Stanspec Corporation, Cross-Appellant v. Jelco, Incorporated, Cross-Appellees

464 F.2d 1184
CourtCourt of Appeals for the Tenth Circuit
DecidedSeptember 8, 1972
Docket71-1639, 71-1640
StatusPublished
Cited by26 cases

This text of 464 F.2d 1184 (Stanspec Corporation, Cross-Appellant v. Jelco, Incorporated, Cross-Appellees) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanspec Corporation, Cross-Appellant v. Jelco, Incorporated, Cross-Appellees, 464 F.2d 1184 (10th Cir. 1972).

Opinion

SETH, Circuit Judge.

Stanspee Corporation brought this action against Jelco, Incorporated, and its sureties to recover the unpaid balance of the purchase price under an equipment supply contract. Jelco admitted the existence of an unpaid balance, but raised in defense and counterclaim Stanspec’s non-performance of an earlier contract for essentially identical machinery. Judgment was entered in favor of Stanspee for the amount in dispute plus six per cent interest. The defendants filed notice of appeal and Stanspee filed notice of cross-appeal.

Jelco was a bidder on the mechanical and electrical work on the Straight Creek Tunnel Project in Colorado, and was ultimately awarded a contract. In preparing its bid Jelco requested bids from suppliers of bulkhead hoists. One of the suppliers contacted was Plant Equipment Company of Denver, who in turn obtained a written proposal for the manufacture and delivery of the hoists from plaintiff Stanspee. A representative of Plant Equipment obtained the plans and specifications for the hoists *1186 from the Colorado State Department of Highways and provided them to S.tan-spec for its use in preparing the proposal. For reasons undisclosed by the record, however, the specifications did not include certain amendments and revisions then in existence, in particular a drawing showing the type of electrical switch to be used in the hoists. On September 20, 1967, the specification change in question had been mailed to Jelco as it was listed with the State Highway Department as a plan-holder and was on the mailing list for revisions and addenda. Stanspee and Plant Equipment Company were not.

For reasons unrelated to this suit, Stanspec’s original proposal to supply the hoists at $1,479.00 each was superseded by a second agreement consummated on May 24, 1968. Still acting in the capacity of a supplier, Plant Equipment Company then contacted Mr. Farley, the Jelco representative in charge of Stanspec’s proposal, and requested a current set of specifications. Mr. Farley supplied a set of specifications identical to those which Plant Equipment Company had originally obtained from the State Highway Department, and on the basis of these specifications Plant Equipment submitted the second proposal for Stanspee on May 10, 1968, which was accepted. Stanspee then submitted its final drawings and plans to the project engineers for approval, and upon their rejection it became apparent that both proposals had been prepared on the basis of incomplete specifications.

Stanspee submitted a new proposal to Jelco designed to meet the additional requirements at a new price, but Jelco rejected the proposal, contending that it was Stanspec’s responsibility to provide equipment conforming to all existing specifications at the original price. After continued discussions, Stanspee received another purchase order from Jelco, this time offering a higher price for the hoists under the revised descriptions, but containing a provision specifically reserving Jelco’s rights under the May 1968 contract. Stanspee returned this order to Jelco rejecting the new order and noting its willingness to provide revised equipment at a higher price without any “special conditions, exhibits, appendixes, or etc. . . .”

Jelco’s attempts to locate another supplier were to no avail, and it agreed to purchase the hoists according to the terms outlined in Stanspec’s letter of September 26th. After further price negotiations an agreement to supply hoists at $1,889.25 each was consummated and Stanspee performed. Jelco withheld a portion of the final payment, a portion essentially equivalent to the price difference between the May 10, 1968, and November 10, 1969, contracts.

At trial Stanspee contended that the November 10, 1969, agreement was the only effective contract, and maintained that it would not have entered into this November contract had it been aware of Jelco’s intention to reserve its rights under the earlier contract. In this regard it urges that Jelco fully appreciated Stanspec’s position at the time. Jelco, on the other hand, maintains that the November 10th agreement was not the solution to the dispute, but on the contrary, maintains that it entered the contract with Stanspee only to facilitate prompt and equitable mitigation of its damages under the initial contract. Jelco further urges that Stanspee was expressly bound under the original contract to furnish equipment in conformity with existing specifications.

