Brady v. Fulghum

308 S.E.2d 327, 309 N.C. 580, 1983 N.C. LEXIS 1450
CourtSupreme Court of North Carolina
DecidedNovember 3, 1983
Docket286A83
StatusPublished
Cited by33 cases

This text of 308 S.E.2d 327 (Brady v. Fulghum) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brady v. Fulghum, 308 S.E.2d 327, 309 N.C. 580, 1983 N.C. LEXIS 1450 (N.C. 1983).

Opinion

*581 EXUM, Justice.

Plaintiff brought this action for monies allegedly due under a contract for construction of a private dwelling. In affirming summary judgment for defendants, the Court of Appeals concluded that plaintiff, a general contractor, had not complied “substantially” with the statutory licensing requirements. See N.C. Gen. Stat. §§ 87-1 to 87-15.2 (1981). We agree with the result reached by the Court of Appeals, but we reject the substantial compliance doctrine which that court has developed in earlier licensing cases and which formed the basis of its analysis in this case.

I.

In February 1980, plaintiff agreed with defendants by written contract to construct their house for a price of approximately $106,850. Plaintiff began construction on or about 13 March 1980. Neither during the negotiation of this contract nor when he began performance was plaintiff licensed as a general contractor as required by North Carolina law. N.C. Gen. Stat. § 87-13 (1981) (making it a misdemeanor for one to undertake work as a general contractor without having first obtained a license). See id. § 87-1 (defining anyone who undertakes to bid upon or construct a building the cost of which is $30,000 or more as a general contractor). Plaintiff was awarded his builder’s license on 22 October 1980, having passed the examination on his second attempt. At that time, he had completed two-thirds of the work on defendant’s house. Defendants paid plaintiff $104,000. Plaintiff by this action seeks an additional $2,850 on the original contract and $28,926.41 for “additions and changes” requested by defendants during construction.

From an adverse decision on defendants’ motion for summary judgment, plaintiff appealed. The North Carolina Court of Appeals affirmed. A majority of that court, after reviewing its cases which had developed the substantial compliance doctrine, concluded that plaintiff was not entitled to the benefit of the doctrine. Chief Judge Vaughn, dissenting, concluded that he was.

II.

The legislature has provided a mechanism for certification of general construction contractors. N.C. Gen. Stat. § 87-1 (1981). This process, anchored by the provision that a general contrac *582 tor’s failure to procure a license constitutes a misdemeanor, id. § 87-13, protects the public by insuring confidence and integrity within the construction industry. Builders Supply v. Midyette, 274 N.C. 264, 270, 162 S.E. 2d 507, 512-13 (1968). Although the statute does not expressly preclude an unlicensed contractor’s suit against an owner for breach of contract, Midyette held the contractor may not recover on the contract or in quantum meruit when he has ignored the protective statute.

After Midyette the Court of Appeals determined several cases, including the one at bar, in terms of whether the contractor had “substantially” complied with the licensing statutes. In Holland v. Walden, 11 N.C. App. 281, 181 S.E. 2d 197, disc. rev. denied, 279 N.C. 349, 182 S.E. 2d 581 (1971), the general contractor was not licensed at the time the contract to build defendant’s house was made nor when construction commenced some six weeks later. The contractor finally obtained a license two months after construction began and held a valid license during the remainder of the twenty-one month construction period. The Court of Appeals concluded that since the contractor held a license for 88 percent of the construction time, the contractor had “substantially complied” with the licensing statute; therefore defendants could not rely on the fact that the contractor was not licensed as a defense. Id. at 285, 181 S.E. 2d at 200.

In Barrett, Robert and Woods, Inc. v. Armi, 59 N.C. App. 134, 296 S.E. 2d 10, disc. rev. denied, 307 N.C. 269, 299 S.E. 2d 214 (1982), the contractor was duly licensed at the time the construction contract was executed. Three and a half months later the license expired and was not renewed until some eight months later. Approximately 90 percent of the work was done while the contractor was unlicensed. Nevertheless, the Court of Appeals concluded that the contractor had substantially complied with the licensing statute. Id. at 140, 296 S.E. 2d at 14. The Court of Appeals, rejecting the contractor’s contention that mere possession of a valid license at the time of contracting always constitutes substantial compliance, said,

We stated in our opinion in Construction Co. v. Anderson [5 N.C. App. 12, 168 S.E. 2d 18 (1969)] that the time of entering the contract is of great significance since that is the time when the owner must decide whether the contractor is suffi *583 ciently competent to perform the work. Nevertheless we decline to hold, and the facts of this case do not require that we decide, that mere possession of a valid license at the moment of contracting, regardless of what transpires thereafter with regard to the license, constitutes ‘substantial compliance’ with the licensing statute.
Article I of chapter 87 clearly contemplates that a contractor should be licensed at the time of contracting and during the construction period.

