Stanley Kline v. William Benefiel

CourtCourt of Appeals of Tennessee
DecidedSeptember 18, 2000
DocketW1999-00918-COA-R3-CV
StatusPublished

This text of Stanley Kline v. William Benefiel (Stanley Kline v. William Benefiel) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stanley Kline v. William Benefiel, (Tenn. Ct. App. 2000).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON SEPTEMBER 18, 2000 Session

STANLEY J. KLINE, ET AL. v. WILLIAM I. BENEFIEL, ET AL.

Direct Appeal from the Circuit Court for Shelby County No. 59043 T.D.; The Honorable Jon Kerry Blackwood, Judge, by Designation

No. W1999-00918-COA-R3-CV - Filed January 9, 2001

This case arises from a home construction contract entered into by the Appellants and the Appellees. The Appellants filed a complaint against the Appellees in the Circuit Court of Shelby County for breach of contract. The Appellees filed a counter-complaint for breach of contract and unjust enrichment. The Appellants filed an amended complaint for violations of the Tennessee Consumer Protection Act. The trial court dismissed the Appellees’ counter-complaint and found in favor of the Appellees as to the Appellants’ complaint. The Appellants appeal from the order of the Circuit Court of Shelby County, finding in favor of the Appellees. For the reasons stated herein, we affirm the trial court’s decision.

Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Circuit Court Affirmed

ALAN E. HIGHERS , J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J., W.S., and HOLLY KIRBY LILLARD , J., joined.

David A. Siegel, for Appellants

Ralph D. Golden, for Appellees

OPINION

I. Facts and Procedural History

On September 17, 1991, the Appellants, Stanley J. Kline and Sandra C. Kline (“the Klines”) entered into a home construction contract with the Appellees, William L. Benefiel (“Mr. Benefiel”) and Robert Benefiel, Individually and d/b/a Benefiel Homes, a Tennessee General Partnership (“Benefiel”). The Klines originally had contracted with another home builder, but this contract was terminated after problems with the lot arose. In their search for a new builder, the Klines interviewed Mr. Benefiel and read his advertisement brochure. The brochure states that “[Mr. Benefiel] became an engineer with several leading firms and eventually owned his own engineering/surveying firms . . . .” Mr. Kline claims that Mr. Benefiel also orally represented that he was an engineer and could handle the Klines’ structural concerns. Mr. Benefiel is a home builder and holds a general contractor’s license. He states that he worked as a draftsman for several engineering firms; however, he is not an engineer. Mr. Benefiel insists that he never told the author of the advertisement brochure that he was an engineer. Mr. Benefiel was aware that the brochure stated that he was an engineer, but he did not think it was important to correct the brochure since he was not working in the engineering field. Mr. Benefiel also asserts that he never orally represented to the Klines that he was an engineer. Mr. Benefiel claims that his wife told Mrs. Kline that Mr. Benefiel was not an engineer. Mrs. Kline denies this conversation took place. The Klines claim they were searching for a builder with “special expertise” and never would have contracted with Mr. Benefiel had they known he was not an engineer and had misrepresented himself as such. Mr. Benefiel argues that the brochure is not the cause of any injury the Klines may have incurred.

Construction on the home began in the fall of 1991. Generally, Mrs. Kline was at the house daily. Mr. Benefiel claims it was difficult to work because Mrs. Kline often spoke with the subcontractors, and she was constantly making changes. Mrs. Kline denies that she bothered or made demands on Mr. Benefiel and the subcontractors. The Klines moved into the house on April 24, 1992. This move-in date was beyond Mr. Benefiel’s sixth month deadline to have substantially completed work on the house. Section two of the contract imposes a penalty upon Mr. Benefiel for failure to meet the construction deadline.1 Mr. Benefiel cites bad weather, numerous changes made by the Klines, and general problems in constructing the house for the delay. The Klines argue that they did not delay Mr. Benefiel, and bad weather and problems in constructing the house had very little to do with the delay. Mr. Benefiel submitted to the Klines a builder fee for $3,727.24 due as of June 10, 1992, but the Klines never paid the bill.

The Klines state that they informed Mr. Benefiel of defects both prior to and after they moved in the house. They claim that Mr. Benefiel refused to correct any of the defects. In August, 1992, the Klines sent Mr. Benefiel a letter outlining sixty-five defects in the house. Mr. Benefiel invoked section six of the contract which provided for a third party to inspect the house and make binding determinations on the parties as to what items were defective.2 Mr. Benefiel selected Donald

1 The pena lty clause of section two of the contract states: Owner agrees that the maxim um liability amount that Contractor shall be held liable for and penalized for if he takes longer than the approved length of time shall be calculated at fifty dollars ($50.00) per day or no m ore than te n percen t (10%) of the total B uilders Fee , for not being able to complete work on time.

