SPUS8 Dakota LP v. KNR Contractors LLC

District Court, D. Arizona·Decided August 9, 2022·No. 2:19-cv-05477·Unknown

Opinion

1 WO 2 3 4 5 6 IN THE UNITED STATES DISTRICT COURT 7 FOR THE DISTRICT OF ARIZONA

9 SPUS8 Dakota LP, et al., No. CV-19-05477-PHX-MTL

10 Plaintiffs, ORDER

11 v.

12 KNR Contractors LLC, et al.,

13 Defendants. 14 15 Pending before the Court is Defendant/ Cross-claimant KNR Contractor, LLC’s 16 motion for summary judgment against Cross-Defendants Oddonetto Granite & Marble 17 LLC and John Oddonetto. (Doc. 146.) For the reasons listed below, the motion is granted 18 in part and denied in part.1 19 I. BACKGROUND 20 The cross-claims at issue here concern a contract dispute between a general 21 contractor, KNR Contractor, LLC (“KNR”), and a subcontractor, Oddonetto Granite & 22 Marble, LLC (“Oddonetto LLC”) and John Oddonetto (collectively, “Oddonetto”). The 23 contract dispute involves the subcontractor’s obligation to procure, supply, and install 24 granite countertops and sinks for a multi-unit apartment complex renovation project (the 25 “KOTA Project”). 26 A. The Uncontroverted Facts 27 1 Neither party requested oral argument pursuant to LRCiv 7.2, and oral argument will not 28 aid the Court’s decision. See Partridge v. Reich, 141 F.3d 920, 926 (9th Cir. 1998); see also LRCiv 7.2(f); Fed. R. Civ. P. 78(b). 1 KNR contracted Oddonetto to procure, supply, and install granite countertops and 2 sinks for the KOTA Project. (Doc. 147 ¶ 1; Doc. 160 ¶ 1.) KNR made an initial payment 3 to Oddonetto of $167,126.00. (Doc. 147 ¶ 2; Doc. 160 ¶ 2.) John Oddonetto emailed KNR 4 on March 21, 2019, requesting additional funds to unload a delivery of granite that was in 5 port, and that KNR made a second payment of $78,200.00 on March 29, 2019. 6 (Doc. 147 ¶ 2; Doc. 160 ¶ 2.) The parties disagree about the content and meaning of that 7 email. (Doc. 147 ¶ 2; Doc. 160 ¶ 2.) They agree, however, that the delivery at port that 8 was mentioned in Oddonetto’s March 21 email, contained less than 25% of the total order 9 of granite countertops and sinks for the KOTA Project. (Doc. 147 ¶ 3; Doc. 160 ¶ 3.) In 10 October 2019, Plaintiffs SPUS8 Dakota LP, SPUS8 Pinnacle LP (collectively, “Dakota”), 11 and KNR called Oddenetto to take inventory of the granite countertops and sinks, but 12 Oddonetto “did not have any of the granite countertops and sinks” prepared. (Doc. 147 ¶ 13 4; see Doc. 159 ¶ 49–50; Doc. 160 ¶ 4.) 14 B. KNR’s Controverted Facts 15 KNR maintains that the two payments it made to Oddonetto were for 25% of the 16 total granite countertops and sinks for the KOTA Project. (Doc. 147 ¶¶ 1–2.) The 17 expectation, according to KNR, was that Oddonetto would have 25% of the total materials 18 after the second payment. (Id. ¶ 2.) KNR asserts that Oddonetto informed Keener that a 19 “container from China containing all of the granite countertops and sinks was in port but 20 could not be released until full payment was made.” (Id.) But, according to KNR, in 21 October of 2019, when it wanted to check the inventory, it discovered that Oddonetto “did 22 not have any of the granite countertops . . . and [Oddonetto] did not have the money KNR 23 [had] paid [Oddonetto] to procure them.” (Id. ¶ 4.) Finally, KNR asserts that Dakota’s 24 expert has concluded that KNR committed no fraud in the transactions with Oddonetto and 25 believes that Oddonetto lied to KNR. (Id. ¶ 5.) 26 C. Oddonetto’s Controverted Facts 27 Oddonetto maintains that it provided an estimate to KNR on October 4, 2018. 28 (Doc. 159 ¶ 10.) Oddonetto asserts that the estimate established the material terms of the 1 agreement between it and KNR, and that KNR accepted those terms. (Id. ¶¶ 11–12.) 2 Oddonetto emphasizes that “[a]ccording to the terms of the contract/ estimate” between it 3 and KNR, and “before any orders are placed for any products or materials regardless of the 4 quantity, the general contractor is required to pay at least a 50 percent deposit and the 5 remaining balance to Oddonetto Granite prior to delivery of any product.” (Id. ¶ 15.) 6 Additionally, Oddonetto asserts that the estimate provided (1) “no specific timeframe for 7 delivery of the stone materials for” the KOTA Project; (2) “no requirement that all stone 8 materials had to be ordered at the time of the initial or final payment by KNR to Oddonetto 9 Granite;” and (3) “no requirement that a specific quantity or all of the stone product would 10 be ordered at one time after the payment from KNR.” (Id. ¶¶ 13–14, 20; Doc. 158 at 5.) 11 Oddonetto also maintains that the parties agreed that it could acquire the material needed 12 to perform on an as-needed basis due to its limited shop space. (Doc. 159 ¶¶ 16–18.) 13 Oddonetto also asserts that it had worked with KNR before and was never required to order 14 all of the product for a project at once. (Id. ¶¶ 21–23) 15 Oddonetto also claims that KNR made representations about the size of the KOTA 16 Project and indicated that Oddonetto should not take on any other work. (Id. ¶ 35.) 17 Oddonetto further asserts that KNR told it to stop work for the KOTA Project while KNR 18 and Dakota settled a payment dispute. (Id. ¶¶ 38–39.) According to Oddonetto, KNR’s 19 stop-work order prevented it from “performing its subcontract with KNR, including being 20 able to finish the product order, fabricate the countertops and sinks, or complete the 21 installation.” (Id. ¶ 40.) Oddonetto maintains that because the KOTA Project was the only 22 project that it was working on, it had to use “some of the funds paid by KNR . . . to support 23 [its] business operations.” (Id. ¶¶ 41–42.) Oddonetto also maintains that it “was always 24 able to perform and willing to complete the work that it had been paid for, including 25 ordering any additional necessary product to complete the work.” (Id. ¶ 43.) Despite this, 26 Oddonetto claims representatives for KNR and Dakota, told it to wait until KNR and 27 Dakota “resolved their dispute. . . .” (Id. ¶¶ 48–49.) Finally, Oddonetto asserts that KNR 28 falsely represented itself as a licensed contractor because at “the time it entered into the 1 Construction Contracts with Plaintiffs, KNR was not a licensed contractor in Arizona with 2 the Arizona Registrar of Contractors.” (Id. ¶¶ 2–3.) 3 II. LEGAL STANDARD 4 Summary judgment is appropriate if the evidence, viewed in the light most favorable 5 to the nonmoving party, here Oddonetto, demonstrates “that there is no genuine dispute as 6 to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. 7 Civ. P. 56(a). A genuine issue of material fact exists if “the evidence is such that a 8 reasonable jury could return a verdict for the nonmoving party,” and material facts are 9 those “that might affect the outcome of the suit under the governing law.” Anderson v. 10 Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). At the summary judgment stage, “[t]he 11 evidence of the non-movant is to be believed, and all justifiable inferences are to be drawn 12 in [its] favor.” Id. at 255; see also Jesinger v. Nev. Fed. Credit Union, 24 F.3d 1127, 1131 13 (9th Cir. 1994) (“The court must not weigh the evidence or determine the truth of the 14 matters asserted but only determine whether there is a genuine issue for trial.”). That said, 15 “[w]hen opposing parties tell two different stories, one of which is blatantly contradicted 16 by the record, so that no reasonable jury could believe it, a court should not adopt that 17 version of the facts for purposes of ruling on a motion for summary judgment.” Scott v.

