Accelerated Framing, Inc. v. Eagle Ridge Builders, Inc.

701 S.E.2d 280, 207 N.C. App. 722, 2010 N.C. App. LEXIS 2016
CourtCourt of Appeals of North Carolina
DecidedNovember 2, 2010
DocketCOA09-1399
StatusPublished
Cited by2 cases

This text of 701 S.E.2d 280 (Accelerated Framing, Inc. v. Eagle Ridge Builders, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Accelerated Framing, Inc. v. Eagle Ridge Builders, Inc., 701 S.E.2d 280, 207 N.C. App. 722, 2010 N.C. App. LEXIS 2016 (N.C. Ct. App. 2010).

Opinion

GEER, Judge.

This appeal arises out of a dispute between plaintiff Accelerated Framing, Inc. and defendant Eagle Ridge Builders, Inc. over a contract to perform carpentry work on property located in Banner Elk, North Carolina. Eagle Ridge appeals from the trial court’s award of damages to Accelerated Framing on its breach of contract claim, contending primarily that Accelerated Framing is not the real party in interest. The parties, however, stipulated at trial that they wished to consider the contract as being between Accelerated Framing and Eagle Ridge. Because Eagle Ridge never filed a motion to set aside that stipulation, it is binding and Accelerated Framing is the real party in interest.

Facts

On 12 June 2008, Accelerated Framing brought a breach of contract claim against Eagle Ridge, seeking payment due for carpentry work Accelerated Framing performed on a log cabin that was being built by Eagle Ridge. Accelerated Framing also brought claims for a mechanic’s lien and for recovery based on quantum meruit. Eagle Ridge subsequently counterclaimed for breach of contract. On 26 May 2009, a bench trial was held in Watauga County Superior Court. On 5 June 2009, the trial court entered an order making the following findings of fact.

On or about 29 January 2008, Accelerated Framing and Eagle Ridge entered into a written contract agreeing that Eagle Ridge would pay Accelerated Framing $14,100.00 in weekly draws for framing work on a log cabin. Accelerated Framing substantially completed the work under that contract and was paid $12,600.00.

On 7 May 2008, the parties entered into an oral contract in which Eagle Ridge agreed to pay Accelerated Framing $20,000.00 to complete the remaining work on the cabin. Under that oral contract, Accelerated Framing incurred costs for four weeks of work spent finishing and sanding the interior of the cabin. Eagle Ridge knew that *724 Accelerated Framing was working on the property at that time and provided the supplies needed to complete the work. Those supplies were stored in Accelerated Framing’s storage trailer on the property.

Before Accelerated Framing could fully complete the work on the property, Eagle Ridge told Accelerated Framing not to return to the job site. The trial court found that “photographs taken on May 15 and introduced by the Plaintiff for illustrative purposes show the condition of the property and the work completed as of the time that the Plaintiff had substantially completed its work.” The trial court found that, as a result of Eagle Ridge’s ordering Accelerated Framing off the job site before the work was completed, Accelerated Framing suffered damages in the amount of $1,500.00 under the written contract and damages in the amount of $12,140.00 under the oral contract.

On the other hand, following the termination of the contract, Eagle Ridge incurred costs to complete some of the work not performed by Accelerated Framing under the oral contract. The trial court determined that, based on those costs, Eagle Ridge was entitled to an offset of $2,050.00 to be applied against Accelerated Framing’s damages. The trial court then awarded Accelerated Framing damages of $11,590.00 plus interest at the legal rate running from 17 June 2008, with each party to bear its own costs. Eagle Ridge timely appealed to this Court.

I

Eagle Ridge first contends that the trial court lacked subject matter jurisdiction over this action. Eagle Ridge asserts that Accelerated Framing was not a party to the contract because the contract was signed by Eagle Ridge and by David Gentry, in his individual capacity, even though he is also the President and owner of Accelerated Framing. Therefore, according to Eagle Ridge, Accelerated Framing was not the real party in interest and lacked standing to sue.

At trial, however, the parties stipulated that they wished to proceed as if the contract were between Accelerated Framing and Eagle Ridge. Plaintiffs counsel stated, without any objection by defendant: “We have agreed that although Mr. Gentry personally is on this contract[,] [w]e are going to consider it to be through this corporation. They are responsible for all liabilities and rights under that contract.”

Eagle Ridge contends that the parties’ stipulation was ineffective because subject matter jurisdiction cannot be waived. See Reece v. *725 Forga, 138 N.C. App. 703, 704, 531 S.E.2d 881, 882 (“A party may not waive jurisdiction, and a court has inherent power to inquire into, and determine, whether it has jurisdiction and to dismiss an action ex mero motu when subject matter jurisdiction is lacking.” (internal citation omitted)), disc. review denied, 352 N.C. 676, 545 S.E.2d 428 (2000). Eagle Ridge’s sole basis for arguing that the trial court lacked subject matter jurisdiction is that Accelerated Framing, which did not sign the contract, is not the real party in interest.

Eagle Ridge has, however, overlooked Rule 17(a) of the North Carolina Rules of Civil Procedure, which provides:

No action shall be dismissed on the ground that it is not prosecuted in the name of the real party in interest until a reasonable time has been allowed after objection for ratification of commencement of the action by, or joinder or substitution of, the real party in interest; and such ratification, joinder, or substitution shall have the same effect as if the action had been commenced in the name of the real party in interest.

In Lawrence v. Wetherington, 108 N.C. App. 543, 547, 423 S.E.2d 829, 831 (1993), this Court, applying Rule 17, held that a real party in interest can ratify an action by stipulation. The plaintiffs, Russell and Evelyn Lawrence, doing business as Carolina Vinyl Siding, brought a breach of contract action against the defendants. Id. at 545, 423 S.E.2d at 830. When the defendants argued at trial that Carolina Vinyl Siding, the corporation with which they signed the contract, was a necessary and proper party, the parties stipulated that the plaintiffs’ participation in the lawsuit would be binding on Carolina Vinyl Siding. Id. at 546-57, 423 S.E.2d at 831. The plaintiffs’ attorney stated:

“We would like to stipulate now that Russell Lawrence and Evelyn Lawrence, whether they are a corporation or individual doing business as that, they would all be bound by the decision in this case and that includes whether it is a corporation called . . . ‘Carolina Vinyl Siding and Home Improvements, Inc.,’ or ‘Carolina Siding, Inc.’ or ‘Russell Lawrence and Evelyn Lawrence doing business as Carolina Siding.’ ”

Id. at 547, 423 S.E.2d at 831.

On appeal, the defendants in Lawrence contended that, because the plaintiffs’ corporation was a necessary party to the case, no valid judgment could be.entered against the defendants arising out of a contract between them and the corporation without the corporation *726 being joined in the action. Id. at 546, 423 S.E.2d at 831.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King Fa, LLC v. Ming Xen Chen
788 S.E.2d 646 (Court of Appeals of North Carolina, 2016)
Micro Capital Investors, Inc. v. Broyhill Furniture Industries, Inc.
728 S.E.2d 376 (Court of Appeals of North Carolina, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
701 S.E.2d 280, 207 N.C. App. 722, 2010 N.C. App. LEXIS 2016, Counsel Stack Legal Research, https://law.counselstack.com/opinion/accelerated-framing-inc-v-eagle-ridge-builders-inc-ncctapp-2010.