project. Specifically, the contract's specifications required 2,941.53 tons of lime for the asphalt mix produced at the Cordele plant in 2002. Howevei during that time, records indicated that only 1,652.3 tons of lime were delivered to the plant. Based on the assumption that the plant's silo, which is capable of holding 40 tons of lime, was full at the beginning of 2002, the audit *472 indicated that there was still a shortage of 1,249.23 tons (42 percent) in the amount of required lime. As a result of this audit and additional testing, DOT informed Douglas Asphalt that any nonconforming asphalt used in the project would have to be replaced.

In August 2004, Douglas Asphalt filed suit against DOT in the Superior Court of Coffee County for breach of contract, alleging that DOT had wrongfully found Douglas Asphalt to be in default of the highway improvement contract and that DOT had failed to pay for project cost over-runs. DOT filed an answer and counterclaim, which was based on breach of contract grounds, and also successfully moved to transfer venue to the Superior Court of Turner County. On December 14, 2006, DOT proffered a representative pursuant to OCGA § 9-11-30 (b) (6) to provide deposition testimony on the methods by which DOT had calculated its breach of contract damages. During that deposition, the DOT representative testified that DOT had calculated damages under four alternative theories, which included: (1) benefit of the bargain (diminution in value of the asphalt mix); (2) benefit of the bargain (applying lime shortage to total value of asphalt mix as properly constructed); (3) annualized cost; and (4) cost to remove and replace the nonconforming asphalt. On that same day, DOT proffered a second 30 (b) (6) representative to testify regarding DOT’s liquidated damages based on Douglas Asphalt’s delays in completing the highway improvement contract. Shortly thereafter, Douglas Asphalt filed a motion in limine to exclude evidence of DOT’s damages calculations, including attorney fees.

A hearing on the issue was held, and on June 12, 2008, the trial court issued an order partially granting Douglas Asphalt’s motion in limine to exclude DOT’s damages evidence, including attorney fees. Specifically, the court ruled that the only damages evidence not excluded was evidence of DOT’s liquidated damages, which were based on Douglas Asphalt’s delays in completing the highway improvement contract. A week later, the order was set aside so that the court would have more time to consider DOT’s request for a certificate of immediate review. On August 25, 2008, the trial court re-issued its order and also issued a certificate of immediate review. DOT filed an application for interlocutory review, which this Court granted. This appeal followed.

1. DOT contends that the trial court erred in granting Douglas Asphalt’s motion in limine to exclude evidence of the calculations for its breach of contract damages, arguing that the court, in effect, improperly granted summary judgment to Douglas Asphalt on the issue of damages. We agree.

“Damages recoverable for a breach of contract are such as arise naturally and according to the usual course of things from such breach and such as the parties contemplated, when the contract was *473 made, as the probable result of its breach.” OCGA § 13-6-2. See Freightliner Chattanooga v. Whitmire. 4 Additionally,

[t]he rule against recovery of vague, speculative, or uncertain damages relates more especially to the uncertainty as to cause, rather than uncertainty as to the measure or extent of the damages. Mere difficulty at fixing their exact amount, where proximately flowing from the alleged injury, does not constitute a legal obstacle in the way of their allowance.

Bollea v. World Championship Wrestling, 5 Furthermore, “[a] motion in limine, which seeks to prevent the introduction of evidence, is not an appropriate vehicle to test the sufficiency of that evidence.” Buck’s Svc. Station v. Dept. ofTransp, 6 See .Dept. ofTransp. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael Miller v. Jim Lynch
Court of Appeals of Georgia, 2019
Miller v. Lynch
830 S.E.2d 749 (Court of Appeals of Georgia, 2019)
Fowlers' Holdings, Lllp v. Clp Family Investments
Court of Appeals of Georgia, 2012
Fowler's Holdings, LLLP v. CLP Family Investments, L.P.
732 S.E.2d 777 (Court of Appeals of Georgia, 2012)
State, Department of Transportation v. Douglas Asphalt Co.
677 S.E.2d 728 (Court of Appeals of Georgia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
677 S.E.2d 699, 297 Ga. App. 470, 2009 Fulton County D. Rep. 1370, 2009 Ga. App. LEXIS 455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-department-of-transportation-v-douglas-asphalt-co-gactapp-2009.