Id. at 139, 296 S.E. 2d at 14. The Court of Appeals found substantial compliance in Armi essentially because the contractor was licensed “at the significant moment of contracting”; the contractor’s license lapsed during construction “through inadvertence, not as a result of incompetence or disciplinary action by the licensing board; . . . [and] was renewed immediately upon . . . filing of a renewal application and fees”; and the contractor’s financial condition and construction personnel “remained unchanged during the period plaintiff was not licensed.”

The Court of Appeals analyzed the instant case in terms of whether plaintiff substantially complied with the licensing requirement. A majority of the panel concluded that because he did not have a license at the time the contract was made and “was not licensed during at least 66 percent of the construction, which comprised the major portion of the work,” plaintiff had not substantially complied with the licensing requirements of the statute. Chief Judge Vaughn dissented on the ground that under Armi substantial compliance existed. The division on the Court of Appeals in this case demonstrates that the doctrine of substantial compliance is sometimes difficult to apply. By generating skewed results, it leaves uncertain the rights of parties which tends to promote litigation. We now reject the doctrine and end its application in this state.

Generally, contracts entered into by unlicensed construction contractors, in violation of a statute passed for the protection of the public, are unenforceable by the contractor. Olsen v. Reese, 114 Utah 411, 416, 200 P. 2d 733, 736 (1948). A majority of the jurisdictions adhere to this interpretation. See Annot., 82 A.L.R. 2d 1429 (1962). Reading these statutes as being designed to protect the public from irresponsible contractors, Meridian Corp. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barr v. Holton Constr. Concepts, LLC
Court of Appeals of North Carolina, 2026
Jcg & Assocs., LLC v. Disaster Am. USA, LLC
2021 NCBC 76 (North Carolina Business Court, 2021)
Wright Constr. Servs., Inc. v. The Hard Art Studio
Court of Appeals of North Carolina, 2020
Johnson v. Starboard Ass'n, Inc.
781 S.E.2d 813 (Court of Appeals of North Carolina, 2016)
Ron Medlin Construction v. Harris
704 S.E.2d 486 (Supreme Court of North Carolina, 2010)
Signature Development, LLC v. Sandler Commercial at Union, L.L.C.
701 S.E.2d 300 (Court of Appeals of North Carolina, 2010)
Triton Industries, Inc. v. Riverwalk in Highlands, LLC
673 S.E.2d 167 (Court of Appeals of North Carolina, 2009)
Ron Medlin Construction v. Harris
658 S.E.2d 6 (Court of Appeals of North Carolina, 2008)
SHAFMAN v. DONALD LARSON, INC.
605 S.E.2d 742 (Court of Appeals of North Carolina, 2004)
Currin & Currin Construction, Inc. v. Lingerfelt
582 S.E.2d 321 (Court of Appeals of North Carolina, 2003)
Petty v. Owen
537 S.E.2d 216 (Court of Appeals of North Carolina, 2000)
Jenco v. Signature Homes, Inc.
468 S.E.2d 533 (Court of Appeals of North Carolina, 1996)
Spivey & Self, Inc. v. Highview Farms, Inc.
431 S.E.2d 535 (Court of Appeals of North Carolina, 1993)
BAKER CONST. CO., INC. v. Phillips
426 S.E.2d 679 (Supreme Court of North Carolina, 1993)
Hall v. Simmons
407 S.E.2d 816 (Supreme Court of North Carolina, 1991)
301 East Seventh Street Ltd. Partnership v. Gellman Corp.
124 B.R. 687 (W.D. North Carolina, 1991)
Hawkins v. Holland
388 S.E.2d 221 (Court of Appeals of North Carolina, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
308 S.E.2d 327, 309 N.C. 580, 1983 N.C. LEXIS 1450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brady-v-fulghum-nc-1983.