Spivey & Self, Inc. v. Highview Farms, Inc.

431 S.E.2d 535, 110 N.C. App. 719, 1993 N.C. App. LEXIS 670
CourtCourt of Appeals of North Carolina
DecidedJuly 6, 1993
Docket9219SC325
StatusPublished
Cited by10 cases

This text of 431 S.E.2d 535 (Spivey & Self, Inc. v. Highview Farms, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spivey & Self, Inc. v. Highview Farms, Inc., 431 S.E.2d 535, 110 N.C. App. 719, 1993 N.C. App. LEXIS 670 (N.C. Ct. App. 1993).

Opinion

GREENE, Judge.

Highview Farms, Inc., Harry Welch, Barbara Welch, Charles Welch, and Highview Farms Golf Club, Inc. (defendants), appeal from the trial court’s order granting Spivey and Self, Inc.’s (plaintiff) motion for a directed verdict on portions of plaintiff’s breach of contract claim and from the trial court’s order denying defendants’ Rule 59 motion to alter or amend the judgment. Plaintiff appeals from the trial court’s order granting defendants’ motion for a directed verdict on portions of plaintiff’s breach of contract claim and from the trial court’s denial of plaintiff’s motion for directed verdict on portions of defendants’ counterclaim for breach of contract.

*722 Plaintiff, a South Carolina corporation, and defendants entered into a contract 6 November 1989, under which plaintiff would construct an eighteen-hole golf course on land belonging to defendants. Work began on the project in November, 1989. Plaintiff left the job on 28 June 1990, and on 19 July 1990, filed a complaint against defendants, alleging defendants breached the contract in that they failed to make timely payments under the contract and seeking damages in the amount of $226,000.00.

A copy of the contract was attached to the complaint, and reflected an agreement that required plaintiff, for the sum of $1,100,000.00, to provide all labor, materials, and equipment for construction of the course according to plans and specifications drawn by defendants’ architect.

The contract called for payment to be made in ten installments as follows:

$55,000.00-When construction starts

$125,000.00-Dec. 5, 1989

$100,000.00-Jan. 5, 1990

$125,000.00-Feb. 5, 1990

$135,000.00-Mar. 5, 1990

$125,000.00-Apr. 5, 1990

$150,000.00-May 5, 1990

$150,000.00-June 5, 1990

$91,000.00-July 5, 1990

Leaving a balance of $135,000.00 which is to be paid when the sand traps are excavated and greens are planted.

A hand-written modification to the contract stated “Less 10°/o” and was followed by the initials of plaintiff’s president Hoyt Spivey (Spivey). In addition, the contract stated that plaintiff was required to implement erosion control measures.

Plaintiff’s complaint alleged that defendants had failed to make the 5 June 1990 payment, which amounted , to $135,000.00 after the deduction of ten percent, and that the 5 July 1990 payment of $91,000.00 was money retained by defendants which was also due plaintiff.

*723 Defendants answered, alleging that the June payment was withheld because plaintiff had fallen behind in its work. Defendants also counterclaimed for breach of contract, alleging that plaintiff’s failure to continue work had prevented it from completing the course prior to the 1991 growing season. Defendants claimed damages of at least $340,000.00.

Prior to trial, defendants served interrogatories on plaintiff, which were answered. Defendants also took the deposition of Spivey.

At trial, Spivey testified for plaintiff that the initial payment of $55,000.00 was made. Payments continued through May, with the last two being made late, and plaintiff continued to work on the job. The 5 June 1990 payment was never made, and should have amounted to $135,000.00 pursuant to the hand-written modification of the contract calling for defendants to retain ten percent of each payment. Spivey further testified that defendants also owed plaintiff $91,000.00, which consisted of the total amount of retainage called for in the hand-written modification of the contract. The hand-written modification of the contract was made, according to Spivey, to correct an error he had made in the original contract, in that

I normally hold or allow the owners to hold a 10°/o retainage for security to make sure I am going to do my work so I made a notation on the contract that 10% was to be deducted each month and held until July 5th as retainage. . . . [T]he $91,000.00 on July 5th in the schedule in the contract was always suppose[d] to be retainage.

