Rex T. Fuhriman, Inc. v. Jarrell

445 P.2d 136, 21 Utah 2d 298, 1968 Utah LEXIS 643
CourtUtah Supreme Court
DecidedSeptember 16, 1968
Docket10925
StatusPublished
Cited by5 cases

This text of 445 P.2d 136 (Rex T. Fuhriman, Inc. v. Jarrell) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rex T. Fuhriman, Inc. v. Jarrell, 445 P.2d 136, 21 Utah 2d 298, 1968 Utah LEXIS 643 (Utah 1968).

Opinion

CALLISTER, Justice:

Plaintiff initiated this action to recover rent on a home occupied by defendants while plaintiff was building defendants a new home. Defendants asserted a counterclaim for damages for breach of the construction contract for the new home. The trial court, sitting without a jury, rendered judgment to the plaintiff in the sum of $865.36 ($858.36 for rent and $7 for damages to a door in the rental unit). The court granted judgment to the defendants in the sum of $1300 ($1200 damages for not waterproofing the basement according to the specifications of the building contract and $100. for a “glaring patch” in the linoleum in the middle of the room). The difference in the two judgments was $434.64, which was awarded in favor of defendants.

Plaintiff-appellant seeks reversal of the award of judgment on defendants’-respondents’ counterclaim. Respondents urge that the trial court improperly omitted certain damages in the award.

Plaintiff is a building contractor corporation and has been engaged in building new homes in the Golf Course Subdivision in Logan, Utah. Defendants desired a new home in this area, and they entered into an arrangement with plaintiff whereby defendants would occupy one of plaintiff’s completed homes at an agreed rental of $125 a month, while a new home was being constructed pursuant to a building contract between the parties. Defendants occupied the rental unit from September 9, 1964, until April 5, 1965, for a total rent of $858.36.

Upon completion of the new home, plaintiff submitted a final statement to defendants, which included a recitation of the contract price of $20,750 and then specified certain extra charges and credits including the aforementioned rent; the sum of $5,029.65 was indicated as the unpaid balance. Defendants sent plaintiff two checks; one was for $138.36 and recited “Rent (1454 North 16 East) less interest on house money,” the other check was for $3,920.10 and recited “In full payment on my home 1675 East 14th North, Logan, Utah.”' Plaintiff cashed the latter check and returned the rent check as unacceptable.

At the time the parties contemplated construction of the home, -the defendants, informed plaintiff that they wbtíftFprocure *300 out-of-state financing from a bank in Tennessee. Defendants made the appropriate arrangements and received $24,000 which they deposited in their names in a local bank on November 6, 1964. The parties orally agreed that while plaintiff was using the funds in the construction of the home, plaintiff would pay defendants 6% interest on the money. Defendants understood this agreement to mean that they would receive 6% of $24,000 or $120 per month from plaintiff from the time they received the loan until completion of the new home. The president of plaintiff understood that he would' pay the agreed 6% interest on the funds only as they were disbursed to him. The building contract, although it neither had a provision for this interest agreement nor the rental arrangement, did provide for four draws at various stages of the construction. In plaintiff’s computations on the recapitulation sheet, a credit of $182.30 for interest on the loan was indicated as follows: $10,000 for 90 days, $150.30, and $6,000, 32 days, $32. The evidence indicated that the first draw was paid January 5, 1965, for $10,000, and the second draw was March 3, 1965 for $6,000.

On November 10, 1964, three days subsequent to defendants’ receipt of the $24,-000 loan, they paid plaintiff $3,900 for the lot upon which the house was to be constructed and received the deed thereto. Defendants, nevertheless, contend that the house and lot were part of a single transaction and that plaintiff is liable for the interest thereon until completion of the house.

It was the duty of the trial court in its interpretation of this oral agreement to ascertain the meaning to be given to the words and manifestations of the parties and thus determine their intention. 1

From all the surrounding facts and circumstances, there is nothing to indicate that the trial court erred in its determination that the intention of the parties to the agreement was consonant with plaintiff’s interpretation, regardless of defendants’ understanding. 2 The construction contract specified a price of $20,750 for labor, materials and supplies and provided a time table for payment according to completion of certain phases of the work, the defendants retained exclusive dominion and control over the funds until they elected to disburse them, and defendants accepted and retained the deed to the property, which was not included in the price of the construction contract.

*301 'Defendants’ ’counterclaim is premised on’ the breach of the construction contract in two particulars: one, breach of the provision to "construct and complete the residence in a good workmanlike manner,” and, ’two, failure to comply with the specifications.

' Defendants have alleged that as a result of plaintiff’s breach, water has seeped into their basement. The testimony indicated that after ■ the defendants moved into their home in the spring of 1965, the basement began to leak; there were approximately 13 places where the water ran through the walls. Plaintiff sent a man who repaired two of these leaks by drilling out two' holes from the inside and filling them with cement.' Only two leaks were patched because defendants were assured that when their patio was poured, the leaking would stop; this desired result was only partially achieved. During the spring of 1966, there was additional leakage in the basement. The leaks appeared from two sources, from the areas where the ties came through the foundation and possibly from a honeycomb area, where the cement was not packed in tightly.

The dispute as to whether plaintiff complied with the specifications in the contract is dependent upon the meaning of the following provision: “2. Foundations: Waterproofing * * * Asphalt Emulsion.”

Plaintiff’s president admits that he personally drew the contract and selected the foregoing terms. He testified that there are two methods of waterproofing: o,ne, paint the foundation below ground level with a solution of asphalt emulsion; two, put on a material of thicker consistency than the asphalt emulsion over areas considered to be prime so far as seepage of water in the area. He further testified that for the past years he has used the thicker material which is applied with a putty or spackle knife to the critical areas in the foundation such as where the tie rods are broken off, rather than painting the entire area with asphalt emulsion.

Counsel queried whether the thicker material was asphalt emulsion; the president responded that he didn’t know the technical content of the thicker material and did not know whether or not it was referred to as asphalt emulsion. The president further admitted that while testifying he did not refer to the material as thicker asphalt emulsion but as thicker material. This testimony alone is indicative of the fact that the material actually used was not that designated by the president in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hone v. Advanced Shoring & Underpinning, Inc.
2012 UT App 327 (Court of Appeals of Utah, 2012)
Baker v. Dataphase, Inc.
781 F. Supp. 724 (D. Utah, 1992)
Nielsen v. Chin-Hsien Wang
613 P.2d 512 (Utah Supreme Court, 1980)
Winsness v. M. J. Conoco Distributors, Inc.
593 P.2d 1303 (Utah Supreme Court, 1979)
Stangl v. Todd
554 P.2d 1316 (Utah Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
445 P.2d 136, 21 Utah 2d 298, 1968 Utah LEXIS 643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rex-t-fuhriman-inc-v-jarrell-utah-1968.