2 Section six , paragrap h two o f the contra ct states: If owne r and co ntractor sh ould disa gree ov er com pleted w ork that owner deems defective, the contractor has the right to have a third party that is mutually respected and approved by both owner and contractor and qualified in the particular field that is in question to make determ inations of what is go od and acceptab le and w hat shall (continu ed...)

-2- Merritt (“Mr. Merritt”) to inspect the house. Mr. Merritt inspected the house on October 22, 1992. Mr. Merritt found approximately fifteen of the sixty-five items to be defective.

Both the Klines and Mr. Benefiel state that they agreed to be bound by Mr. Merritt’s report pursuant to section six of the contract. The Klines argue that Mr. Benefiel breached the contract because he refused to comply with Mr. Merritt’s report. One particular point of contention between the Klines and Mr. Benefiel is that Mr. Merritt’s report stated that the Mexican tile in the house was defective. Mr. Benefiel argues that he should not be responsible for repairing the Mexican tile because the Klines directly contracted for the Mexican tile with Lynn & Adams Tile Company (“Lynn & Adams”). Section nine of the contract states that Mr. Benefiel is responsible only for the work of subcontractors with whom he contracts.3 Mr. Benefiel gave the Klines the name of a tile installer that he used as a subcontractor. The Klines decided not to use this subcontractor, and they looked for another tile installer. Mrs. Kline contacted Bob Lynn (“Mr. Lynn”), a tile installer with Lynn & Adams. Mr. Lynn ordered the tile, and his partner, Hugh Adams (“Mr. Adams”) installed the Mexican tile in the house. Mr. Lynn stated that when he began speaking with Mrs. Kline about installing the tile he did not know Mr. Benefiel was involved in the job. Mr. Benefiel claims that he did not speak to Mr. Lynn before the tile work began.

Mrs. Kline was not satisfied with the Mexican tile. She held two meetings with Mr. Lynn to discuss her complaints with the Mexican tile. Mr. Lynn stated that Mr. Benefiel attended both of these meetings. Whitney Cook (“Ms. Cook”), an expert in refinishing Mexican tile, was brought in to restrip and reseal the tile. Mr. Lynn agreed to pay Ms. Cook for her work if Mrs. Kline was satisfied. After Ms. Cook finished the work, Mrs. Kline stated she would “have to live with it,” and Mr. Lynn paid Ms. Cook. Lynn & Adams submitted the bills for the Mexican tile to Mr. Benefiel who submitted them to the Klines for payment. On other items for which the Klines directly contracted, however, Mr. Benefiel did not submit a check to the Klines. Mr. Benefiel stated that he thought he was responsible for supervising the Mexican tile work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Brown & Williamson Tobacco Corp.
18 S.W.3d 186 (Tennessee Supreme Court, 2000)
McDaniel v. CSX Transportation, Inc.
955 S.W.2d 257 (Tennessee Supreme Court, 1997)
State v. Kennedy
7 S.W.3d 58 (Court of Criminal Appeals of Tennessee, 1999)
Tampa Electric Company v. Nashville Coal Company
214 F. Supp. 647 (M.D. Tennessee, 1963)
Smith County v. Eatherly
820 S.W.2d 366 (Court of Appeals of Tennessee, 1991)
Lazy Seven Coal Sales, Inc. v. Stone & Hinds, P.C.
813 S.W.2d 400 (Tennessee Supreme Court, 1991)
Action Ads, Inc. v. William B. Tanner Co.
592 S.W.2d 572 (Court of Appeals of Tennessee, 1979)
McCaleb v. Saturn Corp.
910 S.W.2d 412 (Tennessee Supreme Court, 1995)
Ridings v. Ralph M. Parsons Co.
914 S.W.2d 79 (Tennessee Supreme Court, 1996)
Cummins v. Brodie
667 S.W.2d 759 (Court of Appeals of Tennessee, 1983)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Gilson v. Gillia
321 S.W.2d 855 (Court of Appeals of Tennessee, 1958)
Wright v. City of Knoxville
898 S.W.2d 177 (Tennessee Supreme Court, 1995)
Ballard v. Herzke
924 S.W.2d 652 (Tennessee Supreme Court, 1996)
Haverlah v. Memphis Aviation, Inc.
674 S.W.2d 297 (Court of Appeals of Tennessee, 1984)
Cook & Nichols v. PEAT, MARWICK, MITCHELL
480 S.W.2d 542 (Court of Appeals of Tennessee, 1971)
Whitaker v. Whitaker
957 S.W.2d 834 (Court of Appeals of Tennessee, 1997)
Salley v. Pickney Co.
852 S.W.2d 240 (Court of Appeals of Tennessee, 1992)
Buchanan v. Harris
902 S.W.2d 941 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Stanley Kline v. William Benefiel, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stanley-kline-v-william-benefiel-tennctapp-2000.