Spivey also testified that Charles Welch told him prior to the time the June payment was due that defendants had run out of money and did not have funds to make the June payment. Spivey stated that plaintiff was responsible for implementing an erosion control plan pursuant to detailed engineering drawings provided by defendants. He also admitted that plaintiff was “not licensed or registered in North Carolina and . . . does not have a North Carolina [general] contractor’s license.” At the end of plaintiff’s evidence, defendants moved for a directed verdict on the grounds that plaintiff rather than defendants had breached the contract by failing to perform the work as scheduled, and that plaintiff was not entitled to recover because it was not a licensed general contractor. The motion was denied.

*724 Defendants’ evidence included testimony by Charles Welch that he did not tell Spivey that the June payment would not be made, and that he talked with Spivey several times about defendants’ concerns that work on the course was not progressing rapidly enough to meet the planting schedule and allow the course to open on time. He also testified that defendants had the money to pay plaintiff in June but did not because the work was behind schedule. Welch stated that he had negotiated the contract with Spivey, and it was his understanding that the “Less 10°/o” notation indicated that “if we paid him by the due date, we would be entitled to a discount of ten percent.” An employee of Rowan County Department of Environmental Services testified that he inspected the erosion control efforts .at the course while plaintiff was still working, and that many of the erosion controls called for in the erosion plan were not in place. Other witnesses testified that the golf course was nowhere near completion at the time plaintiff left the job, and that it would not have been possible to plant in time for the course to open in the following year.

Upon close of all evidence, plaintiff made a motion for a directed verdict for the $135,000.00 for the June payment and the $91,000.00 for retainage pursuant to Rule 50 of the North Carolina Rules of Civil Procedure, on the ground that all the evidence showed that plaintiff did not abandon the job without excuse but rather for non-payment, and for a directed verdict on defendants’ counterclaims. The trial court allowed the motion for a directed verdict on plaintiff’s claim for $135,000.00, but denied the motion as to the $91,000.00 in retainage and for defendants’ counterclaims. Also at the close of all evidence, defendants made a motion for a directed verdict on the question of plaintiff’s claim for $91,000.00 in retainage, which was allowed. Defendants made a second motion for a directed verdict on all of plaintiff’s remaining claims on the ground that plaintiff was an unlicensed general contractor and therefore not entitled to any recovery. The trial court denied the motion.

The remaining issues were submitted to the jury, which returned a verdict in favor of defendants on defendants’ counterclaim for plaintiff’s failure to install erosion controls, awarding damages of $47,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chisum v. Campagna
2019 NCBC 27 (North Carolina Business Court, 2019)
Trantham v. Michael L. Martin, Inc.
745 S.E.2d 327 (Court of Appeals of North Carolina, 2013)
Hawes v. Vandoros
2013 NCBC 31 (North Carolina Business Court, 2013)
Accelerated Framing, Inc. v. Eagle Ridge Builders, Inc.
701 S.E.2d 280 (Court of Appeals of North Carolina, 2010)
Lee v. WINGET ROAD, LLC
693 S.E.2d 684 (Court of Appeals of North Carolina, 2010)
Lato Holdings, LLC v. Bank of North Carolina
691 S.E.2d 96 (Court of Appeals of North Carolina, 2010)
Hodgson Construction, Inc. v. Howard
654 S.E.2d 7 (Court of Appeals of North Carolina, 2007)
Carrico v. Village of Sugar Mountain
114 F. Supp. 2d 422 (W.D. North Carolina, 2000)
Munn v. Munn
435 S.E.2d 74 (Court of Appeals of North Carolina, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
431 S.E.2d 535, 110 N.C. App. 719, 1993 N.C. App. LEXIS 670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spivey-self-inc-v-highview-farms-inc-ncctapp-1993.