Sprintcom, Inc. v. Puerto Rico Regulations & Permits Administration

553 F. Supp. 2d 87, 2008 U.S. Dist. LEXIS 40415
CourtDistrict Court, D. Puerto Rico
DecidedFebruary 8, 2008
DocketCivil 07-1026 (JP)
StatusPublished
Cited by4 cases

This text of 553 F. Supp. 2d 87 (Sprintcom, Inc. v. Puerto Rico Regulations & Permits Administration) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sprintcom, Inc. v. Puerto Rico Regulations & Permits Administration, 553 F. Supp. 2d 87, 2008 U.S. Dist. LEXIS 40415 (prd 2008).

Opinion

OPINION AND ORDER

JAIME PIERAS, JR., Senior District Judge.

The Court has before it Defendant Puer-to Rico Regulations and Permits Administration of the Commonwealth of Puerto Rico’s (“Defendant” or “ARPE”) motion for summary judgment (Nos. 47, 48) and Plaintiff SPRINTCOM, Inc.’s (“Plaintiff’ or “Sprint”) motion for judgment (No. 49). Also before the Court are the parties’ respective responses thereto (Nos. 55, 54). For the reasons stated herein, the Court grants Plaintiff Sprint’s motion for judgment (No. 49).

Plaintiff Sprint brought the instant suit against Defendant ARPE for its decision to deny Sprint’s application for a preliminary plan approval to install a telecommunications facility on the roof of a three-story building located in the town of Isabe-la, Puerto Rico. Plaintiff alleges that the telecommunications facility is necessary to provide seamless, reliable wireless telephone and other communication services to individuals living, working or traveling in and around Isabela. In its motion for judgment, Plaintiff argues that Defendant’s denial of the application is a violation of the Federal Telecommunications Act (“TCA”), 47 U.S.C. Section 332(c)(7)(B)(i)(II), because the denial was based on the citizens’ concerns about alleged adverse environmental and health effects of radio frequency emissions. Sprint also argues that Defendant ARPE has violated Section 2151 of the Puerto *89 Rico Uniform Administrativa Procedure Act (“LPAU”) which grants all parties in an administrative case “the right to have the decision based on the record of the case.” P.R. Laws Ann. tit. 3, § 2151 et seq. Sprint requests injunctive and declaratory relief ordering Defendant to grant the application and issue all necessary permits to allow the installation and operation of the facility.

In their motion for summary judgment, Defendant ARPE argues that ARPE’s decision to deny Plaintiff Sprint’s application was based on substantial evidence contained in the administrative record, and therefore is in compliance with relevant federal and state law.

I. PROCEDURAL HISTORY

An Initial Scheduling Conference was held before the Court on August 15, 2007, wherein the parties agreed that, rather than proceeding to trial, the instant dispute would be decided through dispositive motions. This position was reiterated by all parties hereto in the Further Scheduling Conference held before the Court on November 9, 2007.

On September 11, 2007, Plaintiff asked for the voluntary dismissal of Counts II and III of the complaint, which respectively claimed effective prohibition of service and unreasonable discrimination. The motion was granted on September 21, 2007 (No. 42). Presently, the only issues before the Court are whether ARPE’s decision to deny Sprint’s application was based on substantial evidence emanating from the administrative record, and whether the decision was based on the record of the case as required by the LPAU.

On December 7, 2007, the parties filed respective motions for summary judgment, which are the subject of this Opinion.

II. MATERIAL FACTS NOT IN GENUINE DISPUTE

The following uncontested facts were included in the parties’ cross-motions for summary judgment, and were either agreed upon, or were properly supported and not sufficiently opposed:

A. Sprint executed a lease agreement with Eric Antonio Velasco-Alvarez, owner of the building where a telecommunications facility (the “Facility”) is to be installed, on October 13, 2005.
B. In late 2005 or early 2006, Sprint submitted an application for preliminary plan approval (the “Preliminary Plan”) to ARPE.
C. As part of its application, Sprint argued that the Facility complied with both Law 89 of June 6, 2000, P.R. Laws Ann. tit. 27, Section 321 et seq., known as the Puerto Rico Construction, Installation and Location of the Telecommunications Towers Act (“Law 89”), and the Planning Board’s (the “Board”) Regulation for Telecommunications Projects (“Regulation 26”).
D. Also in support of its application, Sprint argued that if ARPE were to determine that a variance was required because the Facility would be installed in a building of less than five stories, Sprint had complied with all the requirements for the granting of such variance pursuant to Regulation 26.
E. Sprint obtained an endorsement from the Puerto Rico Telecommunications Regulatory Board which was issued on June 28, 2006.
F. Sprint obtained a sworn statement, executed by Sakol Ortiz, supervisor of Sprint’s Radio-Frequency Engineering Department, stating that *90 Sprint had researched several locations before determining where to build the Facility. The resolution further stated that Sprint met all the requirements pleaded.
G. On September 11, 2006, some residents sent a letter to the Administrator of the Permits and Regulations Administration, Engineer Luis A. Vélez-Roche, stating their opposition to the installation of the antenna in the building in Isabela. They stated that the installation of the antenna could provoke health and environmental hazards in the area.
H. On the week of October 4, 2006, the notices for the public hearing (the “Hearing”) to be held in Isabela on October 24, 2006, were published in “Primera Hora” and “El Norte.”
I. After several continuances, and having duly notified the neighbors as required by Regulation 26 and Law 89, the Hearing to consider Sprint’s request for approval of the Preliminary Plan was held on October 24, 2006 in the Justo Méndez Cabrera Amphitheater in Isabela.
J. Thirty-two people attended the Hearing.
K. During the Hearing, Sprint argued through the testimony of Engineer José Santiago-Veray that the Facility complied with all applicable requirements of Law 89 and Regulation 26, and that, in the event that the Administration determined that a variance was required, Sprint had complied with all the requirements for a variance included in Section 3.04 of Regulation 26.
L. Residents of the area opposed the installation of the antenna, basing their allegations on possible health risks, including allegations that the antennas would interfere with the functioning of pace makers, would attract lightning, and would cause skin conditions.
M. In that same Hearing, the Mayor of the Municipality of Isabela, Carlos O. Delgado-Altieri, delivered an address stating the reasons why he opposed the installation and construction of the antenna. He stated that there is a proliferation of antennas in densely populated areas, and that allowing the installation of this antenna would hinder the progress that the Municipality has been experiencing for the past four years and would advance the economic interests of a single company.
N.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
553 F. Supp. 2d 87, 2008 U.S. Dist. LEXIS 40415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sprintcom-inc-v-puerto-rico-regulations-permits-administration-prd-2008.