Stangl v. Todd

554 P.2d 1316, 1976 Utah LEXIS 916
CourtUtah Supreme Court
DecidedSeptember 2, 1976
Docket14105
StatusPublished
Cited by15 cases

This text of 554 P.2d 1316 (Stangl v. Todd) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stangl v. Todd, 554 P.2d 1316, 1976 Utah LEXIS 916 (Utah 1976).

Opinion

MAUGHAN, Justice.

Plaintiff, a building contractor, brought this action to foreclose a mechanic’s lien, for construction work performed pursuant to an agreement to build a high-rise apartment complex. Defendants filed a counterclaim seeking damages, for plaintiff’s breach of a construction contract. Upon trial to the court, after allowing an offset for labor and materials furnished by plaintiff, defendants were awarded damages of $340,877. Plaintiff appeals.

Answers to two questions are definitive of this appeal. Was there a contract, and did the trial court adopt the correct measure of damage? There was a contract, and damage was correctly determined. We affirm. No costs awarded.

Defendants desired to build an apartment complex. They retained the services of an architect to draft the plans. The architect introduced defendants to plaintiff, an experienced contractor, with whom the architect had worked on other projects. In June, 1972, defendants requested plaintiff prepare a cost estimate to submit to a prospective mortgagee. Plaintiff, utilizing the preliminary plans, prepared a cost breakdown sheet itemizing the expenses for each of the various components involved in the construction of the project.

Accompanying this estimate was a letter, in which plaintiff represented that, although it was impossible to give an exact bid without exact plans, he had by using the construction management method, been able to give a prospective owner a preliminary proposal indicating a basic type of construction. Also, this, together with his initial participation in the engineering and selection of specified materials, had enabled him to build over 100 projects; and hold within the budget projected in the preliminary proposal. This estimated cost was $2,359,000. The price was increased to $2,399,222 after the addition of several items. Defendants then secured a loan commitment for $2,350,000.

The architect proceeded to develop the. plans and specifications, and plaintiff was in frequent contact observing and participating in the design. Plaintiff had his lawyers draw a written document, entitled a “construction agreement.” He presented it to defendants about October 10, 1972. Defendants suggested three minor changes. On October 11, defendants executed and delivered the note, trust deed, and land lease for the project. The next day they met with plaintiff, and the three executed the construction agreement.

Plaintiff commenced performance on October 15, 1972. The site was cleared of existing structures; the land was excavated, the footings poured, and much of the re-bar for the foundations was placed. By December, plaintiff was ready to pour the foundation for the east tower of the complex, but the work was delayed by bad weather. When the weather improved, plaintiff refused to continue the construction for the contract price.

The parties conferred several times in January, 1973, and plaintiff presented a cost breakdown reflecting the bids he was receiving from subcontractors. At this time, plaintiff’s estimated cost of con *1318 structing the project was $2,700,000, plus 10 per cent overhead. 1

Later, other bids were sought, plaintiff submitting bid of $3.4 million, which was lower than the other bids received.

In March, 1973, defendants sent plaintiff a letter stating his default; and demanding he resume construction, under the contract. Thereafter, plaintiff filed a mechanic’s lien for the completed work and this action ensued. 2

Defendants abandoned the project; the partial construction was razed. They presented evidence showing their expenditure and loss of $276,390.32, in advancing the project. This sum included the loan commitment fees; and a $50,000 bonus they were required to pay, to repurchase the property which had been subject to a long-term lease.

This matter was tried to the court, over a period of three weeks during which there were many contested issues of fact. The trial court found: On October 12, 1972, the parties entered into a written contract by which plaintiff agreed to construct, in accordance with plans and specifications, a 183-unit apartment complex, for which defendants agreed to pay plaintiff $2,399,222, plus a sum representing the value of extra work, if any. By the time the parties executed the construction agreement, they were in substantial agreement as to all material aspects of the building to be constructed for the fixed price, and the plans and drawings substantially reflecting their agreement had been prepared by the architect, examined by the parties, and become part of the construction agreement. Pursuant to the construction agreement, additional plans and detailed working drawings were developed. Such plans did not depart from the understanding the parties had at the time they executed the agreement. There were specified extras for which plaintiff was to be compensated by defendants, in addition to the agreed price, again according to the agreement. The reasonable worth of these extras was $189,475.

Further findings were: On about January 15, 1973, plaintiff, without just cause or excuse, ceased work under the agreement, removed his tools and equipment from the construction site, advised defendants he would not perform the agreement, for the price fixed therein. Such conduct was a material breach of the construction agreement. At the time of the breach of the agreement, the reasonable cost of completion, including those items incorporated in plans and specifications for which plaintiff was to be compensated as extras, was $2,970,450. If plaintiff had performed the work and furnished the extras, he would have been entitled to $189,475 in addition to the contract price of $2,399,222. As a result of plaintiff’s breach, defendants have been damaged in an amount equal to the difference between the reasonable cost of completion of the project, $2,970,450, and the unpaid portion of the contract price, $2,399,222; less extras in the amount of $189,475; less an offset for partial construction by plaintiff, in the sum of $40,876. The result of such calculations equals damages in the sum of $340,877. 3

Additional findings were: As a matter of law, the construction agreement was a valid, binding contract, which obligated plaintiff to construct the project in substantial compliance with the plans and specifications, for a fixed price, plus the reasonable worth of any agreed extras. The agreement provided for resolution of conflicts and for the incorporation of extras and additions, and inclusion of such items did not invalidate the agreement. The *1319 construction agreement was not invalidated by the ambiguity of any provision or by uncertainty of its terms: The agreement was neither preliminary, nor tentative; and did not constitute an agreement to agree. According to the court’s ruling, the agreement, having been prepared by plaintiff’s attorney pursuant to plaintiff’s instructions, was to be construed against the scrivener.

On appeal, plaintiff contends the parties had not reached an agreement sufficiently definite and certain to support a finding that plaintiff had committed a breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ressa Construction, Inc. v. Jason Dillaman
Court of Appeals of Virginia, 2025
MC Oil & Gas, LLC v. Ultra Resources, Inc.
145 F. Supp. 3d 1066 (D. Utah, 2015)
Montara Owners Ass'n v. La Noue Development, LLC
317 P.3d 257 (Court of Appeals of Oregon, 2013)
Cashman Equipment Corp. v. United States Fire Insurance
368 F. App'x 288 (Third Circuit, 2010)
Traco Steel Erectors, Inc. v. Comtrol, Inc.
2009 UT 81 (Utah Supreme Court, 2009)
Traco Steel Erectors, Inc. v. Comtrol, Inc.
2007 UT App 407 (Court of Appeals of Utah, 2007)
Sachs v. Lesser
2007 UT App 169 (Court of Appeals of Utah, 2007)
Coulter & Smith, Ltd. v. Russell
966 P.2d 852 (Utah Supreme Court, 1998)
Andrulis v. Levin Construction Corp.
628 A.2d 197 (Court of Appeals of Maryland, 1993)
Kirkpatrick v. Temme
654 P.2d 1011 (Nevada Supreme Court, 1982)
Nielsen v. Chin-Hsien Wang
613 P.2d 512 (Utah Supreme Court, 1980)
Tri-County Electric Ass'n v. City of Gillette
584 P.2d 995 (Wyoming Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
554 P.2d 1316, 1976 Utah LEXIS 916, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stangl-v-todd-utah-1976.