Wright Constr. Servs., Inc. v. The Hard Art Studio

CourtCourt of Appeals of North Carolina
DecidedDecember 31, 2020
Docket19-1089
StatusPublished

This text of Wright Constr. Servs., Inc. v. The Hard Art Studio (Wright Constr. Servs., Inc. v. The Hard Art Studio) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wright Constr. Servs., Inc. v. The Hard Art Studio, (N.C. Ct. App. 2020).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

No. COA19-1089

Filed: 31 December 2020

Wake County, No. 18-CVS-5113

WRIGHT CONSTRUCTION SERVICES, INC., Plaintiff,

v.

THE HARD ART STUDIO, PLLC, GEORGE W. CARTER, JR., COLLINS STRUCTURAL CONSULTING, PLLC, and SCOTT A. COLLINS, Defendants.

Appeal by plaintiff from order entered 19 June 2019 by Judge G. Bryan Collins,

Jr., in Wake County Superior Court. Heard in the Court of Appeals 20 October 2020.

Poyner Spruill LLP, by Matthew C. Bouchard and Benjamin T. Buskirk, for plaintiff-appellant.

Gallivan, White & Boyd, P.A., by James M. Dedman, IV, and Tyler L. Martin, for defendants-appellees The Hard Art Studio, PLLC and George W. Carter, Jr.

Allen, Moore & Rogers, LLP, by Joseph C. Moore, III, and Warren Hynson, for defendants-appellees Collins Structural Consulting, PLLC and Scott A. Collins.

DIETZ, Judge.

In North Carolina, architects and engineers performing work on a construction

project owe a duty of care to those who reasonably rely on their work, including the

builder on the project. This duty applies even if the architect was hired by the

property owner and has no other business relationship with the builder. An architect

who breaches this duty—for example, by failing to exercise due care when developing WRIGHT CONSTR. SERVS., INC. V. THE HARD ART STUDIO, PLLC

Opinion of the Court

an architectural plan—can be sued for negligence by the builder.

The plaintiff in this case is a builder relying on this negligence claim to sue a

group of architects and engineers who worked on a failed construction project. Those

defendants responded by asserting what is called the “licensure defense”—a legal

defense stemming from a state law requiring builders to obtain a general contracting

license before bidding on any project costing $30,000 or more. The licensure defense

prevents a builder from recovering under a construction contract if the builder failed

to timely secure the required license.

As explained below, the licensure defense does not apply to these negligence

claims. These claims are not contract claims masquerading as tort claims. They exist

in our jurisprudence because of the special duties imposed on architects and

engineers. Those duties arise because others in the construction industry rely on the

knowledge and skill that only these professionals possess. The purpose of the

licensure defense—protecting the public from incompetent construction work—would

not be served, and indeed would be undermined, if the defense barred claims against

architects and engineers who were negligent in their professional work.

We therefore hold that, because of the importance of ensuring architects and

engineers exercise due care in their respective professions, a builder’s claims for

negligence against an architect or engineer for deficient professional work on a

construction project are not barred by the builder’s failure to secure a general

-2- WRIGHT CONSTR. SERVS., INC. V. THE HARD ART STUDIO, PLLC

contracting license before bidding on the project. Accordingly, we reverse the trial

court’s entry of summary judgment in this case and remand for further proceedings.

Facts and Procedural History

In 2014, Hillsborough Lofts, LLC developed plans for a mixed-use retail and

student housing complex in Raleigh. Hillsborough Lofts hired Olive Architecture as

the architect for the project. Olive Architecture contracted with Defendants Collins

Structural Consulting and Scott A. Collins to provide structural engineering work

and other services. Hillsborough Lofts later directed Olive Architecture to solicit bids

for a general contractor to take over the project.

Plaintiff Wright Construction Services, Inc. submitted a bid for the project.

During the initial call meeting, Hillsborough Lofts explained that it needed to

complete the project by August 2015. Wright Construction indicated that it could

complete the work by that date but also informed Hillsborough Lofts that it was not

yet licensed to engage in general contracting in North Carolina. Nevertheless,

recognizing the tight timeline for the project and corresponding construction loans,

the parties signed a contract before Wright Construction had a general contracting

license. The government issued Wright Construction an unlimited general

contracting license a few months later.

In May 2015, Hillsborough Lofts terminated Olive Architecture for failure to

substantially perform the terms of the parties’ contract and hired Defendant The

-3- WRIGHT CONSTR. SERVS., INC. V. THE HARD ART STUDIO, PLLC

Hard Art Studio, PLLC to take over. As with Olive Architecture before it, Hard Art

Studio entered into a contract with Collins Structural Consulting for structural

engineering and other services.

Both before and after Hillsborough Lofts hired Hard Art Studio, the project

was plagued by delays, including problems with the construction set of drawings, the

unexpected discovery of an underground storage tank in the building footprint, and

issues with obtaining constructible designs for shaft walls and shear walls.

On 26 August 2015, Hard Art Studio acknowledged numerous design issues

that were preventing Wright Construction from completing construction. The firm

made a “strong recommendation that we stop work until ALL the design issues are

worked out or at a minimum extend the schedule to reasonably address the issues

noted.” Later that year, Hillsborough Lofts terminated Wright Construction in a

letter explaining that Wright Construction failed to complete the work on time.

Hillsborough Lofts and Wright Construction then brought numerous claims

and counterclaims against each other in an arbitration proceeding. The defendants

in this case—Hard Art Studio, George Carter, Collins Structural Consulting, and

Scott Collins—were not named in that arbitration. In August 2017, the arbitrators

found that Hillsborough Lofts materially breached the contract by failing to provide

Wright Construction with a constructible design, by failing to respond to shop

drawings and requests for information, and by interfering with Wright Construction’s

-4- WRIGHT CONSTR. SERVS., INC. V. THE HARD ART STUDIO, PLLC

work on the project. In November 2018, the arbitrators awarded Wright Construction

$1,564,668.32 in damages, and the Wake County Superior Court later entered a

judgment confirming that award.

In April 2018, Wright Construction brought this negligence action, alleging

that Hard Art Studio, George Carter, Collins Structural Consulting, and Scott Collins

breached professional duties of care they owed as architects or structural engineers.

The defendants later moved for summary judgment, arguing that the claims were

barred by Wright Construction’s failure to obtain a general contracting license before

beginning work on the project.

After a hearing, the trial court granted summary judgment in favor of all

defendants and dismissed Wright Construction’s complaint. Wright Construction

timely appealed.

Analysis

Wright Construction appeals the trial court’s entry of summary judgment in

favor of all defendants. We review this issue de novo, examining whether the evidence

forecast by the parties shows there is “no genuine issue as to any material fact and

that any party is entitled to a judgment as a matter of law.” N.C. Gen. Stat. § 1A-1,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brady v. Fulghum
308 S.E.2d 327 (Supreme Court of North Carolina, 1983)
Davidson & Jones, Inc. v. County of New Hanover
255 S.E.2d 580 (Court of Appeals of North Carolina, 1979)
Shoffner Industries, Inc. v. W. B. Lloyd Construction Co.
257 S.E.2d 50 (Court of Appeals of North Carolina, 1979)
Bryan Builders Supply v. Midyette
162 S.E.2d 507 (Supreme Court of North Carolina, 1968)
In Re the Will of Jones
669 S.E.2d 572 (Supreme Court of North Carolina, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Wright Constr. Servs., Inc. v. The Hard Art Studio, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wright-constr-servs-inc-v-the-hard-art-studio-ncctapp-2020.