The trial court found that the November 10th contract represented an agreed compromise of the dispute, and was binding on the parties. Thus no rights remained under the first contract. The court further found as a matter of law that an out-of-state supplier of equipment and materials has no duty to inquire into changes in or addenda to the specifications furnished by a bidding subcontractor.

An agreement which compromises a bona fide dispute as to the duties under an existing contract is of course enforceable and binding if the *1187 dispute as to those duties and obligations is not founded on bad faith. Pittsburgh Testing Laboratory v. Farnsworth & Chambers Co., 251 F.2d 77 (10th Cir.). The law actively encourages compromise and settlement of disputes. Tulsa City Lines v. Mains, 107 F.2d 377 (10th Cir.).

A damaged party entitled to the benefit of a contract is under a duty to mitigate his damages, and generally speaking his rights are not diminished if the circumstances force him to deal with the party in default. Warren v. Stoddart, 105 U.S. 224, 26 L.Ed. 1117; see also Annot. 46 A.L.R. 1192; 22 Am. Jur.2d, Damages § 35. However, Jelco maintains that because it had no real choice in this regard, and because of its obligation to mitigate damages, its acceptance of the terms of the second contract cannot be construed as a waiver of its rights under the earlier contract.

A non-defaulting party need not accept a modified contract in mitigation of its damages when the modified offer includes abandonment of any right of action for a prior breach as a condition of acceptance. Campfield v. Sauer, 189 F. 576 (6th Cir.); compare Farmers’ Co-Op. Ass’n v. Shaw, 171 Okl. 358, 42 P.2d 887, and Annot. 72 A.L.R. 1050. The ultimate purchase of the hoists from Stanspec appears to have been made not so much in mitigation of damages but because this was the only source within the time limitations. If it is a fact that the November 10th agreement was conditioned upon Jelco’s non-reservation of rights under the May 10th agreement, it is apparent that Jelco could not have entered into the second contract without relinquishing its rights under the first. Despite the fact that Jelco was faced with a choice, it did not entitle it to avoid the effect of the second contract as it now urges. United States v. Brookridge Farm, 111 F.2d 461 (10th Cir.). The abandonment of fights under a contract by executing a later substituted contract is not prevented by protesting that rights still exist under the former. United States ex rel. International Contracting Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Welding, Inc. v. Advanced Circuits, Inc.
2018 CO 56 (Supreme Court of Colorado, 2018)
Cuyahoga Metropolitan Housing Authority v. United States
65 Fed. Cl. 534 (Federal Claims, 2005)
Franconia Associates v. United States
61 Fed. Cl. 718 (Federal Claims, 2004)
Singer v. WEST PUBLISHING CORP.
310 F. Supp. 2d 1246 (S.D. Florida, 2004)
Westec Construction Management Co. v. Postle Enterprises I, Inc.
68 P.3d 529 (Colorado Court of Appeals, 2002)
Koby v. United States
53 Fed. Cl. 493 (Federal Claims, 2002)
Minto v. Lambert
870 P.2d 572 (Colorado Court of Appeals, 1993)
O'DELL v. Basabe
810 P.2d 1082 (Idaho Supreme Court, 1991)
La Casa Nino, Inc. v. Plaza Esteban
762 P.2d 669 (Supreme Court of Colorado, 1988)
Heiar v. Crawford County
746 F.2d 1190 (Seventh Circuit, 1984)
Jimmy Lee Gray v. Eddie Lucas, Warden
677 F.2d 1086 (Fifth Circuit, 1982)
EQUAL EMP. OPP. COM'N v. American Tel. & Tel. Co.
419 F. Supp. 1022 (E.D. Pennsylvania, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
464 F.2d 1184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanspec-corporation-cross-appellant-v-jelco-incorporated-ca10-1972.