Free access — add to your briefcase to read the full text and ask questions with AI

SPUS8 Dakota LP v. KNR Contractors LLC, (D. Ariz. 2022).

SPUS8 Dakota LP v. KNR Contractors LLC (SPUS8 Dakota LP v. KNR Contractors LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
MDY Industries, LLC v. Blizzard Entertainment, Inc.
629 F.3d 928 (Ninth Circuit, 2010)
Ralph and Carolee Thomas v. Montelucia Villas
302 P.3d 617 (Arizona Supreme Court, 2013)
Aesthetic Property Maintenance, Inc. v. Capitol Indemnity Corp.
900 P.2d 1210 (Arizona Supreme Court, 1995)
Taylor v. State Farm Mutual Automobile Insurance
913 P.2d 1092 (Arizona Supreme Court, 1996)
Clark v. Compania Ganadera De Cananea, S. A.
385 P.2d 691 (Arizona Supreme Court, 1963)
Graham v. Asbury
540 P.2d 656 (Arizona Supreme Court, 1975)
Comerica Bank v. MAHMOODI
229 P.3d 1031 (Court of Appeals of Arizona, 2010)
Arizona Tile, L.L.C. v. Berger
224 P.3d 988 (Court of Appeals of Arizona, 2010)
Wang Electric, Inc. v. Smoke Tree Resort, LLC
283 P.3d 45 (Court of Appeals of Arizona, 2012)
Next Gen Capital, LLC v. Consumer Lending Associates LLC
316 P.3d 598 (Court of Appeals of Arizona, 2013)
Day v. LSI Corp.
174 F. Supp. 3d 1130 (D. Arizona, 2016)